TxDOT contract A00178374 bid tabulation

Bridge Replacement, S BURTON RD (S. BURTON RD @ SANDY CREEK to (STR#201810AA0237001)). Let by Texas DOT on May 7, 2026, Orange, Beaumont District. 3 bids received; low bid $1,783,411 by Skyline Bridge LLC, +0.2% against the engineer's estimate of $1,780,485.

Owner
Texas DOT
Letting
07 MAY 2026
Pay items
55
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Skyline Bridge LLC$1,783,411Low0.0%
2Hodges and Son Construction Company, Inc.$1,972,581+11%+11%
3Garret Shields Infrastructure$2,067,591+16%+16%
TxDOT contract A00178374: bids by rank

Engineer's estimate: $1,780,485.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Skyline Bridge LLC2. Hodges and Son Construction Company, Inc.3. Garret Shields Infrastructure
1Preparing row (100-7002)STA12.10$2,000.00$1,500.00$7,520.00$1,000.00
2Remove (3"-7") TRT/untrt base & asphalt pavement (105-7003)SY1,329$8.00$8.00$2.00$10.00
3Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006)SY907$14.00$25.00$10.00
4Excavation (roadway) (110-7001)CY522$12.00$14.50$15.00$30.00
5Excavation (channel) (110-7002)CY710$25.00$12.00$15.00$30.00
6Embankment (final)(OC)(type C) (132-7005)CY1,368$40.00$30.00$25.00$40.00
7Embankment (final)(DC)(type C) (132-7006)CY391$20.00$45.00$25.00$40.00
8Broadcast seed (permanent_rural_sand) (164-7001)SY3,172$1.00$1.25$2.00$0.15
9Broadcast seed (permanent_urban_sand) (164-7003)SY655$1.60$2.00$0.25
10Broadcast seed (permanent_urban_clay) (164-7004)SY656$1.60$2.00$0.10
11Vegetative watering (168-7001)TGL31$25.00$1.00$1.00$50.00
12FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY561$80.00$175.00$130.00$130.00
13Prime coat (AE-P) (310-7001)GAL577$8.00$22.00$10.00$5.00
14Asphalt (AC-20-5TR or AC-20XP) (316-7067)GAL1,190$3.50$16.00$15.00$5.00
15Aggregate (type-PB or PL, GR-4)(sac-A) (316-7241)CY31$500.00$1,500.00$1,500.00$300.00
16D-GR HMA type D PG 64-22 (exempt) (341-7064)TON385$140.00$375.00$200.00$200.00
17Tack coat (341-7082)GAL174$4.00$10.00$8.00$20.00
18Cem stabil BKFL (400-7010)CY177$130.00$250.00$300.00$200.00
19Drilled shaft (24 in) (416-7004)LF828$200.00$165.00$190.00$200.00
20Drilled shaft (30 in) (416-7005)LF348$205.00$260.00$300.00
21Class C concrete (abutment) (420-7012)CY69$1,200.00$1,200.00$1,600.00$1,000.00
22Reinforced concrete slab (box beam) (422-7005)SF1,832$22.00$28.00$30.00
23Reinforced concrete slab (slab beam) (422-7007)SF2,804$31.00$21.00$28.00$30.00
24Approach slab (422-7013)CY123$725.00$775.00$800.00$1,000.00
25Shear key (422-7020)CY18.70$600.00$800.00$1,000.00
26Prestressed concrete slab beam (5SB15) (425-7019)LF545$275.00$340.00$320.00$300.00
27Prestressed concrete box beam (4B28) (425-7028)LF278$400.00$380.00$400.00
28Prestressed concrete box beam (5B28) (425-7029)LF139$335.00$380.00$500.00
29Riprap (stone protection)(18 in) (432-7043)CY275$190.00$167.00$250.00$200.00
30Rail (type T223) (450-7008)LF428$100.00$116.00$180.00$150.00
31Armor joint (sealed) (454-7003)LF163$150.00$100.00$180.00$200.00
32RC pipe (CL III)(18 in) (464-7003)LF20$90.00$80.00$80.00
33RC pipe (CL III)(24 in) (464-7005)LF20$110.00$85.00$120.00
34Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH2$930.00$3,000.00$1,500.00
35Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH2$1,350.00$3,000.00$2,500.00
36Removing structure (bridge 0 - 99 FT length) (496-7009)EACH3$20,000$11,500$20,000$25,000
37Removing structure (pipe) (496-7037)EACH2$150.00$500.00$1,000.00
38Mobilization (500-7001)LS1$150,000$175,000$100,000
39Barricades, signs and traffic handling (502-7001)MO15$5,000.00$1,745.00$4,000.00$20,000
40Portable changeable message sign (503-7001)DAY21$175.00$124.75$75.00$100.00
41Rock filter dams (install) (type 2) (506-7002)LF232$50.00$10.00$1.00$20.00
42Rock filter dams (remove) (506-7011)LF232$20.00$1.00$1.00$10.00
43Temporary sediment control fence (install) (506-7039)LF2,511$8.00$3.00$1.00$5.00
44Temporary sediment control fence (remove) (506-7041)LF2,511$6.00$1.00$1.00$1.00
45Driveways (base) (530-7015)SY148$35.00$65.70$70.00$30.00
46Metal W-beam guard fence (timber post) (540-7001)LF262.50$25.00$25.75$25.00$18.00
47Metal beam guard fence trans (thrie-beam) (540-7005)EACH9$2,050.00$1,725.00$1,600.00$1,500.00
48Downstream anchor terminal section (540-7015)EACH2$1,500.00$1,450.00$1,600.00$1,000.00
49Guardrail end treatment (install) (544-7001)EACH7$3,500.00$3,300.00$3,500.00$3,500.00
50Crash cushion attenuator (install)(L)(N)(TL2) (545-7005)EACH2$24,000$10,000$18,000
51Relocate existing mailbox (560-7012)EACH3$400.00$250.00$500.00$500.00
52Remove SM RD SN sup&AM (644-7073)EACH6$105.00$100.00$50.00$100.00
53Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH6$30.00$25.00$40.00$10.00
54Install delineator assembly (D-DW)SZ 1(BRF)GF2 (658-7048)EACH12$40.00$50.00$40.00$30.00
55Remove delin & object marker assms (658-7078)EACH2$25.00$500.00$10.00
TxDOT contract A00178374: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy