Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Westfield Insurance Company | $829,673 | Low | -12% |
| 2 | Hodges and Son Construction Company, Inc. | $870,896 | +5.0% | -7.0% |
| 3 | Pmco Construction LLC | $919,220 | +11% | -2.0% |
| 4 | Texas Steel Industrial Placing, LLC | $938,906 | +13% | 0.0% |
| 5 | Scott Tucker Construction Company, LLC | $1,045,742 | +26% | +11% |
| 6 | STX Civil | $1,053,362 | +27% | +12% |
| 7 | Ed Bell Construction Company | $1,210,337 | +46% | +29% |
| 8 | Coppell Construction Co., Inc. | $1,311,653 | +58% | +39% |
Engineer's estimate: $940,443.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Westfield Insurance Company | 2. Hodges and Son Construction Company, Inc. | 3. Pmco Construction LLC | 4. Texas Steel Industrial Placing, LLC | 5. Scott Tucker Construction Company, LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 3.75 | $5,000.00 | $2,750.00 | $4,000.00 | $5,000.00 | $1,750.00 | $5,242.00 | $2,800.00 |
| 2 | Remove (4"-8") TRT/untrt base & asphalt pavement (105-7004) | SY | 719 | $21.00 | $7.91 | $6.00 | $15.00 | $10.00 | $20.00 | $20.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 368 | $36.00 | $22.00 | $30.00 | $24.00 | $20.00 | $49.00 | $35.00 |
| 4 | Embankment (final)(OC)(type C) (132-7005) | CY | 125 | $122.00 | $22.00 | $30.00 | $34.00 | $30.00 | $135.00 | $90.00 |
| 5 | Backfill (type A or B) (134-7004) | STA | 4.93 | $332.00 | $517.00 | $400.00 | $800.00 | $500.00 | $2,590.00 | $240.00 |
| 6 | Block sodding (162-7002) | SY | 884 | $10.00 | $6.05 | $6.00 | $6.50 | $8.00 | $6.00 | $10.00 |
| 7 | Vegetative watering (168-7001) | TGL | 31 | $165.00 | $55.00 | $1.00 | $100.00 | $50.00 | $292.00 | $100.00 |
| 8 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 672 | $31.00 | $16.50 | $45.00 | $60.00 | $30.00 | $27.00 | $110.00 |
| 9 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 197 | $7.00 | $26.40 | $10.00 | $26.00 | $5.00 | $30.00 | $7.50 |
| 10 | D-GR HMA type-B PG64-22 (341-7001) | TON | 149 | $177.00 | $212.30 | $200.00 | $209.00 | $195.00 | $219.00 | $230.00 |
| 11 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 73 | $183.00 | $280.50 | $250.00 | $276.00 | $395.00 | $307.00 | $430.00 |
| 12 | Tack coat (344-7077) | GAL | 127 | $5.00 | $1.10 | $10.00 | $1.00 | $5.00 | $1.00 | $10.00 |
| 13 | Cem stabil BKFL (400-7010) | CY | 80.30 | $200.00 | $203.50 | $300.00 | $300.00 | $200.00 | $335.00 | $220.00 |
| 14 | Drilled shaft (24 in) (416-7004) | LF | 222 | $251.00 | $242.00 | $190.00 | $280.00 | $400.00 | $334.00 | $250.00 |
| 15 | Class C concrete (abutment)(HPC) (420-7013) | CY | 20.60 | $1,557.00 | $1,375.00 | $1,800.00 | $1,500.00 | $1,250.00 | $2,172.00 | $1,500.00 |
| 16 | Class C concrete (cap)(HPC) (420-7023) | CY | 15.40 | $1,720.00 | $1,540.00 | $1,800.00 | $2,000.00 | $1,400.00 | $3,255.00 | $2,000.00 |
| 17 | Class C concrete (column)(HPC) (420-7039) | CY | 7.70 | $1,734.00 | $1,595.00 | $1,800.00 | $2,300.00 | $1,400.00 | $4,655.00 | $2,900.00 |
| 18 | Reinforced concrete slab (HPC) (422-7002) | SF | 1,950 | $32.00 | $27.50 | $30.00 | $30.00 | $25.00 | $39.00 | $32.00 |
| 19 | Approach slab (HPC) (422-7014) | CY | 50.80 | $889.00 | $880.00 | $800.00 | $850.00 | $675.00 | $992.00 | $900.00 |
| 20 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 367.12 | $228.00 | $231.75 | $325.00 | $350.00 | $275.00 | $297.00 | $275.00 |
| 21 | Riprap (mow strip)(5 in) (432-7014) | CY | 20 | $573.00 | $869.44 | $700.00 | $825.00 | $600.00 | $788.00 | $850.00 |
| 22 | Riprap (stone protection)(18 in) (432-7043) | CY | 664 | $200.00 | $200.51 | $175.00 | $145.00 | $185.00 | $139.00 | $260.00 |
| 23 | Rail (type T223)(HPC) (450-7009) | LF | 178 | $180.00 | $181.50 | $180.00 | $150.00 | $150.00 | $261.00 | $300.00 |
| 24 | Armor joint (sealed) (454-7003) | LF | 55.40 | $150.00 | $183.70 | $200.00 | $165.00 | $150.00 | $103.00 | $200.00 |
| 25 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $41,377 | $11,000 | $8,000.00 | $40,000 | $36,500 | $40,016 | $25,000 |
| 26 | Mobilization (500-7001) | LS | 1 | $80,906 | $105,000 | $75,000 | $91,000 | $93,045 | $104,518 | $85,000 |
| 27 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $8,412.00 | $1,657.83 | $8,000.00 | $3,500.00 | $2,200.00 | $1,543.00 | $5,000.00 |
| 28 | Portable changeable message sign (503-7002) | EACH | 4 | $15,000 | $10,560 | $11,000 | $6,000.00 | $26,000 | $8,557.00 | $6,500.00 |
| 29 | Rock filter dams (install) (type 2) (506-7002) | LF | 155 | $40.00 | $27.50 | $1.00 | $27.50 | $50.00 | $32.00 | $50.00 |
| 30 | Rock filter dams (remove) (506-7011) | LF | 155 | $17.00 | $11.00 | $1.00 | $9.00 | $20.00 | $13.00 | $5.00 |
| 31 | Temporary sediment control fence (install) (506-7039) | LF | 723 | $3.50 | $3.58 | $1.00 | $3.65 | $5.00 | $4.00 | $5.00 |
| 32 | Temporary sediment control fence (remove) (506-7041) | LF | 723 | $1.10 | $1.10 | $1.00 | $1.20 | $2.00 | $2.00 | $1.00 |
| 33 | Metal W-beam guard fence (timber post) (540-7001) | LF | 100 | $24.00 | $24.75 | $25.00 | $34.50 | $30.00 | $44.00 | $38.00 |
| 34 | Metal beam guard fence trans (TL2) (540-7006) | EACH | 4 | $896.00 | $1,320.00 | $1,400.00 | $1,350.00 | $2,800.00 | $1,640.00 | $2,250.00 |
| 35 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,844.00 | $3,245.00 | $3,000.00 | $3,265.00 | $3,250.00 | $3,371.00 | $3,100.00 |
| 36 | Wire fence (type C) (552-7003) | LF | 328 | $30.00 | $27.50 | $20.00 | $25.00 | $20.00 | $31.00 | $35.00 |
| 37 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $178.00 | $108.90 | $50.00 | $100.00 | $130.00 | $154.00 | $50.00 |
| 38 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 4 | $33.00 | $22.00 | $25.00 | $35.00 | $35.00 | $113.00 | $60.00 |
| 39 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 4 | $40.00 | $27.50 | $25.00 | $35.00 | $35.00 | $44.00 | $100.00 |
| 40 | Install object marker assembly (OM-2Z)(WFLX)GND (658-7058) | EACH | 4 | $115.00 | $22.00 | $500.00 | $100.25 | $120.00 | $139.00 | $95.00 |
| 41 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 258 | $1.50 | $1.65 | $1.50 | $2.00 | $2.00 | $2.00 | $4.00 |
| 42 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 258 | $1.80 | $1.65 | $1.50 | $2.00 | $2.00 | $2.00 | $4.00 |
| 43 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 751 | $1.50 | $3.30 | $3.00 | $3.30 | $5.00 | $4.00 | $6.00 |
| 44 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 750 | $1.40 | $3.30 | $3.00 | $3.30 | $5.00 | $4.00 | $6.00 |
| 45 | Pavement surface preparation for marking (6") (678-7002) | LF | 516 | $0.20 | $0.55 | $0.50 | $0.70 | $1.00 | $1.00 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.