Norman Highway Constructors, Inc.: TxDOT bid record

Norman Highway Constructors, Inc. submitted 12 bids on Texas DOT contracts in the data, from 08 APR 2020 to 07 JAN 2026, and was the low bidder on 3 of them (25%). When it was not low, its total sat a median +16% above the low bid.

Owner
Texas DOT
Low bid volume
$2,644,106
Latest bid
07 JAN 2026
Data through
19 NOV 2026
12Bids
3Low bids
25Win rate, percent
+16%Median gap to the low bid when not low, 8 bids

By year

YearBidsLow bidsWin rate
202022100%
2021300%
20224125%
2023100%
2024100%
2026100%
Norman Highway Constructors, Inc., TxDOT: bids and low bids by year of letting

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Barricades, signs and traffic handling502-7001MO117 (64%)$1,725.00$5,000.00
Biodegradable erosion control logs (install) (12")506-7044LF63 (50%)$6.00$6.00
Biodegradable erosion control logs (remove)506-7046LF72 (29%)$2.00$1.40
RC pipe (CL III)(24 in)464-7005LF52 (40%)$115.00$108.13
Set (type II) (24 in) (RCP) (6: 1) (P)467-7328EACH52 (40%)$1,250.00$1,900.00
Vegetative watering168-7001MG81 (13%)$170.00$29.97
Portable changeable message sign503-7001DAY51 (20%)$250.00$100.00
Norman Highway Constructors, Inc., TxDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
FNH Construction, LLC60 of 6
SJ&J Construction, LLC33 of 3
Project Allied Resources, LLC32 of 3
SCR Civil Construction, LLC31 of 3
Icos Management, LLC21 of 2
Dbi Services, LLC20 of 2
MK Constructors20 of 2
Main Lane Industries LTD.20 of 2
Ragle Construction, Inc.21 of 2
Ti-Zack Concrete, LLC21 of 2
Norman Highway Constructors, Inc., TxDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
07 JAN 2026A00134330Beaumont DistrictBridge Maintenance, Various (DISTRICT WIDE to JEFF, JASP, HARD, ORANGE, TYLER, NEWTON)5 of 7$2,086,265+295%
09 AUG 202408242003Beaumont DistrictSH0073 Bridge preventative maintenance from VARIOUS LOCATIONS IN to JEFFERSON & HARDIN COUNTIES5 of 6$818,645+61%
07 MAR 202303233037Beaumont DistrictCS Bridge replacement from AT DRAINAGE DITCH to STR#201810C018350032 of 5$615,509+2.0%
16 NOV 202211222002Beaumont DistrictUS0069 Bridge preventative maintenance from VARIOUS LOCATIONS IN to JEFFERSON , HARDIN, AND ORANGE COUN2 of 5$361,068+30%
02 NOV 202211223017Beaumont DistrictVA Construct pedestrian infrastructure from ON FM 2799 FROM MAIN ST. to PARK LANE4 of 4$1,667,074+19%
30 JUN 202206223628Beaumont DistrictFM 364 Hazard elimination & safety from 300' N OF SPURLOCK, SOUTH to SH 1051 of 3$871,505Low, 36% under the second
02 JUN 202206223244Beaumont DistrictSH 73 Hazard elimination & safety from SH 124, EAST to 0.627 MILES SOUTH OF PORTLAND ST.2 of 4$175,274+12%
26 OCT 202110212001Beaumont DistrictSH0012 Bridge repair from VARIOUS LOCATIONS to VARIOUS LOCATIONS3 of 4$171,090+26%
06 MAY 202105213229Beaumont DistrictVA Construct pedestrian infrastructure from ON S.CLEVELAND, LOVERS LANE, AND FM to FROM HOUSTON ST TO SOUTH OF BROWN R3 of 6$440,033+13%
07 APR 202104213013Beaumont DistrictFM 1006 Hazard elimination & safety from SH 87, EAST to 0.171 MI N OF FM 21772 of 6$408,598+1.0%
09 APR 202004203232Beaumont DistrictFM 1078 Safety improvement project from SH 62, NORTH to FM 11301 of 4$697,979Low, 14% under the second
08 APR 202004203025Beaumont DistrictSH 321 Sft-safety improvement projects from SH 105 to 0.30 MI S OF FM 10081 of 7$1,074,621Low, 2.0% under the second
Norman Highway Constructors, Inc.: latest TxDOT bids in the data

How this record was read

TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; TxDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy