TxDOT contract A00184204 bid tabulation

Bridge Replacement, CARGILL RD E (At Eight Mile Creek to .). Let by Texas DOT on June 4, 2025, Harrison, Atlanta District. 6 bids received; low bid $1,320,898 by True Roads Construction, LLC, -27% against the engineer's estimate of $1,820,704.

Owner
Texas DOT
Letting
04 JUN 2025
Pay items
48
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1True Roads Construction, LLC$1,320,898Low-27%
2THK Construction LLC$1,532,225+16%-16%
3East Texas Bridge, Inc.$1,620,604+23%-11%
4Hodges and Son Construction Company, Inc.$1,669,145+26%-8.0%
5Longview Bridge and Road, LTD.$1,686,861+28%-7.0%
6Highway 19 Construction LLC$2,110,839+60%+16%
TxDOT contract A00184204: bids by rank

Engineer's estimate: $1,820,704.

Bid tabulation

LinePay itemUnitQuantityEstimate1. True Roads Construction, LLC2. THK Construction LLC3. East Texas Bridge, Inc.4. Hodges and Son Construction Company, Inc.5. Longview Bridge and Road, LTD.6. Highway 19 Construction LLC
1Preparing row (100-7002)STA8.93$3,000.00$1,000.00$2,000.00$4,000.00$5,600.00$5,000.00$10,000
2Remove (0"-8") TRT/untrt base & asphalt pavement (105-7048)SY563$12.00$6.00$15.00$8.00$8.00$18.00$15.00
3Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052)SY501$7.00$15.00$10.00$10.00$20.00$25.00
4Excavation (roadway) (110-7001)CY332$40.00$18.00$20.00$15.00$20.00$40.00$25.00
5Excavation (channel) (110-7002)CY627$80.00$22.00$15.00$20.00$20.00$25.00$30.00
6Embankment (final)(OC)(type C) (132-7005)CY301$40.00$20.00$20.00$30.00$25.00$45.00$50.00
7Blading (150-7001)STA1.20$400.00$1,500.00$500.00$250.00$20.00$2,500.00$500.00
8Furn & place topsoil (4") (160-7002)SY5,167$5.00$4.00$3.50$4.00$4.00$4.75$4.00
9Broadcast seed (permanent_rural_sand) (164-7001)SY5,167$0.60$0.76$0.27$0.30$1.00$0.80$2.00
10Broadcast seed (temporary_warm) (164-7005)SY2,584$1.00$0.01$0.24$0.25$1.00$0.70$2.00
11Broadcast seed (temporary_cool) (164-7006)SY2,584$1.00$0.01$0.24$0.25$1.00$0.75$2.00
12Cement (275-7001)TON24$500.00$325.00$400.00$330.00$350.00$320.00$500.00
13Cement TRT (subgrade)(6") (275-7022)SY1,602$15.00$9.00$20.00$8.00$18.00$7.50$10.00
14Prime coat (MC-30) (310-7004)GAL355$10.00$12.00$28.89$10.00$15.00$7.50$15.00
15Cem stabil BKFL (400-7010)CY124$200.00$300.00$338.00$275.00$275.00$300.00$500.00
16Drilled shaft (30 in) (416-7005)LF255$350.00$270.00$334.33$355.00$295.00$380.00$450.00
17Drilled shaft (36 in) (416-7006)LF390$305.00$350.91$390.00$330.00$415.00$500.00
18Class C concrete (abutment) (420-7012)CY75.40$1,500.00$1,125.00$1,100.00$1,200.00$1,800.00$1,100.00$1,500.00
19Reinforced concrete slab (422-7001)SF2,080$32.00$35.00$35.00$38.00$45.00$33.00
20Reinforced concrete slab (box beam) (422-7005)SF1,832$35.00$21.00$35.00$28.00$26.00$40.00$25.00
21Approach slab (422-7013)CY88.60$1,000.00$625.00$900.00$850.00$1,000.00$800.00$700.00
22Prestressed concrete girder (TX34) (425-7002)LF317.69$280.00$305.00$315.00$325.00$270.00$386.00
23Prestressed concrete box beam (4B28) (425-7028)LF278$300.00$340.00$314.00$385.00$350.00$375.00$409.00
24Prestressed concrete box beam (5B28) (425-7029)LF139$400.00$340.00$314.00$385.00$350.00$375.00$409.00
25Riprap (stone protection)(12 in) (432-7041)CY684$275.00$180.00$205.00$225.00$200.00$220.00$250.00
26Bedding material (6 in) (432-7050)CY145$200.00$200.00$195.00$225.00$180.00$215.00$250.00
27Rail (type T223) (450-7008)LF384$175.00$115.00$160.00$165.00$160.00$160.00$180.00
28Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF112$250.00$225.00$150.00$235.00$225.00$250.00$180.00
29RC pipe (CL III)(24 in) (464-7005)LF28$160.00$80.00$130.00$140.00$120.00$110.00
30Removing structure (pipe) (496-7007)LF31$18.00$20.00$20.00$50.00$20.00$50.00
31Removing structure (bridge 0 - 99 FT length) (496-7009)EACH2$25,000$10,000$10,000$18,000$25,000$15,000$100,000
32Mobilization (500-7001)LS1$165,520$75,000$120,000$150,000$150,000$100,000$150,000
33Barricades, signs and traffic handling (502-7001)MO14$5,000.00$900.00$1,188.47$2,000.00$2,000.00$5,000.00$3,500.00
34TMA (stationary) (505-7001)DAY40$215.00$160.00$275.00$100.00$300.00$250.00$500.00
35Rock filter dams (install) (type 2) (506-7002)LF230$50.00$40.00$40.66$40.00$1.00$42.00$75.00
36Rock filter dams (remove) (506-7011)LF230$15.00$11.00$10.70$10.00$1.00$10.00$10.00
37Temporary sediment control fence (install) (506-7039)LF2,555$4.50$4.00$4.00$4.00$1.00$4.00$4.00
38Temporary sediment control fence (remove) (506-7041)LF2,555$1.50$1.10$1.07$0.65$1.00$1.00$1.00
39Metal W-beam guard fence (timber post) (540-7001)LF550$30.00$26.00$26.22$26.50$25.00$27.00$35.00
40Metal beam guard fence trans (TL2) (540-7006)EACH8$1,000.00$1,400.00$1,391.00$1,450.00$1,300.00$1,500.00$3,750.00
41Remove metal beam guard fence (542-7001)LF142$3.00$2.20$2.14$2.50$2.00$2.50$5.00
42Guardrail end treatment (install) (544-7001)EACH8$4,500.00$3,300.00$3,210.00$3,300.00$3,000.00$3,300.00$3,100.00
43Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH12$730.00$935.00$867.77$900.00$1,000.00$900.00$850.00
44Remove SM RD SN sup&AM (644-7073)EACH2$120.00$82.00$105.93$125.00$50.00$110.00$100.00
45Remove lrsa (647-7003)EACH2$1,250.00$550.00$500.00$250.00$400.00$600.00$500.00
46Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH9$45.00$48.00$48.15$50.00$45.00$50.00$65.00
47Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH17$60.00$48.00$48.15$50.00$45.00$60.00$45.00
48Asphalt-stabilized flexible base (2002-7002)TON554$130.00$170.00$190.00$155.00$195.00$155.00$160.00
TxDOT contract A00184204: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of June 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy