TDOT contract CN261069 bid tabulation
The rehabilitation of the bridge on i-40 over the pigeon river and hartford road near l.m. 15.05. Let by Tennessee DOT on October 2, 2026, Cocke County. 4 bids received; low bid $2,042,519 by Whaley Construction, LLC.
- Owner
- Tennessee DOT
- Letting
- 02 OCT 2026
- Pay items
- 24
- Data through
- 02 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Whaley Construction, LLC | $2,042,519 | Low |
| 2 | Charles Blalock & Sons, Inc. | $2,287,100 | +12% |
| 3 | W.G. Harrell Construction LLC | $2,291,481 | +12% |
| 4 | Jones Bros. Contractors, LLC | $2,361,949 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Whaley Construction, LLC | 2. Charles Blalock & Sons, Inc. | 3. W.G. Harrell Construction LLC | 4. Jones Bros. Contractors, LLC |
|---|---|---|---|---|---|---|---|
| 1 | Construction stakes, lines and grades (105-01) | LS | 1 | $25,121 | $15,094 | $12,500 | $20,000 |
| 2 | Clearing and grubbing (201-01) | LS | 1 | $85,213 | $550,000 | $80,000 | $150,000 |
| 3 | Road & drainage excavation (unclassified) (203-01) | CY | 33 | $99.97 | $51.91 | $33.00 | $100.00 |
| 4 | Borrow excavation (graded solid rock) (203-02.01) | TON | 12,830 | $66.02 | $31.00 | $70.00 | $55.00 |
| 5 | Construction of haul road (203-50) | LS | 1 | $781,468 | $900,000 | $900,000 | $1,090,000 |
| 6 | Sediment removal (209-05) | CY | 59 | $100.23 | $26.17 | $40.00 | $100.00 |
| 7 | W beam GR (type 2) MASH TL-3 (long post) (705-06.02) | LF | 32 | $37.40 | $39.10 | $37.18 | $34.00 |
| 8 | Guardrail removed (706-01) | LF | 32 | $1.39 | $1.44 | $1.50 | $1.25 |
| 9 | High-visibility construction fence (707-08.11) | LF | 772 | $4.95 | $5.18 | $3.40 | $4.50 |
| 10 | Machined rip-rap (class A-3) (709-05.05) | TON | 213 | $85.21 | $75.02 | $70.00 | $65.00 |
| 11 | Traffic control (712-01) | LS | 1 | $59,258 | $40,000 | $50,000 | $40,000 |
| 12 | Portable barrier rail (MASH TL-3) (712-02.10) | LF | 660 | $78.88 | $80.33 | $87.36 | $40.00 |
| 13 | Temporary work zone crash cushion (MASH TL-3) (712-02.60) | EACH | 1 | $9,339.24 | $9,890.00 | $9,284.06 | $6,650.00 |
| 14 | Flexible drums (channelizing) (712-04.01) | EACH | 150 | $36.30 | $37.95 | $36.09 | $33.00 |
| 15 | Barrier rail delineator (712-04.50) | EACH | 33 | $20.35 | $9.20 | $8.80 | $8.00 |
| 16 | Warning lights (type A) (712-05.01) | EACH | 75 | $5.50 | $5.75 | $5.47 | $5.00 |
| 17 | Signs (construction) (712-06) | SF | 421 | $8.36 | $8.74 | $8.31 | $7.60 |
| 18 | Arrow board (type C) (712-08.03) | EACH | 1 | $935.10 | $977.50 | $929.48 | $850.00 |
| 19 | Removable pavement marking (8" barrier line) (712-09.02) | LF | 5,491 | $4.95 | $5.18 | $4.92 | $4.50 |
| 20 | Removable black-out tape (8IN) (712-09.31) | LF | 780 | $4.95 | $5.18 | $4.92 | $4.50 |
| 21 | Mobilization (717-01) | LS | 1 | $75,147 | $225,000 | $200,000 | $235,000 |
| 22 | Geotextile (type III)(erosion control) (740-10.03) | SY | 363 | $8.25 | $9.82 | $3.50 | $4.50 |
| 23 | Geotextile (type IV)(stabilization) (740-10.04) | SY | 2,512 | $8.37 | $5.92 | $3.50 | $5.00 |
| 24 | Temporary sediment tube 18IN (740-11.03) | LF | 1,710 | $5.50 | $5.75 | $6.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TDOT's tabulation for this contract. TDOT Summary of Bids PDFs: every letting posted for February 2024 to October 2026, and nine lettings of 2018 to 2023 recovered from archived copies of the tn.gov files. Cost-plus-time bids, and bids that did not match their published total, are left out.
Every contract let that day: TDOT letting of October 2, 2026. Compiled by Mirage Metrics.