No. 4 deformed GFRP reinforcement, ODOT 509E30020
Low bidders on ODOT contracts carried a median of $1.73 per FT for this item, from 05 NOV 2020 to 12 OCT 2023, across 66 low bids. Half of all 260 bids fell between $1.52 and $2.00.
- Owner
- Ohio DOT
- Item
- 509E30020
- Unit
- FT
- Data through
- 12 NOV 2026
ODOT prints this item as “NO. 4 GFRP DEFORMED BARS”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 1 | 1 | $2.39 | 5 | $2.39 |
| 2021 | 14 | 22 | $1.46 | 105 | $1.60 |
| 2022 | 10 | 12 | $1.75 | 41 | $2.00 |
| 2023 | 19 | 31 | $1.80 | 109 | $1.90 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| SUM | 12 | $1.88 | 68 | $1.90 |
| FRA | 10 | $1.50 | 21 | $1.60 |
| BUT | 3 | $1.15 | 16 | $1.91 |
| LUC | 4 | $1.70 | 15 | $1.75 |
| WAR | 4 | $1.40 | 15 | $1.68 |
| CUY | 4 | $1.80 | 11 | $2.15 |
| District 8 | 3 | $1.50 | 10 | $1.98 |
| HAM | 3 | $2.35 | 8 | $1.75 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 110 to 3,764 | 16 | $2.00 |
| 4,171 to 6,991 | 17 | $1.48 |
| 7,188 to 10,474 | 16 | $1.75 |
| 10,642 to 68,146 | 17 | $1.61 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Kokosing Construction Company Inc | 18 | 13 (72%) |
| Shelly & Sands Inc | 31 | 10 (32%) |
| Great Lakes Construction Co | 16 | 8 (50%) |
| Complete General Construction Company | 30 | 6 (20%) |
| Shelly Company | 10 | 6 (60%) |
| Eagle Bridge Co | 13 | 4 (31%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 OCT 2023 | 230494 | LAK | 8,763 | $2.00 | $2.00 | 3 | J D Williamson Construction Co Inc | ODOT |
| 28 SEP 2023 | 230479 | RIC | 4,826 | $2.25 | $2.44 | 8 | Black Horse Bridge Construction Inc | ODOT |
| 14 SEP 2023 | 230447 | FRA | 9,169 | $1.80 | $1.73 | 5 | Ruhlin Company | ODOT |
| 31 AUG 2023 | 230437 | SUM | 2,913 | $2.00 | $2.00 | 5 | Kenmore Construction Co Inc | ODOT |
| 31 AUG 2023 | 230437 | SUM | 2,913 | $2.00 | $2.00 | 5 | Kenmore Construction Co Inc | ODOT |
| 31 AUG 2023 | 230437 | SUM | 2,821 | $2.00 | $2.00 | 5 | Kenmore Construction Co Inc | ODOT |
| 31 AUG 2023 | 230437 | SUM | 2,821 | $2.00 | $2.00 | 5 | Kenmore Construction Co Inc | ODOT |
| 31 AUG 2023 | 230437 | SUM | 3,238 | $2.00 | $2.00 | 5 | Kenmore Construction Co Inc | ODOT |
| 31 AUG 2023 | 230437 | SUM | 3,407 | $2.00 | $2.00 | 5 | Kenmore Construction Co Inc | ODOT |
| 10 AUG 2023 | 230420 | PRE | 10,474 | $1.75 | $1.69 | 2 | Eagle Bridge Co | ODOT |
| 27 JUL 2023 | 230400 | JEF | 4,562 | $1.82 | $2.85 | 3 | Shelly & Sands Inc | ODOT |
| 25 MAY 2023 | 230321 | FRA | 5,346 | $1.40 | $1.40 | 1 | Kokosing Construction Company Inc | ODOT |
| 25 MAY 2023 | 230321 | FRA | 5,521 | $1.40 | $1.40 | 1 | Kokosing Construction Company Inc | ODOT |
| 25 MAY 2023 | 230321 | FRA | 3,713 | $1.40 | $1.40 | 1 | Kokosing Construction Company Inc | ODOT |
| 25 MAY 2023 | 230321 | FRA | 3,764 | $1.40 | $1.40 | 1 | Kokosing Construction Company Inc | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.