TxDOT contract A00183926 bid tabulation

Rehabilitate Existing Roadway, FM 46 (SH 6 to Robertson CL). Let by Texas DOT on February 7, 2025, Falls, Waco District. 6 bids received; low bid $3,949,757 by Big Creek Construction, LTD., -20% against the engineer's estimate of $4,914,109.

Owner
Texas DOT
Letting
07 FEB 2025
Pay items
75
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Big Creek Construction, LTD.$3,949,757Low-20%
2Texas Materials Group, Inc.$4,117,509+4.0%-16%
3Knife River Corporation - South$4,146,002+5.0%-16%
4CDM Holdings$4,206,742+7.0%-14%
5A. L. Helmcamp, Inc.$4,621,813+17%-6.0%
6Lakey, Inc.$6,026,364+53%+23%
TxDOT contract A00183926: bids by rank

Engineer's estimate: $4,914,109.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Big Creek Construction, LTD.2. Texas Materials Group, Inc.3. Knife River Corporation - South4. CDM Holdings5. A. L. Helmcamp, Inc.6. Lakey, Inc.
1Preparing row (100-7002)STA149.20$1,000.00$750.00$535.00$650.00$500.00$750.00$1,300.00
2Removing concrete (riprap) (104-7006)SY52$60.00$35.00$50.00$30.00$21.00$83.00$26.38
3Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006)SY1,795$20.00$12.00$25.00$4.00$12.50$20.00$18.00
4Excavation (roadway) (110-7001)CY1,862$20.00$15.00$27.00$15.00$22.00$8.00$16.00
5Embankment (final)(DC)(type B) (132-7004)CY7,913$25.00$25.00$32.00$25.00$35.00$30.00$65.00
6Spec excavation work (backhoe) (158-7001)HR4$200.00$200.00$176.00$300.00$160.00$116.00$125.00
7Furn & place topsoil (4") (160-7002)SY79,279$2.00$0.60$0.46$0.50$1.00$0.70$3.20
8Drill seed (permanent_rural_clay) (164-7010)SY79,279$0.33$0.25$0.18$0.18$0.26$0.18$0.40
9Drill seed (temporary_warm_cool) (164-7015)SY79,279$0.33$0.25$0.16$0.16$0.23$0.16$0.28
10Vegetative watering (168-7001)TGL1,290$34.00$5.00$37.00$1.00$25.00$5.00$34.50
11FL BS (compacted in place)(tyd GR1-2)(final pos) (247-7188)CY9,116$72.50$60.00$58.50$63.00$52.00$70.00$45.00
12FL BS (roadway del)(type D GR 3)(final pos) (247-7272)CY5,998$75.00$50.00$37.00$44.00$50.00$52.00$133.00
13Rework BS metal (type C)(8")(ord comp) (251-7051)SY56,366$2.20$1.50$0.90$2.50$2.00$1.00$8.00
14Cement (275-7001)TON537$250.00$250.00$230.00$240.00$237.00$250.00$236.25
15Cement TRT (existing material)(6") (275-7002)SY56,366$2.00$3.00$2.75$2.50$2.75$5.00$4.22
16Emuls asphalt (BS or subgr TRT)(CSS-1H) (314-7004)GAL65,646$5.20$3.00$3.60$2.00$3.50$4.75$12.60
17Fog seal (CSS-1H) (315-7004)GAL5,475$4.50$5.00$4.55$3.70$3.00$4.75$2.59
18Asphalt (CRS-2) (316-7011)GAL33,923$3.75$3.00$3.30$3.00$3.70$4.25$4.28
19Aggregate (type-D or L, GR-4) (316-7253)CY417$280.00$125.00$180.00$185.00$200.00$275.00$133.00
20SP mixes SP-C sac-B PG70-22 (344-7021)TON5,834$120.00$100.00$143.00$125.00$145.00$110.00$134.50
21Tack coat (344-7077)GAL5,311$2.00$3.00$2.90$2.50$3.00$3.50$4.48
22Cut & restore asphalt paving (400-7008)SY48$275.00$200.00$250.00$150.00$140.00$50.00$157.95
23Cem stabil BKFL (400-7010)CY54$300.00$200.00$200.00$283.00$275.00$273.00$225.00
24Trench excavation protection (402-7001)LF118$50.00$10.00$8.00$8.70$90.00$8.50$10.00
25Class C concrete (miscellaneous) (420-7067)CY3.29$2,500.00$7,000.00$2,500.00$6,500.00$4,000.00$6,350.00$1,507.50
26Riprap (mow strip)(4 in) (432-7013)CY122.20$650.00$750.00$675.00$640.00$600.00$623.00$700.00
27Riprap (stone protection)(18 in) (432-7043)CY108.83$245.00$200.00$300.00$235.00$222.00$233.00$185.00
28Miscellaneous non-bridge (nbis) (442-7017)LB96$30.00$25.00$7.00$10.00$150.00$8.00$90.00
29RC pipe (CL III)(18 in) (464-7003)LF804$90.00$90.00$65.00$101.00$70.00$98.00$90.00
30RC pipe (CL III)(24 in) (464-7005)LF152$120.00$125.00$150.00$150.00$95.00$145.00$114.57
31RC pipe (CL III)(36 in) (464-7009)LF64$220.00$175.00$300.00$217.00$172.00$210.00$185.56
32Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307)EACH8$1,700.00$1,250.00$1,000.00$1,423.00$859.00$1,375.00$1,620.00
33Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH46$1,700.00$1,250.00$1,000.00$1,482.00$872.00$1,430.00$1,569.58
34Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH2$1,800.00$1,400.00$2,000.00$1,458.00$1,340.00$1,410.00$1,597.50
35Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH6$2,000.00$1,600.00$2,500.00$1,707.00$1,440.00$1,650.00$1,924.07
36Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368)EACH4$4,000.00$6,000.00$4,500.00$5,865.00$4,809.00$5,665.00$6,910.47
37Clean existing culverts (480-7001)EACH4$2,500.00$2,500.00$2,500.00$2,338.00$2,500.00$2,260.00$4,750.00
38Removing structure (set) (496-7004)EACH12$700.00$500.00$750.00$638.00$650.00$620.00$704.25
39Removing structure (pipe) (496-7007)LF786$44.00$15.00$30.00$13.00$30.00$13.00$20.00
40Mobilization (500-7001)LS1$350,000$390,000$320,000$395,000$300,000$350,000$113,500
41Barricades, signs and traffic handling (502-7001)MO11$7,500.00$5,000.00$2,440.00$14,000$8,000.00$17,000$5,000.00
42Portable changeable message sign (503-7002)EACH2$13,000$10,250$3,000.00$15,000$6,500.00$10,000$9,150.00
43TMA (stationary) (505-7001)DAY196$300.00$225.00$10.00$100.00$100.00$250.00$205.00
44TMA (mobile operation) (505-7002)HR100$65.00$60.00$40.00$25.00$55.00$50.00$61.25
45Rock filter dams (install) (type 2) (506-7002)LF600$52.00$35.00$36.00$47.00$46.00$38.00$40.00
46Rock filter dams (remove) (506-7011)LF600$15.00$10.00$10.00$12.00$10.50$10.00$10.00
47Temporary sediment control fence (install) (506-7039)LF10,026$5.30$3.50$4.00$4.00$6.15$3.15$4.00
48Temporary sediment control fence (remove) (506-7041)LF10,026$1.30$1.00$0.35$1.05$1.10$1.05$1.25
49Driveways (ACP) (type 1) (530-7011)SY1,795$70.00$50.00$108.00$63.00$40.00$90.00$49.50
50Turnouts (ACP) (530-7018)SY164$100.00$50.00$26.00$75.00$55.00$95.00$90.00
51Mill rumble strips (asphalt) (shoulder) (533-7001)LF29,545$0.50$0.25$0.36$0.30$0.19$0.30$0.25
52Mill rumble strips (asphalt) (centerline) (533-7002)LF14,630$0.40$0.50$0.42$0.30$0.39$0.30$0.35
53Metal W-beam guard fence (steel post) (540-7002)LF1,325$35.00$35.00$30.00$32.00$30.00$32.00$31.00
54Guardrail end treatment (install) (544-7001)EACH12$3,300.00$3,000.00$2,877.50$3,100.00$2,960.00$3,025.00$2,877.50
55Mailbox install-S (TWG-post) type 2 (560-7002)EACH3$390.00$200.00$190.00$206.00$230.00$200.00$306.18
56Mailbox install-D (TWG-post) type 2 (560-7003)EACH1$420.00$250.00$215.00$233.00$271.00$225.00$340.20
57Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH4$1,100.00$800.00$775.00$842.00$940.00$815.00$765.00
58Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026)EACH1$1,500.00$1,000.00$990.00$1,076.00$1,092.00$1,040.00$652.50
59Install small roadside sign support and assembly tytwt(1)WS(P) (644-7057)EACH35$700.00$500.00$495.00$538.00$490.00$520.00$512.29
60Install small roadside sign support and assembly tytwt(1)WS(T) (644-7058)EACH2$750.00$600.00$550.00$598.00$663.00$575.00$587.50
61Remove SM RD SN sup&AM (644-7073)EACH28$150.00$100.00$100.00$105.00$125.00$105.00$115.00
62Relocate SM RD SN sup & AM type temporary (644-7077)EACH9$350.00$500.00$550.00$250.00$250.00$315.00$600.00
63Install delineator assembly (D-SW)SZ 1(WFLX)GF2(BI) (658-7002)EACH24$50.00$50.00$45.00$49.00$46.00$48.00$125.00
64Install object marker assembly (OM-2X)(WC)GND (658-7055)EACH8$25.00$50.00$90.00$54.00$51.00$55.00$2.50
65Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF30,815$0.50$0.42$0.34$0.46$0.32$0.44$0.44
66Work zone pavement marking non-removing (Y)6"(broken) (662-7036)LF2,560$0.50$0.42$0.34$0.46$0.32$0.44$0.33
67Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF15,813$0.50$0.42$0.34$0.46$0.32$0.44$0.41
68Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH1,559$2.50$1.50$1.01$1.50$1.00$1.00$1.00
69Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF88$12.00$25.00$16.00$27.00$13.50$27.00$8.59
70Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF30,815$0.82$0.80$0.77$0.82$0.82$0.79$0.90
71Type I high perf PM (Y)6"(broken)(100MIL) (666-7302)LF2,560$0.82$0.80$0.77$0.82$0.82$0.79$0.86
72Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF15,813$0.86$0.80$0.77$0.82$0.82$0.79$0.90
73PRFB rumble strip (BLK)(4')(transverse) (668-7001)LF80$20.00$25.00$25.00$27.00$19.50$26.00$17.00
74Prefabricated PM type C (W)(word) (668-7103)EACH2$350.00$575.00$1,060.00$600.00$350.00$295.00$300.00
75Reflectorized pavement marker type II-A-A (672-7004)EACH603$9.00$7.00$5.20$6.75$5.25$7.00$5.50
TxDOT contract A00183926: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of February 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy