TxDOT contract A00132273 bid tabulation
Widen Road - Add Lanes And Shoulders, FM 2185 (750 feet south of Looney Spur Road to Junction with FM 3541). Let by Texas DOT on June 4, 2025, Culberson, El Paso District. 4 bids received; low bid $123,682,484 by A. L. Helmcamp, Inc., +17% against the engineer's estimate of $105,998,212.
- Owner
- Texas DOT
- Letting
- 04 JUN 2025
- Pay items
- 123
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | A. L. Helmcamp, Inc. | $123,682,484 | Low | +17% |
| 2 | CK Newberry, LLC | $135,926,769 | +10% | +28% |
| 3 | Dan Williams Company | $144,386,366 | +17% | +36% |
| 4 | Kiewit Infrastructure South Co. | $149,255,443 | +21% | +41% |
Engineer's estimate: $105,998,212.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. A. L. Helmcamp, Inc. | 2. CK Newberry, LLC | 3. Dan Williams Company | 4. Kiewit Infrastructure South Co. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 1,567 | $500.00 | $350.00 | $8,500.00 | $8,155.00 | $729.90 |
| 2 | Remove (6") TRT/untrt base & asphalt pavement (105-7026) | SY | 884 | $5.00 | $12.00 | $15.00 | $4.00 | $13.80 |
| 3 | Excavation (roadway) (110-7001) | CY | 541,518 | $17.00 | $20.00 | $18.00 | $13.50 | $8.20 |
| 4 | Excavation (special) (110-7003) | CY | 80,264 | $37.00 | $30.00 | $20.00 | $28.50 | $38.77 |
| 5 | Embankment (final)(DC)(type C1) (132-7008) | CY | 728,898 | $14.00 | $25.00 | $25.00 | $22.00 | $32.00 |
| 6 | Embankment (final)(DC)(type C2) (132-7010) | CY | 474,915 | $12.50 | $14.00 | $15.00 | $22.00 | $26.50 |
| 7 | Blading (150-7002) | HR | 100 | $300.00 | $295.00 | $500.00 | $225.00 | $232.62 |
| 8 | Bulldozer work (156-7001) | HR | 100 | $275.00 | $266.00 | $600.00 | $145.00 | $534.13 |
| 9 | Proof rolling (216-7001) | HR | 100 | $200.00 | $200.00 | $100.00 | $90.00 | $224.55 |
| 10 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 136,219 | $98.00 | $120.00 | $120.00 | $125.00 | $112.00 |
| 11 | Prime coat (multi option) (310-7015) | GAL | 115,883 | $6.00 | $8.00 | $4.50 | $6.25 | $22.99 |
| 12 | Asphalt (A-R type II) (316-7001) | GAL | 318,401 | $7.00 | $4.70 | $5.00 | $4.50 | $4.51 |
| 13 | Aggregate (type-PB, GR-4)(sac-A) (316-7136) | CY | 5,293 | $175.00 | $145.00 | $150.00 | $145.00 | $162.35 |
| 14 | Aggregate (type-B, GR-3)(sac-B) (316-7171) | CY | 6,446 | $200.00 | $195.00 | $120.00 | $135.00 | $174.63 |
| 15 | Asphalt (multi option) (316-7263) | GAL | 260,481 | $7.00 | $5.00 | $4.00 | $5.50 | $6.05 |
| 16 | Struct excavation (box) (400-7002) | CY | 17,959 | $18.00 | $1.00 | $15.00 | $1.00 | $4.66 |
| 17 | Struct excavation (pipe) (400-7003) | CY | 7,590 | $20.00 | $1.00 | $15.00 | $1.00 | $43.70 |
| 18 | Cem stabil BKFL (400-7010) | CY | 12,242 | $180.00 | $460.00 | $550.00 | $600.00 | $586.01 |
| 19 | Trench excavation protection (402-7001) | LF | 2,561 | $25.00 | $7.00 | $50.00 | $3.00 | $8.52 |
| 20 | Drilled shaft (18 in) (416-7002) | LF | 620 | $350.00 | $400.00 | $500.00 | $330.00 | $388.57 |
| 21 | Drilled shaft (36 in) (416-7006) | LF | 4,772 | $550.00 | $450.00 | $625.00 | $640.00 | $577.73 |
| 22 | Class C concrete (abutment)(HPC) (420-7013) | CY | 329.50 | $1,500.00 | $2,000.00 | $2,700.00 | $1,800.00 | $2,999.41 |
| 23 | Class C concrete (cap)(HPC) (420-7023) | CY | 451.60 | $2,500.00 | $2,100.00 | $2,100.00 | $2,700.00 | $4,500.00 |
| 24 | Class C concrete (column)(HPC) (420-7039) | CY | 155.10 | $5,000.00 | $3,200.00 | $3,000.00 | $2,300.00 | $4,410.28 |
| 25 | Reinforced concrete slab (HPC) (422-7002) | SF | 119,700 | $40.00 | $47.00 | $40.00 | $48.00 | $59.50 |
| 26 | Prestressed concrete girder (TX46) (425-7004) | LF | 8,954.04 | $300.00 | $265.00 | $225.00 | $375.00 | $287.00 |
| 27 | Prestressed concrete girder (TX54) (425-7005) | LF | 7,592.50 | $325.00 | $265.00 | $225.00 | $375.00 | $287.00 |
| 28 | Riprap (concrete)(5 in) (432-7002) | CY | 201 | $747.00 | $1,100.00 | $1,000.00 | $1,250.00 | $1,770.84 |
| 29 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 41,632 | $170.00 | $145.00 | $100.00 | $135.00 | $147.08 |
| 30 | Riprap (stone common)(dry)(18 in) (432-7033) | CY | 3,175 | $185.00 | $150.00 | $125.00 | $150.00 | $131.22 |
| 31 | Riprap (stone common)(dry)(24 in) (432-7034) | CY | 1,683 | $200.00 | $155.00 | $130.00 | $150.00 | $124.00 |
| 32 | Riprap (stone common)(grout)(18 in) (432-7039) | CY | 110 | $220.00 | $320.00 | $275.00 | $600.00 | $1,067.61 |
| 33 | Riprap (special) (432-7053) | CY | 25 | $400.00 | $750.00 | $300.00 | $750.00 | $2,682.27 |
| 34 | Riprap (concrete)(CL B)(RR8&RR9) (432-7055) | CY | 1,563 | $700.00 | $1,100.00 | $1,000.00 | $1,100.00 | $1,220.00 |
| 35 | Rail (type T223)(HPC) (450-7009) | LF | 7,010 | $125.00 | $135.00 | $250.00 | $200.00 | $320.78 |
| 36 | Sealed expansion joint (4 in) (SEJ - M) (454-7004) | LF | 646 | $300.00 | $300.00 | $250.86 | $202.00 | $424.45 |
| 37 | Concrete box culvert (4 FT X 2 FT) (462-7003) | LF | 148 | $450.00 | $450.00 | $425.00 | $500.00 | $718.65 |
| 38 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 630 | $475.00 | $560.00 | $525.00 | $600.00 | $881.55 |
| 39 | Concrete box culvert (6 FT X 4 FT) (462-7012) | LF | 910 | $575.00 | $700.00 | $625.00 | $800.00 | $1,066.38 |
| 40 | Concrete box culvert (7 FT X 3 FT) (462-7015) | LF | 2,473 | $600.00 | $800.00 | $850.00 | $900.00 | $1,140.00 |
| 41 | Concrete box culvert (7 FT X 4 FT) (462-7016) | LF | 2,295 | $625.00 | $850.00 | $900.00 | $1,000.00 | $1,220.00 |
| 42 | Concrete box culvert (7 FT X 5 FT) (462-7017) | LF | 63 | $650.00 | $1,000.00 | $1,000.00 | $1,150.00 | $1,185.25 |
| 43 | Concrete box culvert (8 FT X 4 FT) (462-7021) | LF | 180 | $750.00 | $1,100.00 | $1,050.00 | $1,200.00 | $1,275.88 |
| 44 | Concrete box culvert (8 FT X 6 FT) (462-7023) | LF | 1,686 | $850.00 | $1,200.00 | $1,100.00 | $1,300.00 | $1,860.00 |
| 45 | Concrete box culvert (8 FT X 8 FT) (462-7025) | LF | 1,123 | $910.00 | $1,300.00 | $1,200.00 | $1,500.00 | $2,230.00 |
| 46 | RC pipe (CL III)(24 in) (464-7005) | LF | 4,955 | $150.00 | $125.00 | $130.00 | $130.00 | $125.05 |
| 47 | RC pipe (CL III)(30 in) (464-7007) | LF | 2,842 | $175.00 | $180.00 | $180.00 | $200.00 | $185.14 |
| 48 | RC pipe (CL III)(36 in) (464-7009) | LF | 1,601 | $278.00 | $240.00 | $225.00 | $270.00 | $236.16 |
| 49 | RC pipe (CL IV)(30 in) (464-7023) | LF | 800 | $156.00 | $210.00 | $200.00 | $220.00 | $209.95 |
| 50 | Headwall (CH - FW - 30) (diameter= 36 in) (466-7039) | EACH | 1 | $18,300 | $14,000 | $15,000 | $15,000 | $37,312 |
| 51 | Wingwall (FW - 0) (HW=6 FT) (466-7148) | EACH | 2 | $20,500 | $21,000 | $18,000 | $25,000 | $27,390 |
| 52 | Wingwall (FW - S) (HW=6 FT) (466-7162) | EACH | 2 | $23,600 | $15,000 | $17,000 | $20,000 | $14,514 |
| 53 | Wingwall (FW - S) (HW=8 FT) (466-7164) | EACH | 1 | $27,500 | $43,000 | $40,000 | $50,000 | $53,099 |
| 54 | Wingwall (FW - S) (HW=10 FT) (466-7166) | EACH | 2 | $34,471 | $50,000 | $45,000 | $50,000 | $47,530 |
| 55 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 12 | $16,500 | $51,000 | $45,000 | $45,000 | $40,000 |
| 56 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 17 | $26,000 | $46,000 | $50,000 | $55,000 | $50,000 |
| 57 | Wingwall (PW - 1) (HW=7 FT) (466-7177) | EACH | 1 | $23,600 | $45,000 | $45,000 | $55,000 | $59,366 |
| 58 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 5 | $42,000 | $80,000 | $60,000 | $90,000 | $104,011 |
| 59 | Wingwall (PW - 1) (HW=9 FT) (466-7179) | EACH | 4 | $50,000 | $110,000 | $120,000 | $100,000 | $132,897 |
| 60 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 8 | $66,000 | $115,000 | $160,000 | $150,000 | $239,993 |
| 61 | Set (type I)(S= 4 FT)(HW= 4 FT)(6:1)(C) (467-7073) | EACH | 4 | $9,000.00 | $24,000 | $20,000 | $20,000 | $36,109 |
| 62 | Set (type I)(S= 5 FT)(HW= 5 FT)(3:1)(C) (467-7103) | EACH | 10 | $12,500 | $16,000 | $10,000 | $15,000 | $18,175 |
| 63 | Set (type I)(S= 5 FT)(HW= 5 FT)(4:1)(C) (467-7104) | EACH | 6 | $14,000 | $11,000 | $10,000 | $10,000 | $15,955 |
| 64 | Set (type I)(S= 5 FT)(HW= 5 FT)(6:1)(C) (467-7105) | EACH | 4 | $14,250 | $23,000 | $15,000 | $20,000 | $29,699 |
| 65 | Set (type I)(S= 6 FT)(HW= 7 FT)(4:1)(C) (467-7141) | EACH | 2 | $17,000 | $38,000 | $40,000 | $40,000 | $57,030 |
| 66 | Set (type I)(S= 7 FT)(HW= 5 FT)(3:1)(C) (467-7157) | EACH | 13 | $15,000 | $20,000 | $16,000 | $20,000 | $21,257 |
| 67 | Set (type I)(S= 7 FT)(HW= 5 FT)(4:1)(C) (467-7158) | EACH | 9 | $15,300 | $23,000 | $17,000 | $20,000 | $27,606 |
| 68 | Set (type I)(S= 7 FT)(HW= 5 FT)(6:1)(C) (467-7159) | EACH | 2 | $18,000 | $38,000 | $30,000 | $30,000 | $46,105 |
| 69 | Set (type I)(S= 7 FT)(HW= 6 FT)(3:1)(C) (467-7161) | EACH | 1 | $19,800 | $25,000 | $30,000 | $25,000 | $34,843 |
| 70 | Set (type I)(S= 7 FT)(HW= 6 FT)(4:1)(C) (467-7162) | EACH | 2 | $22,000 | $21,000 | $30,000 | $30,000 | $54,654 |
| 71 | Set (type I)(S= 7 FT)(HW= 7 FT)(3:1)(C) (467-7165) | EACH | 2 | $23,000 | $32,000 | $30,000 | $30,000 | $50,040 |
| 72 | Set (type I)(S= 7 FT)(HW= 7 FT)(4:1)(C) (467-7166) | EACH | 1 | $24,000 | $40,000 | $40,000 | $35,000 | $67,331 |
| 73 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 2 | $1,000.00 | $2,000.00 | $4,000.00 | $4,000.00 | $4,964.46 |
| 74 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 178 | $2,200.00 | $2,000.00 | $3,000.00 | $2,200.00 | $5,750.00 |
| 75 | Set (type II) (30 in) (RCP) (3: 1) (C) (467-7345) | EACH | 35 | $2,500.00 | $2,200.00 | $3,700.00 | $3,200.00 | $6,302.48 |
| 76 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 36 | $3,000.00 | $2,300.00 | $4,500.00 | $3,500.00 | $7,614.22 |
| 77 | Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347) | EACH | 5 | $3,300.00 | $3,300.00 | $6,000.00 | $5,500.00 | $10,644 |
| 78 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 38 | $3,300.00 | $3,200.00 | $6,200.00 | $5,000.00 | $12,585 |
| 79 | Set (type II) (36 in) (RCP) (3: 1) (C) (467-7365) | EACH | 8 | $3,650.00 | $3,000.00 | $5,000.00 | $5,500.00 | $6,917.35 |
| 80 | Set (type II) (36 in) (RCP) (4: 1) (C) (467-7366) | EACH | 15 | $5,000.00 | $3,500.00 | $5,000.00 | $5,500.00 | $8,652.89 |
| 81 | Set (type II) (36 in) (RCP) (6: 1) (C) (467-7367) | EACH | 7 | $6,533.00 | $5,000.00 | $7,000.00 | $8,000.00 | $10,960 |
| 82 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 10 | $6,492.00 | $5,000.00 | $7,000.00 | $7,500.00 | $15,365 |
| 83 | Removing structure (cattle guard) (496-7029) | EACH | 1 | $4,000.00 | $6,000.00 | $6,000.00 | $2,000.00 | $5,858.54 |
| 84 | Mobilization (500-7001) | LS | 1 | $9,400,000 | $11,500,000 | $12,250,000 | $14,000,000 | $11,951,082 |
| 85 | Barricades, signs and traffic handling (502-7001) | MO | 42 | $10,000 | $29,380 | $20,000 | $35,000 | $48,000 |
| 86 | Portable changeable message sign (503-7002) | EACH | 4 | $11,436 | $15,000 | $35,000 | $15,000 | $145,272 |
| 87 | TMA (stationary) (505-7001) | DAY | 330 | $250.00 | $200.00 | $300.00 | $200.00 | $449.14 |
| 88 | TMA (mobile operation) (505-7003) | DAY | 34 | $700.00 | $200.00 | $500.00 | $700.00 | $936.38 |
| 89 | Rock filter dams (install) (type 1) (506-7001) | LF | 1,662 | $45.00 | $48.00 | $40.00 | $37.00 | $43.87 |
| 90 | Rock filter dams (install) (type 2) (506-7002) | LF | 1,380 | $45.50 | $53.00 | $50.00 | $47.00 | $56.06 |
| 91 | Rock filter dams (remove) (506-7011) | LF | 3,042 | $18.50 | $15.00 | $20.00 | $17.00 | $20.11 |
| 92 | Construction exits (install) (type 1) (506-7020) | SY | 1,554 | $34.50 | $20.00 | $25.00 | $24.00 | $28.03 |
| 93 | Construction exits (remove) (506-7024) | SY | 1,554 | $7.50 | $5.00 | $8.00 | $7.50 | $9.14 |
| 94 | Temporary sediment control fence (install) (506-7039) | LF | 18,658 | $5.00 | $5.60 | $5.00 | $5.25 | $6.28 |
| 95 | Temporary sediment control fence (remove) (506-7041) | LF | 18,658 | $2.00 | $1.30 | $1.00 | $1.25 | $1.40 |
| 96 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 1,775 | $8.00 | $11.00 | $10.00 | $8.50 | $10.06 |
| 97 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,775 | $4.00 | $2.30 | $3.00 | $2.25 | $2.75 |
| 98 | Constructing detours (508-7001) | SY | 84,468 | $15.00 | $3.80 | $16.00 | $9.00 | $11.53 |
| 99 | One-way traffic control (flagger cont) (510-7001) | HR | 140 | $12.00 | $55.00 | $200.00 | $100.00 | $184.20 |
| 100 | Intrsct, drvways, & turnout (ACP) (530-7022) | SY | 22,027 | $80.00 | $50.00 | $55.00 | $75.00 | $75.00 |
| 101 | Metal W-beam guard fence (timber post) (540-7001) | LF | 25,393 | $40.00 | $30.00 | $30.00 | $35.00 | $28.75 |
| 102 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 20 | $2,790.00 | $2,500.00 | $2,500.00 | $3,500.00 | $2,454.19 |
| 103 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 1,332 | $60.00 | $120.00 | $125.00 | $125.00 | $120.18 |
| 104 | Metal beam guard fence (long span system) (540-7027) | EACH | 6 | $2,000.00 | $1,600.00 | $1,600.00 | $2,000.00 | $1,523.02 |
| 105 | Guardrail end treatment (install) (544-7001) | EACH | 114 | $4,000.00 | $3,800.00 | $4,000.00 | $4,500.00 | $3,805.91 |
| 106 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 161 | $1,100.00 | $800.00 | $800.00 | $750.00 | $881.75 |
| 107 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 10 | $1,100.00 | $850.00 | $850.00 | $800.00 | $975.09 |
| 108 | Remove SM RD SN sup&AM (644-7073) | EACH | 11 | $250.00 | $120.00 | $110.00 | $150.00 | $110.00 |
| 109 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 137 | $45.00 | $60.00 | $150.00 | $40.00 | $26.03 |
| 110 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 581 | $45.00 | $65.00 | $50.00 | $40.00 | $49.71 |
| 111 | Install object marker assembly (OM-2Y)(WC)GND (658-7056) | EACH | 204 | $65.00 | $80.00 | $80.00 | $75.00 | $68.08 |
| 112 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 9,385 | $2.00 | $1.10 | $1.00 | $2.50 | $2.50 |
| 113 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 136 | $12.00 | $11.00 | $10.00 | $9.75 | $8.78 |
| 114 | Reflectorized profile pavement marking type I(W)6"(solid)(100MIL) (666-7266) | LF | 312,653 | $2.00 | $1.00 | $1.00 | $0.90 | $1.32 |
| 115 | Reflectorized profile pavement marking type I(Y)6"(solid)(100MIL) (666-7270) | LF | 165,962 | $2.00 | $1.00 | $1.00 | $0.90 | $1.32 |
| 116 | Reflectorized profile pavement marking type I(Y)6"(broken)(100MIL) (666-7274) | LF | 21,111 | $2.00 | $1.00 | $1.00 | $0.95 | $1.32 |
| 117 | Pavement sler 6" (666-7347) | LF | 12,304 | $1.00 | $0.50 | $0.50 | $0.45 | $0.55 |
| 118 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 1,295 | $3.00 | $0.80 | $1.00 | $0.75 | $2.75 |
| 119 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 3,177 | $8.00 | $6.50 | $7.00 | $6.00 | $4.94 |
| 120 | Pavement surface preparation for marking (6") (678-7002) | LF | 12,304 | $1.00 | $0.20 | $0.25 | $0.20 | $0.22 |
| 121 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 82 | $6.00 | $2.00 | $2.00 | $1.75 | $3.29 |
| 122 | Filter fabric (2004-7001) | SY | 40 | $30.00 | $8.00 | $150.00 | $75.00 | $34.15 |
| 123 | Geogrid base reinforcement (3018-7001) | SY | 4,224 | $10.00 | $8.00 | $10.00 | $4.00 | $5.63 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.