TxDOT contract A00121832 bid tabulation

Bridge Replacement, BI 27U (FM 3466 to W 3RD STREET). Let by Texas DOT on April 4, 2025, Hale, Lubbock District. 6 bids received; low bid $6,813,363 by Coppell Construction Co., Inc., -10% against the engineer's estimate of $7,580,981.

Owner
Texas DOT
Letting
04 APR 2025
Pay items
102
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Coppell Construction Co., Inc.$6,813,363Low-10%
2L A Fuller & Sons Construction, LTD.$7,678,802+13%+1.0%
3Gilvin-Terrill, LTD.$8,299,990+22%+9.0%
4McMillen, Inc.$9,863,292+45%+30%
5Earth Builders, L.P.$10,691,887+57%+41%
6A. L. Helmcamp, Inc.$11,462,193+68%+51%
TxDOT contract A00121832: bids by rank

Engineer's estimate: $7,580,981.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Coppell Construction Co., Inc.2. L A Fuller & Sons Construction, LTD.3. Gilvin-Terrill, LTD.4. McMillen, Inc.5. Earth Builders, L.P.6. A. L. Helmcamp, Inc.
1Preparation row (tree remove) (12"-24" diameter) (100-7004)EACH1$2,500.00$2,500.00$1,284.00$3,000.00$3,000.00$2,200.00$2,500.00
2Preparation row (tree remove) (24"-36" diameter) (100-7005)EACH2$3,000.00$2,600.00$1,398.05$4,000.00$3,000.00$3,500.00$3,100.00
3Removing concrete (riprap) (104-7006)SY270$20.00$25.00$40.00$20.00$100.00$100.00$85.00
4Removing concrete (curb & gutter) (104-7017)LF230$25.00$15.00$26.05$20.00$40.00$35.00$35.00
5Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001)SY4,097$10.00$4.75$4.05$25.00$6.00$9.00$10.00
6Excavation (roadway) (110-7001)CY681$50.00$35.00$34.80$80.00$42.00$35.00$30.00
7Embankment (final)(OC)(type C) (132-7005)CY144$50.00$55.00$94.70$80.00$50.00$40.00$88.00
8Drill seed (permanent_urban_clay) (164-7012)SY10,240$1.00$0.60$1.00$0.75$1.00$0.35$0.65
9Drill seed (temporary_warm_cool) (164-7015)SY10,240$1.00$0.60$0.75$0.75$1.00$0.35$0.65
10Vegetative watering (168-7001)TGL689$200.00$30.00$99.55$35.00$50.00$30.00$35.00
11Proof rolling (216-7001)HR20$200.00$140.00$232.15$200.00$375.00$150.00$220.00
12FL BS (compacted in place) (type A GR 4) (4"-21") (247-7342)SY3,774$50.00$98.00$43.65$75.00$74.00$130.00$38.00
13Prime coat (MC-30) (310-7004)GAL755$10.00$25.00$9.20$12.00$15.00$20.00$11.00
14Emuls asphalt (erosion control)(CSS-1H) (314-7011)GAL2,662$5.00$25.00$5.40$10.00$4.00$18.00$4.50
15Fog seal (CSS-1H) (315-7004)GAL23,962$5.00$15.00$4.85$4.00$14.00$10.00$3.50
16Aggregate (type-B, GR-5)(sac-B) (316-7175)CY285$250.00$130.00$364.10$150.00$462.00$850.00$450.00
17D-GR HMA type-C sac-B PG70-28 (341-7028)TON867$300.00$250.00$277.50$250.00$300.00$320.00$290.00
18Tack coat (341-7082)GAL529$10.00$25.00$10.30$10.00$15.00$25.00$8.00
19SP mixes SP-D sac-A PG70-28 (344-7057)TON435$400.00$460.00$291.45$300.00$300.00$350.00$360.00
20Tack coat (344-7077)GAL529$10.00$25.00$10.30$10.00$15.00$25.00$8.00
21Flexible pavement structure repair(3") (351-7002)SY500$80.00$250.00$174.60$90.00$110.00$150.00$152.00
22Planing asphalt concrete pavement(6") (354-7055)SY4,097$12.00$4.75$7.50$20.00$12.00$15.00$8.50
23Cem stabil BKFL (400-7010)CY288$300.00$400.00$279.20$800.02$350.00$500.00$400.00
24Temporary special shoring (cofferdam) (403-7002)SF5,760$30.00$35.00$12.95$50.00$90.00$10.00$12.00
25Drilled shaft (36 in) (416-7006)LF952$450.00$400.00$484.30$410.00$365.00$500.00$560.00
26Class C concrete (abutment) (420-7012)CY99.60$2,300.00$1,400.00$2,343.00$2,000.00$2,300.00$3,000.00$3,000.00
27Class C concrete (cap) (420-7022)CY81.20$2,600.00$1,400.00$1,893.50$2,000.00$2,800.00$4,000.00$3,400.00
28Class C concrete (column) (420-7038)CY23.60$2,600.00$2,000.00$3,105.00$2,000.00$5,000.00$4,000.00$3,400.00
29Reinforced concrete slab (422-7001)SF13,200$45.00$39.00$57.90$40.09$55.00$60.00$60.00
30Approach slab (422-7013)CY172.80$1,400.00$1,200.00$1,042.80$2,000.00$1,200.00$2,500.00$1,100.00
31Prestressed concrete girder (TX28) (425-7001)LF1,484.80$300.00$282.00$295.35$350.00$425.00$450.00$320.00
32Epoxy waterproof finish (type X) (427-7005)SF2,936.50$20.00$10.00$10.85$15.00$15.00$25.00$15.00
33Riprap (concrete)(CL B) (432-7005)CY378$700.00$500.00$667.15$1,000.00$975.00$1,000.00$920.00
34Riprap (mow strip)(5 in) (432-7014)CY60$750.00$700.00$559.35$1,000.00$1,200.00$750.00$920.00
35STR steel (miscellaneous non-bridge) (442-7007)LB112$50.00$35.00$33.55$20.00$31.00$25.00$25.00
36Rail (type T223) (450-7008)LF680$250.00$225.00$274.20$175.00$340.00$325.00$270.00
37Armor joint (sealed) (454-7003)LF168$320.00$200.00$215.80$150.00$196.00$200.00$200.00
38RC pipe (CL III)(30 in) (464-7007)LF120$360.00$425.00$260.25$200.00$225.00$200.00$200.00
39Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH3$6,000.00$4,500.00$8,142.55$10,000$4,200.00$4,000.00$8,000.00
40Removing structure (set) (496-7004)EACH3$1,500.00$2,500.00$2,053.10$2,000.00$1,600.00$1,000.00$2,000.00
41Removing structure (bridge 100 - 499 FT length) (496-7010)EACH2$400,000$350,000$589,372$467,000$1,075,000$1,000,000$1,950,000
42Mobilization (500-7001)LS1$689,000$600,000$762,627$800,000$950,000$1,100,000$1,100,000
43Barricades, signs and traffic handling (502-7001)MO18$30,000$15,000$12,800$42,550$12,000$4,000.00$42,000
44Portable changeable message sign (503-7001)DAY960$150.00$100.00$84.85$80.00$60.00$120.00$75.00
45TMA (stationary) (505-7001)DAY482$250.00$275.00$500.85$450.00$250.00$300.00$100.00
46TMA (mobile operation) (505-7003)DAY15$1,000.00$500.00$961.20$450.00$1,000.00$500.00$100.00
47Rock filter dams (install) (type 3) (506-7003)LF270$90.00$150.00$138.90$175.00$70.00$100.00$160.00
48Rock filter dams (remove) (506-7011)LF135$30.00$35.00$84.90$50.00$50.00$20.00$30.00
49Construction exits (install) (type 1) (506-7020)SY900$50.00$45.00$57.95$50.00$25.00$75.00$30.00
50Construction exits (remove) (506-7024)SY450$20.00$25.00$45.90$30.00$25.00$10.00$10.00
51Temporary sediment control fence (install) (506-7039)LF750$8.00$6.50$3.55$6.50$5.00$7.00$7.00
52Temporary sediment control fence (remove) (506-7041)LF375$4.00$3.00$1.35$3.00$2.00$2.00$3.00
53Biodegradable erosion control logs (install) (18") (506-7045)LF1,995$10.00$10.00$12.10$10.00$8.00$12.00$10.00
54Biodegradable erosion control logs (remove) (506-7046)LF998$5.00$3.00$0.65$3.00$3.00$2.00$3.00
55Constructing detours (type 1) (508-7003)SY563$150.00$150.00$129.40$85.00$300.00$200.00$142.00
56Constructing detours (type 2) (508-7004)SY59$500.00$200.00$377.65$410.00$800.00$700.00$1,000.00
57Concrete curb & gutter (type II) (529-7009)LF175$100.00$50.00$49.34$50.00$60.00$40.00$100.00
58Metal W-beam guard fence (steel post) (540-7002)LF1,300$50.00$29.00$31.90$35.00$34.65$42.00$32.00
59Downstream anchor terminal section (540-7015)EACH4$2,000.00$1,450.00$1,705.00$1,550.00$1,325.00$2,000.00$1,800.00
60Metal beam guard fence trans (non - sym) (540-7016)EACH2$1,300.00$1,025.00$1,210.00$1,100.00$1,350.00$1,600.00$1,300.00
61Metal thrie-beam guard fence (steel post) (540-7020)EACH6$3,000.00$2,100.00$2,447.50$2,300.00$2,625.00$3,200.00$2,500.00
62Remove metal beam guard fence (542-7001)LF875$5.00$3.00$5.50$5.00$2.00$5.00$6.00
63Remove terminal anchor section (542-7002)EACH4$500.00$150.00$440.00$400.00$215.00$350.00$450.00
64Guardrail end treatment (install) (544-7001)EACH9$4,000.00$3,275.00$3,630.00$3,300.00$4,225.00$4,000.00$3,700.00
65Guardrail end treatment (remove) (544-7003)EACH8$500.00$200.00$440.00$400.00$320.00$300.00$450.00
66In RD IL (U/P) (type 1) (250W EQ) LED (610-7015)EACH2$3,000.00$2,500.00$3,245.00$2,500.00$4,000.00$4,000.00$3,300.00
67Conduit (HDPE) (2") bore (618-7010)LF192$40.00$71.00$32.45$100.00$55.00$90.00$33.00
68Conduit (RM) (2") (618-7078)LF314$100.00$58.00$67.32$30.00$60.00$80.00$70.00
69Electrical conductor (no.6) bare (620-7009)LF526$8.00$8.00$4.07$2.50$35.00$8.00$4.10
70Electrical conductor (no.6) insulated (620-7010)LF1,052$8.50$9.00$4.40$3.00$15.00$9.00$4.50
71Ground box type A (122311)W/apron (624-7002)EACH3$2,000.00$2,500.00$2,695.00$1,800.00$1,500.00$2,300.00$2,700.00
72Remove electrical services (628-7002)EACH1$2,000.00$2,400.00$1,100.00$500.00$7,500.00$2,200.00$1,200.00
73Elc SRV type A 120/240 060(NS)SS(E)SP(O) (628-7009)EACH1$10,000$9,000.00$10,313$10,000$20,000$10,000$11,000
74Install delineator assembly (D-SW)SZ 1(BRF)CTB (BR) (658-7014)EACH4$60.00$45.00$50.60$46.00$45.00$55.00$55.00
75Install delineator assembly (D-SW)SZ 1(BRF)GF2(BR) (658-7020)EACH6$100.00$45.00$46.20$42.00$45.00$55.00$50.00
76Install delineator assembly (D-SY)SZ 1(BRF)CTB (BR) (658-7033)EACH4$60.00$45.00$50.60$46.00$45.00$55.00$55.00
77Install delineator assembly (D-SY)SZ 1(BRF)GF2(BR) (658-7038)EACH5$100.00$45.00$46.20$42.00$44.00$55.00$50.00
78Remove delin & object marker assms (658-7078)EACH8$30.00$15.00$24.15$10.00$18.00$25.00$40.00
79Work zone pavement marking removing (traffic BTN) type W (662-7058)LF17,520$2.00$1.20$1.32$1.20$1.50$1.80$1.50
80Work zone pavement marking removing (traffic BTN) type Y (662-7060)LF28,365$2.00$1.20$1.32$1.20$1.50$1.80$1.50
81Work zone pavement marking removing (W)24"(solid) (662-7077)LF1,037$20.00$21.00$23.10$21.00$21.00$25.00$23.00
82Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH678$2.00$1.50$11.05$21.50$2.60$0.80$1.20
83Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH240$2.00$1.50$11.05$1.50$2.20$0.80$1.20
84Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF850$2.00$2.00$2.20$2.00$2.00$2.40$2.30
85Type I high perf PM (W)6"(broken)(100MIL) (666-7290)LF1,555$1.50$1.50$1.65$1.50$1.50$2.00$1.70
86Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF4,020$1.50$1.50$1.65$1.50$1.50$2.00$1.70
87Type I high perf PM (Y)6"(broken)(100MIL) (666-7302)LF330$1.50$1.50$1.65$1.50$1.50$2.00$1.70
88Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF5,080$1.50$1.50$1.65$1.50$1.50$2.00$1.70
89Prefabricated PM type B (W)(6")(broken) (668-7008)LF100$15.00$10.00$11.00$10.00$10.00$12.00$11.00
90Prefabricated PM type B (W)(6")(solid) (668-7009)LF400$15.00$10.00$11.00$10.00$10.00$12.00$11.00
91Prefabricated PM type B (Y)(6")(solid) (668-7051)LF400$15.00$10.00$11.00$10.00$10.00$12.00$11.00
92Prefabricated PM type C (W)(24")(solid) (668-7089)LF40$30.00$20.00$22.00$20.00$20.00$25.00$22.00
93Prefabricated PM type C (W)(arrow) (668-7091)EACH14$300.00$250.00$275.00$250.00$250.00$300.00$275.00
94Reflectorized pavement marker type II-C-R (672-7006)EACH241$5.00$5.50$6.05$5.50$6.00$7.00$6.50
95Eliminating existing PM & markers (6") (677-7002)LF46,934$0.80$0.75$0.83$0.75$1.00$1.00$0.90
96Eliminating existing PM & markers (24") (677-7008)LF691$10.00$5.00$5.50$5.00$5.00$7.00$6.00
97Pavement surface preparation for marking (6") (678-7002)LF900$2.00$4.00$4.40$4.00$4.00$5.00$4.20
98Temporary traffic signals (681-7001)EACH2$35,000$65,000$59,511$43,100$50,000$50,000$15,000
99Full - width mowing (730-7019)CYC4$6,000.00$1,500.00$1,073.35$1,013.75$8,000.00$3,500.00$3,200.00
100Litter removal (734-7002)CYC4$3,000.00$250.00$670.85$1,538.00$5,000.00$3,500.00$2,800.00
101Anti-graffiti coatng (permnent-type III) (740-7006)SF23,602$3.00$2.00$2.04$2.00$2.00$2.50$2.20
102Temporary construction access (4006-7001)LS1$100,000$70,000$261,606$230,000$100,000$500,000$250,000
TxDOT contract A00121832: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy