TDOT contract CN261005 bid tabulation
The repair of the bridges on u.s. 321 (s.r. 73) over tellico lake and s.r. 444 (l.m. 8.72). Let by Tennessee DOT on February 6, 2026, Loudon County. 5 bids received; low bid $5,082,040 by Mid-State Construction Company, Inc..
- Owner
- Tennessee DOT
- Letting
- 06 FEB 2026
- Pay items
- 40
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Mid-State Construction Company, Inc. | $5,082,040 | Low |
| 2 | Bell & Associates Construction, LLC | $5,500,751 | +8.0% |
| 3 | Southern Constructors, Inc. | $5,540,320 | +9.0% |
| 4 | Olympus Painting Contractors, Inc. | $5,816,960 | +14% |
| 5 | Southern Road & Bridge, LLC | $7,574,967 | +49% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Mid-State Construction Company, Inc. | 2. Bell & Associates Construction, LLC | 3. Southern Constructors, Inc. | 4. Olympus Painting Contractors, Inc. | 5. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removal and disposal of brush & trees (201-07.01) | LS | 1 | $17,037 | $10,000 | $60,000 | $15,000 | $27,000 |
| 2 | Removal of asbestos (202-01.02) | LS | 1 | $96,747 | $91,000 | $110,000 | $275,000 | $967,000 |
| 3 | Asphalt concrete mix (PG64-22) (BPMB-HM) grading B-M2 (307-01.08) | TON | 802 | $187.80 | $165.00 | $190.00 | $198.00 | $272.00 |
| 4 | Bituminous material for tack coat (TC) (403-01) | TON | 6 | $1,138.20 | $1,000.00 | $1,100.00 | $1,200.00 | $1,500.00 |
| 5 | Acs mix(PG64-22) grading D (411-01.10) | TON | 470 | $244.71 | $215.00 | $250.00 | $258.00 | $322.00 |
| 6 | Cold planing bituminous pavement (415-01.02) | SY | 778 | $27.32 | $29.00 | $30.00 | $28.00 | $36.00 |
| 7 | Jacking steel spans (602-10.19) | LS | 1 | $353,484 | $324,000 | $520,000 | $500,000 | $175,000 |
| 8 | Structural steel weld repair (602-10.22) | EACH | 2 | $6,542.56 | $10,000 | $2,000.00 | $25,000 | $7,500.00 |
| 9 | Bearing device (abutment no. 1 & 2, pier no. 1 & 4) (602-10.61) | EACH | 16 | $21,812 | $50,000 | $28,000 | $14,000 | $71,000 |
| 10 | Heat straightening (602-10.81) | LS | 1 | $65,491 | $100,000 | $45,000 | $225,000 | $222,000 |
| 11 | Repainting existing steel structures (bridge no. 53-SR73-8.72 left) (603-02.01) | LS | 1 | $950,248 | $1,050,000 | $1,150,000 | $1,221,450 | $1,210,000 |
| 12 | Containment & disposal of waste(bridge no. 53-SR73-8.72 left) (603-05.20) | LS | 1 | $635,159 | $450,000 | $530,000 | $657,000 | $600,012 |
| 13 | Applied texture finish (existing structures) (604-04.02) | SY | 3,153 | $30.73 | $29.00 | $25.00 | $27.00 | $81.00 |
| 14 | Concrete (604-10.05) | SF | 238 | $393.18 | $300.00 | $460.00 | $400.00 | $392.00 |
| 15 | Remove existing wearing surface (604-10.14) | LS | 1 | $73,983 | $75,000 | $80,000 | $75,000 | $97,500 |
| 16 | Bridge deck repairs (partial depth of slab) (604-10.50) | SY | 115 | $393.20 | $300.00 | $550.00 | $1,000.00 | $775.00 |
| 17 | Concrete repairs (604-10.54) | SF | 238 | $966.57 | $300.00 | $460.00 | $400.00 | $392.00 |
| 18 | Concrete (foundation repairs) (604-10.55) | CY | 6 | $2,291.08 | $3,500.00 | $2,400.00 | $4,500.00 | $6,200.00 |
| 19 | Epoxy injection (injection) (604-10.58) | GAL | 6 | $85.37 | $80.00 | $220.00 | $120.00 | $275.00 |
| 20 | Expansion joint repairs (modular type) (604-10.60) | LF | 100 | $3,422.61 | $5,000.00 | $4,100.00 | $4,700.00 | $4,500.00 |
| 21 | Epoxy injection repair (complete and in place) (604-10.62) | LF | 124 | $96.75 | $250.00 | $210.00 | $150.00 | $150.00 |
| 22 | Bridge deck sealant (617-01) | SY | 5,700 | $39.24 | $42.00 | $35.00 | $35.00 | $36.50 |
| 23 | Chain-link fence (bridges) (707-07.01) | SF | 1,600 | $34.15 | $33.00 | $35.00 | $34.00 | $36.00 |
| 24 | Traffic control (712-01) | LS | 1 | $118,062 | $25,000 | $70,000 | $155,000 | $85,000 |
| 25 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 2,760 | $54.18 | $90.00 | $62.00 | $33.18 | $58.00 |
| 26 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 2 | $8,195.04 | $8,000.00 | $9,000.00 | $8,300.00 | $17,700 |
| 27 | Flexible drums (channelizing) (712-04.01) | EACH | 369 | $54.63 | $55.00 | $60.00 | $52.00 | $72.00 |
| 28 | Barrier rail delineator (712-04.50) | EACH | 165 | $5.69 | $5.00 | $38.00 | $10.00 | $28.00 |
| 29 | Warning lights (type A) (712-05.01) | EACH | 13 | $28.46 | $28.00 | $30.00 | $40.00 | $37.00 |
| 30 | Signs (construction) (712-06) | SF | 852 | $8.08 | $10.00 | $15.00 | $15.00 | $11.00 |
| 31 | Temporary barricades (type II) (712-07.02) | LF | 587 | $1.14 | $1.00 | $2.00 | $3.80 | $2.00 |
| 32 | Temporary barricades (type III) (712-07.03) | LF | 60 | $22.19 | $22.00 | $25.00 | $30.00 | $30.00 |
| 33 | Arrow board (type C) (712-08.03) | EACH | 2 | $1,365.84 | $1,375.00 | $3,200.00 | $1,700.00 | $1,800.00 |
| 34 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 27,094 | $3.53 | $3.10 | $4.00 | $3.75 | $6.33 |
| 35 | Removable black-out tape (8IN) (712-09.31) | LF | 13,138.75 | $4.84 | $4.25 | $4.00 | $5.10 | $6.15 |
| 36 | Changeable message sign unit (713-16.01) | EACH | 3 | $6,601.56 | $6,500.00 | $9,000.00 | $7,000.00 | $8,700.00 |
| 37 | Navigational lighting (714-16.01) | LS | 1 | $102,438 | $100,000 | $200,000 | $195,241 | $217,500 |
| 38 | Temporary navigational lighting (714-16.05) | LS | 1 | $48,943 | $50,000 | $55,000 | $54,122 | $75,000 |
| 39 | Enhanced flatline thermo PVMT MRKNG (6IN line) (716-12.02) | LM | 1 | $10,244 | $10,000 | $12,500 | $11,000 | $15,750 |
| 40 | Mobilization (717-01) | LS | 1 | $463,817 | $562,000 | $460,000 | $350,000 | $500,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of February 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.