TxDOT contract A00125824 bid tabulation
Bridge Replacement, COUNTY ROAD 331 (On CR 331 Over west Fork Branch to 0.5 miles north of CR 262). Let by Texas DOT on January 8, 2025, Runnels, San Angelo District. 8 bids received; low bid $1,997,089 by J. H. Strain & Sons, Inc., -25% against the engineer's estimate of $2,664,344.
- Owner
- Texas DOT
- Letting
- 08 JAN 2025
- Pay items
- 49
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J. H. Strain & Sons, Inc. | $1,997,089 | Low | -25% |
| 2 | Delgado'S Contractors, LLC | $2,262,627 | +13% | -15% |
| 3 | STX Civil | $2,393,584 | +20% | -10% |
| 4 | Skyline Bridge LLC | $2,637,977 | +32% | -1.0% |
| 5 | C. E. Barker, LTD. | $3,174,558 | +59% | +19% |
| 6 | Hodges and Son Construction Company, Inc. | $3,311,857 | +66% | +24% |
| 7 | Reece Albert, Inc. | $3,402,059 | +70% | +28% |
| 8 | Talbert Companies LLC | $3,454,079 | +73% | +30% |
Engineer's estimate: $2,664,344.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. J. H. Strain & Sons, Inc. | 2. Delgado'S Contractors, LLC | 3. STX Civil | 4. Skyline Bridge LLC | 5. C. E. Barker, LTD. | 6. Hodges and Son Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 18.30 | $3,800.00 | $1,500.00 | $1,000.00 | $5,000.00 | $5,000.00 | $18,450 | $7,000.00 |
| 2 | Remove (0"-4") TRT/untrt base & asphalt pavement (105-7001) | SY | 880 | $7.00 | $22.00 | $18.00 | $15.00 | $34.84 | $10.00 | |
| 3 | Excavation (roadway) (110-7001) | CY | 312 | $45.00 | $25.00 | $40.00 | $20.00 | $27.00 | $33.44 | $60.00 |
| 4 | Excavation (channel) (110-7002) | CY | 399 | $40.00 | $30.00 | $40.00 | $40.00 | $25.00 | $39.02 | $60.00 |
| 5 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,682 | $45.00 | $18.00 | $60.00 | $35.00 | $45.00 | $40.30 | $50.00 |
| 6 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 3,922 | $3.00 | $0.35 | $1.00 | $1.00 | $5.00 | $1.11 | $5.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 1,961 | $3.00 | $0.35 | $1.00 | $1.00 | $5.00 | $1.11 | $3.00 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 1,961 | $3.00 | $0.35 | $1.00 | $1.00 | $5.00 | $1.11 | $3.00 |
| 9 | FL BS (compacted in place)(type A GR 1-2) (8") (247-7067) | SY | 3,838 | $40.00 | $14.50 | $40.00 | $75.00 | $39.00 | $40.97 | $120.00 |
| 10 | Prime coat (MC-30) (310-7004) | GAL | 284 | $12.00 | $15.00 | $13.50 | $25.00 | $11.15 | $20.00 | |
| 11 | Asphalt (AC-20-5TR or AC-20XP) (316-7067) | GAL | 1,103 | $12.00 | $25.00 | $7.50 | $22.00 | $22.30 | $25.00 | |
| 12 | Aggregate (type-PB, GR-3)(sac-B) (316-7208) | CY | 13 | $200.00 | $1,000.00 | $350.00 | $2,500.00 | $445.92 | $2,000.00 | |
| 13 | Aggregate (type-PB, GR-4)(sac-B) (316-7211) | CY | 11 | $200.00 | $1,000.00 | $350.00 | $2,500.00 | $445.92 | $2,000.00 | |
| 14 | Cem stabil BKFL (400-7010) | CY | 26 | $275.00 | $225.00 | $272.00 | $350.00 | $167.22 | $350.00 | |
| 15 | Drilled shaft (24 in) (416-7004) | LF | 480 | $235.00 | $225.00 | $450.00 | $550.00 | $408.93 | $215.00 | |
| 16 | Class C concrete (abutment) (420-7012) | CY | 18.40 | $1,300.00 | $1,800.00 | $1,500.00 | $1,600.00 | $2,464.51 | $2,500.00 | |
| 17 | Class C concrete (cap) (420-7022) | CY | 13.20 | $1,450.00 | $1,800.00 | $2,000.00 | $2,000.00 | $2,502.33 | $2,600.00 | |
| 18 | Class C concrete (column) (420-7038) | CY | 5.30 | $1,200.00 | $1,800.00 | $2,500.00 | $2,500.00 | $2,480.17 | $3,000.00 | |
| 19 | Reinforced concrete slab (slab beam) (422-7007) | SF | 3,380 | $29.00 | $30.00 | $23.00 | $35.00 | $33.46 | $40.00 | |
| 20 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 642.50 | $240.00 | $275.00 | $238.00 | $325.00 | $259.93 | $330.00 | |
| 21 | Riprap (concrete)(4 in) (432-7001) | CY | 2 | $750.00 | $800.00 | $1,000.00 | $2,000.00 | $1,508.70 | $1,500.00 | |
| 22 | Riprap (mow strip)(4 in) (432-7013) | CY | 102.20 | $745.00 | $725.00 | $675.00 | $722.00 | $750.05 | $1,034.74 | $750.00 |
| 23 | Riprap (stone common)(grout)(12 in) (432-7038) | CY | 20.30 | $250.00 | $300.00 | $300.00 | $225.00 | $325.00 | $222.96 | $350.00 |
| 24 | Riprap (stone protection)(12 in) (432-7041) | CY | 150 | $175.00 | $250.00 | $185.00 | $250.00 | $222.96 | $250.00 | |
| 25 | Rail (type T223) (450-7008) | LF | 284 | $115.00 | $185.00 | $200.00 | $175.00 | $271.54 | $180.00 | |
| 26 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 52 | $300.00 | $300.00 | $260.00 | $325.00 | $242.19 | $220.00 | |
| 27 | Concrete box culvert (6 FT X 2 FT) (462-7010) | LF | 200 | $615.00 | $600.00 | $380.00 | $700.00 | $440.51 | $750.00 | |
| 28 | Concrete box culvert (8 FT X 4 FT) (462-7021) | LF | 240 | $1,192.00 | $875.00 | $725.00 | $640.00 | $900.00 | $655.73 | $1,200.00 |
| 29 | Concrete box culvert (9 FT X 4 FT) (462-7026) | LF | 200 | $1,150.00 | $825.00 | $750.00 | $1,000.00 | $736.88 | $1,000.00 | |
| 30 | RC pipe (CL III)(18 in) (464-7003) | LF | 40 | $90.00 | $100.00 | $83.00 | $250.00 | $324.52 | $150.00 | |
| 31 | Wingwall (PW - 1) (HW=3 FT) (466-7173) | EACH | 2 | $17,000 | $17,500 | $20,000 | $15,000 | $51,269 | $35,000 | |
| 32 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 6 | $18,000 | $18,700 | $22,000 | $25,000 | $20,000 | $62,569 | $55,000 |
| 33 | Removing structure (box culvert) (496-7001) | EACH | 4 | $13,000 | $14,000 | $20,000 | $12,000 | $10,000 | $34,838 | $30,000 |
| 34 | Removing structure (bridge 100 - 499 FT length) (496-7010) | EACH | 1 | $95,000 | $60,000 | $130,000 | $50,000 | $101,726 | $50,000 | |
| 35 | Mobilization (500-7001) | LS | 1 | $225,800 | $115,000 | $190,000 | $190,000 | $225,000 | $303,000 | $320,000 |
| 36 | Barricades, signs and traffic handling (502-7001) | MO | 22 | $9,609.70 | $5,000.00 | $4,000.00 | $3,500.00 | $4,000.00 | $3,370.15 | $3,000.00 |
| 37 | Rock filter dams (install) (type 1) (506-7001) | LF | 92 | $45.00 | $75.00 | $40.00 | $50.00 | $55.74 | $1.00 | |
| 38 | Rock filter dams (remove) (506-7011) | LF | 92 | $5.00 | $10.00 | $15.00 | $10.00 | $22.30 | $1.00 | |
| 39 | Temporary sediment control fence (install) (506-7039) | LF | 2,449 | $4.84 | $6.00 | $7.00 | $5.00 | $4.00 | $5.57 | $1.00 |
| 40 | Temporary sediment control fence (remove) (506-7041) | LF | 2,449 | $1.55 | $1.50 | $1.00 | $1.00 | $1.75 | $2.23 | $1.00 |
| 41 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 489 | $10.00 | $8.00 | $10.00 | $7.00 | $12.00 | $22.30 | $5.00 |
| 42 | Biodegradable erosion control logs (remove) (506-7046) | LF | 489 | $5.00 | $2.00 | $1.00 | $1.00 | $5.00 | $11.15 | $1.00 |
| 43 | Driveways (base) (530-7015) | SY | 47 | $40.00 | $50.00 | $45.00 | $200.00 | $401.33 | $60.00 | |
| 44 | Metal W-beam guard fence (steel post) (540-7002) | LF | 700 | $34.00 | $35.00 | $40.00 | $40.00 | $34.00 | $35.67 | $30.00 |
| 45 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 4 | $2,700.00 | $3,200.00 | $2,500.00 | $2,800.00 | $3,344.40 | $2,500.00 | |
| 46 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 150 | $94.12 | $85.00 | $100.00 | $100.00 | $115.00 | $87.51 | $95.00 |
| 47 | Guardrail end treatment (install) (544-7001) | EACH | 20 | $3,685.00 | $3,600.00 | $4,000.00 | $3,800.00 | $3,500.00 | $1,978.77 | $3,000.00 |
| 48 | Wire fence (type C) (552-7003) | LF | 600 | $27.00 | $28.25 | $25.00 | $30.00 | $72.46 | $25.00 | |
| 49 | Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018) | EACH | 34 | $32.00 | $30.00 | $54.25 | $55.00 | $50.00 | $39.02 | $40.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 8, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way