TxDOT contract A00140254 bid tabulation
Construct Rest Area, IH 10 (IH 10 Approx 3 miles Pecos County Line to .). Let by Texas DOT on August 6, 2026, Crockett, San Angelo District. 6 bids received; low bid $13,741,321 by Ragle Construction, Inc., -31% against the engineer's estimate of $19,998,295.
- Owner
- Texas DOT
- Letting
- 06 AUG 2026
- Pay items
- 111
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ragle Construction, Inc. | $13,741,321 | Low | -31% |
| 2 | Relmco, Inc. | $16,617,786 | +21% | -17% |
| 3 | Allen Keller Company | $17,441,115 | +27% | -13% |
| 4 | CK Newberry, LLC | $17,698,805 | +29% | -11% |
| 5 | A. L. Helmcamp, Inc. | $21,530,035 | +57% | +8.0% |
| 6 | FNF Construction, Inc. | $21,852,939 | +59% | +9.0% |
Engineer's estimate: $19,998,295.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ragle Construction, Inc. | 2. Relmco, Inc. | 3. Allen Keller Company | 4. CK Newberry, LLC | 5. A. L. Helmcamp, Inc. | 6. FNF Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 121 | $6,000.00 | $10,500 | $2,500.00 | $2,119.57 | $2,500.00 | $5,000.00 | $10,000 |
| 2 | Remove (15"-19") TRT/untrt base & asphalt pavement (105-7015) | SY | 6,385 | $30.00 | $10.80 | $5.00 | $22.09 | $15.00 | $34.00 | $14.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 34,963 | $20.00 | $11.00 | $15.00 | $21.69 | $15.00 | $19.00 | $15.00 |
| 4 | Embankment (final)(DC)(type B) (132-7004) | CY | 70,118 | $40.00 | $11.00 | $21.00 | $32.92 | $25.00 | $22.00 | $23.25 |
| 5 | Drill seed (permanent_rural_clay) (164-7010) | SY | 186,168 | $0.50 | $0.10 | $0.23 | $0.22 | $0.25 | $0.22 | $0.17 |
| 6 | Drill seed (temporary_warm) (164-7013) | SY | 93,086 | $0.50 | $0.10 | $0.19 | $0.18 | $0.15 | $0.18 | $0.15 |
| 7 | Drill seed (temporary_cool) (164-7014) | SY | 93,086 | $0.50 | $0.10 | $0.19 | $0.18 | $0.15 | $0.18 | $0.15 |
| 8 | Vegetative watering (168-7001) | TGL | 3,133 | $200.00 | $5.00 | $50.00 | $39.90 | $15.00 | $40.00 | $70.00 |
| 9 | Cement (275-7001) | TON | 356 | $275.00 | $300.00 | $300.00 | $314.08 | $300.00 | $350.00 | $380.00 |
| 10 | Cement TRT (existing material & new base)(6") (275-7006) | SY | 36,978 | $3.50 | $2.30 | $3.00 | $4.51 | $2.00 | $6.20 | $6.75 |
| 11 | Cement TRT (existing material & new base)(8") (275-7007) | SY | 13,633 | $2.00 | $2.40 | $3.00 | $5.10 | $3.00 | $7.20 | $6.75 |
| 12 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 10,234 | $8.00 | $5.00 | $5.00 | $7.65 | $5.00 | $7.00 | $6.00 |
| 13 | D-GR HMA type-B PG64-22 (341-7001) | TON | 8,087 | $150.00 | $135.00 | $189.00 | $191.90 | $155.00 | $192.00 | $140.00 |
| 14 | D-GR HMA type-B PG70-22 (341-7006) | TON | 1,949 | $200.00 | $142.00 | $194.00 | $198.96 | $165.00 | $238.00 | $147.00 |
| 15 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 1,548 | $200.00 | $167.00 | $215.00 | $222.52 | $200.00 | $255.00 | $166.00 |
| 16 | Tack coat (344-7077) | GAL | 708 | $10.00 | $11.00 | $7.00 | $24.62 | $5.00 | $15.00 | $6.50 |
| 17 | Concrete pavement (CRCP) (9") (360-7003) | SY | 36,488 | $150.00 | $80.00 | $155.00 | $119.49 | $140.00 | $172.00 | $230.00 |
| 18 | Flowable backfill (401-7001) | CY | 645 | $300.00 | $250.00 | $175.00 | $280.18 | $200.00 | $350.00 | $700.00 |
| 19 | Temporary special shoring (403-7001) | SF | 990 | $50.00 | $49.00 | $35.00 | $22.78 | $22.00 | $75.00 | $60.00 |
| 20 | Drilled shaft (42 in) (416-7007) | LF | 114 | $700.00 | $485.00 | $521.38 | $683.38 | $525.00 | $700.00 | $700.00 |
| 21 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 94 | $300.00 | $255.00 | $274.13 | $383.10 | $225.00 | $220.00 | $225.00 |
| 22 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 424 | $400.00 | $305.00 | $327.88 | $497.00 | $325.00 | $550.00 | $325.00 |
| 23 | Riprap (concrete)(4 in) (432-7001) | CY | 8 | $1,100.00 | $682.00 | $800.00 | $1,340.06 | $800.00 | $2,200.00 | $1,600.00 |
| 24 | Riprap (concrete)(5 in) (432-7002) | CY | 158 | $800.00 | $504.00 | $560.00 | $678.03 | $800.00 | $1,000.00 | $1,300.00 |
| 25 | Riprap (concrete)(dissipater) (432-7011) | CY | 6 | $1,400.00 | $713.00 | $1,500.00 | $1,641.78 | $1,000.00 | $3,000.00 | $6,500.00 |
| 26 | Riprap (mow strip)(4 in) (432-7013) | CY | 43 | $750.00 | $662.00 | $575.00 | $861.08 | $1,000.00 | $1,000.00 | $1,400.00 |
| 27 | Concrete box culvert (9 FT X 5 FT) (462-7027) | LF | 105 | $1,800.00 | $919.00 | $1,476.50 | $1,736.38 | $2,500.00 | $2,000.00 | $1,400.00 |
| 28 | Concrete box culvert (6 FT X 3 FT)(extend) (462-7066) | LF | 126 | $1,100.00 | $580.00 | $727.50 | $1,131.24 | $1,000.00 | $1,000.00 | $1,300.00 |
| 29 | Concrete box culvert (7 FT X 3 FT)(extend) (462-7070) | LF | 180 | $1,200.00 | $607.00 | $757.50 | $1,296.04 | $1,200.00 | $1,200.00 | $1,300.00 |
| 30 | Concrete box culvert (9 FT X 5 FT)(extend) (462-7082) | LF | 171 | $1,500.00 | $930.00 | $772.50 | $1,772.63 | $2,250.00 | $2,200.00 | $1,700.00 |
| 31 | RC pipe (CL III)(24 in) (464-7005) | LF | 53 | $150.00 | $203.00 | $128.25 | $346.53 | $140.00 | $90.00 | $200.00 |
| 32 | RC pipe (CL III)(30 in) (464-7007) | LF | 188 | $200.00 | $177.00 | $157.50 | $376.95 | $180.00 | $130.00 | $200.00 |
| 33 | Inlet (complete)(PSL)(FG)(4FTX4FT-4FTX4FT) (465-7128) | EACH | 1 | $10,000 | $9,245.00 | $12,985 | $12,338 | $8,000.00 | $6,000.00 | $8,000.00 |
| 34 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 3 | $40,000 | $27,208 | $48,075 | $49,182 | $50,000 | $95,000 | $36,000 |
| 35 | Set (type I)(S= 6 FT)(HW= 4 FT)(6:1)(C) (467-7130) | EACH | 1 | $10,000 | $29,000 | $23,626 | $34,908 | $30,000 | $26,000 | $24,000 |
| 36 | Set (type I)(S= 7 FT)(HW= 4 FT)(6:1)(C) (467-7155) | EACH | 1 | $20,000 | $30,000 | $23,625 | $36,979 | $32,000 | $28,000 | $27,000 |
| 37 | Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327) | EACH | 1 | $3,000.00 | $2,000.00 | $2,410.50 | $5,728.70 | $2,000.00 | $3,000.00 | $2,500.00 |
| 38 | Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347) | EACH | 4 | $6,500.00 | $5,200.00 | $2,760.00 | $2,974.17 | $3,000.00 | $3,900.00 | $4,500.00 |
| 39 | Clean existing culverts (480-7001) | EACH | 3 | $6,000.00 | $2,413.00 | $3,500.00 | $6,595.78 | $6,500.00 | $3,200.00 | $44,000 |
| 40 | Removing structure (wingwall) (496-7005) | EACH | 3 | $4,000.00 | $1,375.00 | $1,200.00 | $6,497.90 | $4,000.00 | $1,200.00 | $1,100.00 |
| 41 | Removing structure (box culvert) (496-7008) | LF | 73 | $100.00 | $89.00 | $150.00 | $302.51 | $100.00 | $80.00 | $125.00 |
| 42 | Mobilization (500-7001) | LS | 1 | $2,000,000 | $1,190,000 | $1,300,000 | $1,660,001 | $1,750,000 | $1,900,000 | $2,175,780 |
| 43 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $10,000 | $100,000 | $4,500.00 | $9,483.93 | $10,000 | $23,500 | $33,946 |
| 44 | Portable changeable message sign (503-7002) | EACH | 5 | $15,000 | $15,400 | $15,000 | $45,228 | $10,000 | $15,000 | $11,900 |
| 45 | Rock filter dams (install) (type 4) (506-7004) | LF | 176 | $150.00 | $50.00 | $55.00 | $51.77 | $50.00 | $52.00 | $98.00 |
| 46 | Rock filter dams (remove) (506-7011) | LF | 176 | $50.00 | $15.00 | $16.50 | $15.53 | $15.00 | $16.00 | $27.00 |
| 47 | Construction exits (install) (type 1) (506-7020) | SY | 448 | $60.00 | $38.00 | $41.80 | $39.35 | $38.00 | $40.00 | $90.00 |
| 48 | Construction exits (remove) (506-7024) | SY | 448 | $30.00 | $11.00 | $12.10 | $11.39 | $11.00 | $10.00 | $16.00 |
| 49 | Temporary sediment control fence (install) (506-7039) | LF | 5,836 | $10.00 | $4.25 | $4.68 | $4.40 | $4.25 | $4.50 | $7.00 |
| 50 | Temporary sediment control fence (remove) (506-7041) | LF | 5,836 | $5.00 | $1.00 | $1.10 | $1.04 | $1.00 | $1.00 | $1.30 |
| 51 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 1,140 | $7.50 | $10.00 | $11.00 | $10.35 | $10.00 | $11.00 | $16.50 |
| 52 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,140 | $3.50 | $3.00 | $3.30 | $3.11 | $3.00 | $3.00 | $1.25 |
| 53 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 15,090 | $30.00 | $47.00 | $42.00 | $49.77 | $75.00 | $105.00 | $40.00 |
| 54 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 3,030 | $20.00 | $7.40 | $8.00 | $11.81 | $20.00 | $34.00 | $3.50 |
| 55 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 15,090 | $15.00 | $16.30 | $42.00 | $10.53 | $60.00 | $68.00 | $5.50 |
| 56 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 5,212 | $5.00 | $2.25 | $0.75 | $1.56 | $3.00 | $3.00 | $1.00 |
| 57 | Metal W-beam guard fence (timber post) (540-7001) | LF | 551 | $45.00 | $27.75 | $29.83 | $28.73 | $30.00 | $47.00 | $30.00 |
| 58 | Downstream anchor terminal section (540-7015) | EACH | 3 | $2,500.00 | $1,649.75 | $1,773.48 | $1,708.19 | $1,800.00 | $2,000.00 | $1,800.00 |
| 59 | Remove metal beam guard fence (542-7001) | LF | 188 | $25.00 | $3.25 | $3.49 | $3.37 | $3.25 | $5.30 | $4.00 |
| 60 | Remove downstream anchor terminal (542-7003) | EACH | 1 | $1,500.00 | $225.00 | $241.87 | $232.99 | $225.00 | $430.00 | $240.00 |
| 61 | Guardrail end treatment (install) (544-7001) | EACH | 3 | $4,250.00 | $3,449.75 | $3,708.48 | $3,571.95 | $3,500.00 | $4,800.00 | $3,600.00 |
| 62 | Guardrail end treatment (remove) (544-7003) | EACH | 1 | $2,000.00 | $274.75 | $295.36 | $284.48 | $275.00 | $430.00 | $300.00 |
| 63 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 2 | $1,300.00 | $1,113.00 | $322.50 | $638.83 | $2,500.00 | $1,200.00 | $600.00 |
| 64 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $635.00 | $916.00 | $322.50 | $639.24 | $1,500.00 | $1,200.00 | $2,500.00 |
| 65 | Cca (install)(N)(TL3)(work zone) (545-7018) | EACH | 4 | $10,500 | $7,572.00 | $8,500.00 | $958.66 | $20,000 | $10,000 | $14,000 |
| 66 | Chain link fence (install) (8') (550-7005) | LF | 6,422 | $60.00 | $54.75 | $58.85 | $56.69 | $55.00 | $55.00 | $60.00 |
| 67 | Wire fence (remove) (552-7011) | LF | 6,338 | $10.00 | $3.50 | $3.76 | $2.96 | $3.50 | $5.00 | $5.50 |
| 68 | In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124) | EACH | 53 | $6,500.00 | $4,900.00 | $5,267.50 | $5,901.89 | $5,000.00 | $6,100.00 | $5,000.00 |
| 69 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 13,180 | $10.00 | $17.00 | $18.28 | $17.60 | $20.00 | $18.00 | $18.00 |
| 70 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 4,270 | $40.00 | $18.00 | $19.35 | $19.67 | $18.00 | $20.00 | $19.00 |
| 71 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 520 | $35.00 | $19.00 | $20.43 | $22.78 | $19.00 | $24.00 | $20.00 |
| 72 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 475 | $50.00 | $35.00 | $37.63 | $54.88 | $35.00 | $56.00 | $37.00 |
| 73 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 355 | $60.00 | $40.00 | $43.00 | $61.09 | $40.00 | $62.00 | $42.00 |
| 74 | Electrical conductor (no.8) bare (620-7007) | LF | 16,810 | $4.00 | $1.70 | $1.83 | $2.07 | $1.75 | $2.20 | $2.00 |
| 75 | Electrical conductor (no.8) insulated (620-7008) | LF | 41,400 | $1.50 | $2.15 | $2.31 | $2.33 | $2.25 | $2.40 | $2.25 |
| 76 | Ground box type A (122311)W/apron (624-7002) | EACH | 11 | $2,500.00 | $1,000.00 | $1,075.00 | $1,863.76 | $1,000.00 | $1,900.00 | $1,400.00 |
| 77 | Ground box type D (162922)W/apron (624-7008) | EACH | 16 | $3,000.00 | $1,200.00 | $1,290.00 | $2,381.47 | $1,200.00 | $2,400.00 | $1,700.00 |
| 78 | Elc SRV type D 120/240 060(NS)GS(N)SP(O) (628-7136) | EACH | 3 | $5,000.00 | $9,500.00 | $10,213 | $7,869.19 | $9,500.00 | $8,000.00 | $14,000 |
| 79 | Aluminum signs (type A) (636-7001) | SF | 32 | $75.00 | $27.00 | $29.03 | $34.17 | $26.50 | $35.00 | $35.00 |
| 80 | Aluminum signs (type G) (636-7002) | SF | 828 | $50.00 | $28.00 | $30.10 | $44.53 | $32.25 | $40.00 | $40.00 |
| 81 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $2,000.00 | $921.84 | $913.75 | $1,206.19 | $850.00 | $1,200.00 | $1,200.00 |
| 82 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 4 | $1,700.00 | $1,062.08 | $1,612.50 | $1,698.08 | $1,500.00 | $1,800.00 | $1,700.00 |
| 83 | Install LRSS (struct steel) (647-7001) | LB | 6,281 | $10.00 | $8.78 | $8.60 | $6.48 | $7.25 | $8.20 | $8.00 |
| 84 | Work zone pavement marking non-removing (W)4"(solid) (662-7004) | LF | 15,182 | $2.50 | $0.60 | $0.65 | $0.42 | $0.40 | $0.45 | $0.50 |
| 85 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 889 | $2.00 | $2.65 | $2.85 | $0.73 | $0.70 | $0.75 | $0.75 |
| 86 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,772 | $2.00 | $1.45 | $1.56 | $0.92 | $0.90 | $0.95 | $1.00 |
| 87 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 1,430 | $5.00 | $6.30 | $6.77 | $4.14 | $4.00 | $4.50 | $4.25 |
| 88 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 4 | $500.00 | $830.00 | $892.25 | $186.38 | $180.00 | $190.00 | $185.00 |
| 89 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 2,933 | $1.50 | $0.75 | $0.81 | $0.36 | $0.35 | $0.38 | $0.40 |
| 90 | Reflectorized pavement marking type II (W) 6" (DOT) (666-7173) | LF | 889 | $1.50 | $1.85 | $1.99 | $0.42 | $0.40 | $0.43 | $0.45 |
| 91 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 16,918 | $1.50 | $0.45 | $0.50 | $0.36 | $0.35 | $0.38 | $0.40 |
| 92 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 6,166 | $2.50 | $0.60 | $0.70 | $0.57 | $0.55 | $0.60 | $0.60 |
| 93 | Reflectorized pavement marking type II (W) 12" (solid) (666-7182) | LF | 1,430 | $5.00 | $2.25 | $2.42 | $1.55 | $1.50 | $1.60 | $1.60 |
| 94 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 4 | $300.00 | $290.00 | $311.75 | $31.07 | $30.00 | $32.00 | $32.00 |
| 95 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 4,985 | $1.50 | $0.45 | $0.48 | $0.36 | $0.35 | $0.40 | $0.40 |
| 96 | Type I high perf PM (W)4"(solid)(100MIL) (666-7287) | LF | 6,787 | $2.00 | $2.75 | $2.96 | $0.73 | $0.70 | $0.75 | $0.80 |
| 97 | Type I high perf PM (W)6"(broken)(100MIL) (666-7290) | LF | 2,933 | $1.50 | $1.40 | $1.51 | $0.77 | $0.75 | $0.80 | $0.80 |
| 98 | Type I high perf PM (W)6"(solid)(100MIL) (666-7293) | LF | 16,918 | $1.50 | $1.05 | $1.13 | $0.73 | $0.70 | $0.75 | $0.80 |
| 99 | Type I high perf PM (Y)6"(solid)(100MIL) (666-7305) | LF | 4,985 | $1.50 | $1.05 | $1.13 | $0.77 | $0.75 | $0.80 | $0.80 |
| 100 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 399 | $10.00 | $7.00 | $7.53 | $4.14 | $4.00 | $4.50 | $4.25 |
| 101 | Pavement surface preparation for marking (4") (678-7001) | LF | 6,787 | $0.60 | $0.95 | $1.02 | $0.35 | $0.35 | $0.40 | $0.40 |
| 102 | Pavement surface preparation for marking (6") (678-7002) | LF | 18,603 | $0.60 | $0.95 | $1.02 | $0.36 | $0.35 | $0.40 | $0.40 |
| 103 | Pavement surface preparation for marking (12") (678-7006) | LF | 887 | $0.60 | $3.00 | $3.23 | $1.04 | $1.00 | $1.20 | $1.25 |
| 104 | System integration (6009-7001) | LS | 1 | $75,000 | $15,000 | $16,125 | $4,555.85 | $15,000 | $5,000.00 | $22,000 |
| 105 | ITS pole (50 FT) (90 MPH) (6011-7005) | EACH | 2 | $25,000 | $15,000 | $16,125 | $19,362 | $15,000 | $20,000 | $16,000 |
| 106 | ITS pole MNT cab (type 2) (conf 2) (6011-7011) | EACH | 4 | $9,000.00 | $8,100.00 | $8,707.50 | $7,144.40 | $8,100.00 | $7,500.00 | $9,000.00 |
| 107 | ITS pole MNT cab (type 1)(conf 2) (6011-7017) | EACH | 4 | $11,150 | $6,900.00 | $7,417.50 | $7,040.86 | $6,900.00 | $7,200.00 | $7,500.00 |
| 108 | ITS pole (30 FT)(90 MPH) (6011-7019) | EACH | 4 | $12,000 | $10,500 | $11,288 | $12,943 | $11,000 | $13,000 | $11,000 |
| 109 | Installation of cellular modem (6015-7001) | EACH | 4 | $2,400.00 | $950.00 | $1,021.25 | $517.71 | $1,000.00 | $550.00 | $1,006.00 |
| 110 | CCTV field equipment (digital) (6018-7002) | EACH | 2 | $7,500.00 | $9,945.00 | $10,691 | $14,082 | $10,000 | $15,000 | $15,000 |
| 111 | ITS system support equipment (6037-7001) | LS | 1 | $67,845 | $19,500 | $20,963 | $38,725 | $20,000 | $40,000 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 6, 2026. Compiled by Mirage Metrics.