TxDOT contract A00184550 bid tabulation
Widen Road - Add Shoulders, SH 29 (0.382 MI W of Algerita Hill Rd to Lehne Rd). Let by Texas DOT on August 8, 2025, Burnet, Austin District. 8 bids received; low bid $10,701,288 by Allen Keller Company, -15% against the engineer's estimate of $12,526,241.
- Owner
- Texas DOT
- Letting
- 08 AUG 2025
- Pay items
- 103
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allen Keller Company | $10,701,288 | Low | -15% |
| 2 | Texas Materials Group, Inc. | $11,184,748 | +5.0% | -11% |
| 3 | Acme Bridge Company, Inc. | $11,990,879 | +12% | -4.0% |
| 4 | Hunter Industries, LTD. | $12,546,208 | +17% | 0.0% |
| 5 | Big Creek Construction, LTD. | $12,575,936 | +18% | 0.0% |
| 6 | Dan Williams Company | $12,577,462 | +18% | 0.0% |
| 7 | Aaron Concrete Contractors, LLC | $14,722,285 | +38% | +18% |
| 8 | Dean Word Company, LTD. | $17,735,593 | +66% | +42% |
Engineer's estimate: $12,526,241.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Allen Keller Company | 2. Texas Materials Group, Inc. | 3. Acme Bridge Company, Inc. | 4. Hunter Industries, LTD. | 5. Big Creek Construction, LTD. | 6. Dan Williams Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 275 | $2,700.00 | $157.79 | $350.00 | $1,020.00 | $801.04 | $595.00 | $3,255.00 |
| 2 | Removing concrete (mowstrip) (104-7005) | LF | 1,876 | $15.00 | $6.98 | $9.00 | $9.00 | $13.68 | $16.00 | $7.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 2,439 | $37.59 | $34.89 | $22.75 | $13.60 | $27.36 | $20.00 | $14.00 |
| 4 | Removing stab base and asphalt pavement(0"-16") (105-7129) | SY | 33,713 | $12.86 | $0.78 | $8.00 | $8.40 | $4.58 | $10.00 | $7.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 40,146 | $10.50 | $5.54 | $17.00 | $14.40 | $24.00 | $15.00 | $16.00 |
| 6 | Embankment (final)(OC)(type A) (132-7001) | CY | 8,469 | $16.50 | $11.73 | $6.00 | $7.80 | $17.10 | $15.00 | $20.00 |
| 7 | Embankment (final)(OC)(type B) (132-7003) | CY | 217 | $11.72 | $7.00 | $19.30 | $27.36 | $15.00 | $20.00 | |
| 8 | Furn & place topsoil (4") (160-7002) | SY | 62,960 | $2.18 | $2.02 | $4.00 | $2.25 | $1.36 | $2.80 | $1.50 |
| 9 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 62,960 | $0.14 | $0.16 | $0.17 | $0.18 | $0.17 | $0.20 | $0.16 |
| 10 | Hydro mulch seed (permanent_rural_clay) (164-7018) | SY | 62,960 | $1.83 | $0.52 | $0.56 | $0.57 | $0.55 | $0.65 | $0.60 |
| 11 | Vegetative watering (168-7001) | TGL | 5,465 | $27.20 | $49.97 | $0.01 | $29.70 | $23.94 | $10.00 | $4.50 |
| 12 | Soil ret BLKT(SL_mod_clay_short_roll) (169-7009) | SY | 45,650 | $2.80 | $1.62 | $2.25 | $1.75 | $1.70 | $2.00 | $1.80 |
| 13 | FL BS (compacted in place)(type A GR 5)(final pos) (247-7179) | CY | 24,912 | $30.00 | $50.18 | $41.80 | $52.80 | $53.87 | $53.00 | $50.00 |
| 14 | Prime coat (multi option) (310-7015) | GAL | 13,799 | $6.62 | $5.93 | $5.30 | $5.60 | $5.05 | $5.00 | $5.30 |
| 15 | D-GR HMA type-B PG64-22 (341-7001) | TON | 22,767 | $92.00 | $79.75 | $78.00 | $79.60 | $103.50 | $95.00 | $82.00 |
| 16 | D-GR HMA type D PG76-22 (341-7056) | TON | 7,520 | $130.00 | $88.86 | $98.00 | $101.00 | $114.50 | $102.00 | $100.00 |
| 17 | D-GR HMA type D PG76-22 (level-UP) (341-7059) | TON | 2,457 | $130.00 | $88.86 | $105.00 | $109.00 | $116.76 | $112.00 | $110.00 |
| 18 | Tom-C PG76-22 sac-B (347-7002) | TON | 11,760 | $120.00 | $109.91 | $120.00 | $132.00 | $143.16 | $124.00 | $130.00 |
| 19 | Trench excavation protection (402-7001) | LF | 40 | $28.60 | $95.63 | $25.00 | $103.00 | $111.20 | $50.00 | $25.00 |
| 20 | Retaining wall (spread footing) (423-7015) | SF | 1,951 | $103.33 | $110.98 | $77.00 | $98.20 | $95.00 | $138.00 | $75.00 |
| 21 | Riprap (concrete)(4 in) (432-7001) | CY | 532 | $600.00 | $454.25 | $550.00 | $491.00 | $723.90 | $650.00 | $550.00 |
| 22 | Riprap (mow strip)(4 in) (432-7013) | CY | 181 | $300.00 | $645.50 | $555.00 | $698.00 | $961.43 | $650.00 | $575.00 |
| 23 | Rirrap (stone common)(dry)(15 in) (432-7032) | CY | 116 | $190.00 | $126.28 | $270.00 | $169.00 | $259.17 | $160.00 | $275.00 |
| 24 | Concrete box culvert (4 FT X 3 FT)(extend) (462-7059) | LF | 25 | $1,300.00 | $1,008.90 | $427.00 | $1,090.00 | $1,173.12 | $600.00 | $500.00 |
| 25 | Concrete box culvert (4 FT X 4 FT)(extend) (462-7060) | LF | 12 | $1,350.00 | $1,099.74 | $496.00 | $1,190.00 | $1,278.75 | $820.00 | $650.00 |
| 26 | Concrete box culvert (5 FT X 4 FT)(extend) (462-7063) | LF | 48 | $1,277.33 | $1,099.74 | $562.00 | $1,190.00 | $1,278.75 | $600.00 | $615.00 |
| 27 | Concrete box culvert (6 FT X 6 FT)(extend) (462-7069) | LF | 21 | $1,081.38 | $1,291.00 | $801.77 | $1,400.00 | $1,501.15 | $840.00 | $900.00 |
| 28 | Concrete box culvert (8 FT X 7 FT)(extend) (462-7079) | LF | 25 | $1,500.00 | $1,338.82 | $1,055.55 | $1,450.00 | $1,556.74 | $870.00 | $1,200.00 |
| 29 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,408 | $113.40 | $67.90 | $102.00 | $60.00 | $64.49 | $70.00 | $65.00 |
| 30 | RC pipe (CL III)(24 in) (464-7005) | LF | 568 | $131.23 | $87.98 | $128.00 | $77.60 | $83.40 | $105.00 | $80.00 |
| 31 | RC pipe (CL III)(30 in) (464-7007) | LF | 80 | $193.32 | $119.54 | $183.00 | $103.00 | $111.20 | $145.00 | $100.00 |
| 32 | RC pipe (CL III)(36 in) (464-7009) | LF | 114 | $214.63 | $181.70 | $290.00 | $155.00 | $166.79 | $190.00 | $155.00 |
| 33 | Junction box(complete)(PJB)(6FTX6FT) (465-7011) | EACH | 2 | $13,175 | $9,706.42 | $11,520 | $9,640.00 | $10,369 | $13,000 | $12,000 |
| 34 | Headwall (CH - PW - 0) (diameter= 36 in) (466-7105) | EACH | 1 | $14,500 | $8,176.36 | $8,000.00 | $8,840.00 | $9,507.26 | $15,600 | $10,000 |
| 35 | Headwall (CH - PW - 0) (diameter= 42 in) (466-7106) | EACH | 1 | $19,400 | $8,845.76 | $10,225 | $9,570.00 | $10,286 | $16,300 | $12,000 |
| 36 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $15,792 | $15,157 | $13,150 | $16,400 | $17,625 | $18,500 | $16,000 |
| 37 | Wingwall (PW - 1) (HW=5 FT) (466-7175) | EACH | 2 | $19,465 | $16,353 | $14,700 | $17,700 | $19,015 | $19,000 | $17,500 |
| 38 | Wingwall (PW - 1) (HW=6 FT) (466-7176) | EACH | 1 | $24,807 | $22,090 | $19,455 | $23,900 | $25,686 | $20,800 | $25,000 |
| 39 | Wingwall (PW - 1) (HW=8 FT) (466-7178) | EACH | 1 | $31,798 | $27,828 | $25,350 | $30,100 | $32,358 | $37,800 | $30,000 |
| 40 | Wingwall (PW - 1) (HW=9 FT) (466-7179) | EACH | 4 | $35,000 | $31,080 | $32,558 | $33,600 | $36,139 | $42,000 | $40,000 |
| 41 | Wingwall (PW - 1) (HW=10 FT) (466-7180) | EACH | 1 | $40,800 | $41,408 | $43,673 | $44,800 | $48,148 | $55,000 | $55,000 |
| 42 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 68 | $1,554.85 | $1,874.34 | $1,500.00 | $1,850.00 | $1,985.96 | $1,350.00 | $1,500.00 |
| 43 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 30 | $2,184.59 | $2,223.39 | $1,900.00 | $2,150.00 | $2,307.32 | $1,800.00 | $1,600.00 |
| 44 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 4 | $2,716.42 | $3,155.79 | $2,200.00 | $3,060.00 | $3,285.84 | $2,800.00 | $2,400.00 |
| 45 | Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368) | EACH | 6 | $5,778.00 | $5,833.42 | $3,500.00 | $5,740.00 | $6,176.94 | $6,700.00 | $4,500.00 |
| 46 | Removing structure (set) (496-7004) | EACH | 78 | $233.81 | $215.16 | $900.00 | $233.00 | $250.19 | $275.00 | $300.00 |
| 47 | Removing structure (wingwall) (496-7005) | EACH | 8 | $1,753.59 | $239.07 | $2,800.00 | $259.00 | $277.99 | $2,200.00 | $3,000.00 |
| 48 | Removing structure (headwall) (496-7006) | EACH | 2 | $1,753.59 | $478.15 | $2,800.00 | $517.00 | $555.98 | $2,200.00 | $3,000.00 |
| 49 | Removing structure (pipe) (496-7007) | LF | 1,526 | $23.38 | $8.60 | $33.00 | $9.30 | $10.01 | $16.50 | $18.00 |
| 50 | Mobilization (500-7001) | LS | 1 | $849,463 | $1,000,000 | $942,000 | $1,050,000 | $817,368 | $1,250,000 | $920,000 |
| 51 | Barricades, signs and traffic handling (502-7001) | MO | 24 | $6,700.00 | $7,046.36 | $3,500.00 | $7,230.00 | $3,282.78 | $4,000.00 | $25,000 |
| 52 | Portable changeable message sign (503-7002) | EACH | 2 | $6,717.00 | $33,378 | $5,000.00 | $12,200 | $7,139.60 | $12,000 | $15,000 |
| 53 | TMA (stationary) (505-7001) | DAY | 406 | $221.47 | $242.15 | $208.00 | $149.00 | $178.49 | $230.00 | $175.00 |
| 54 | TMA (mobile operation) (505-7003) | DAY | 49 | $484.82 | $769.14 | $275.00 | $596.00 | $305.98 | $900.00 | $650.00 |
| 55 | Rock filter dams (install) (type 1) (506-7001) | LF | 50 | $30.00 | $31.08 | $70.72 | $33.60 | $32.50 | $35.00 | $35.00 |
| 56 | Rock filter dams (remove) (506-7011) | LF | 50 | $10.00 | $21.52 | $12.12 | $23.30 | $22.50 | $25.00 | $25.00 |
| 57 | Temporary sediment control fence (install) (506-7039) | LF | 20,378 | $3.92 | $3.30 | $3.28 | $3.55 | $3.45 | $3.80 | $3.50 |
| 58 | Temporary sediment control fence (remove) (506-7041) | LF | 20,378 | $1.28 | $0.48 | $1.01 | $0.52 | $0.50 | $0.75 | $0.55 |
| 59 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 1,150 | $9.14 | $5.26 | $5.05 | $5.70 | $5.50 | $6.00 | $6.00 |
| 60 | Biodegradable erosion control logs (remove) (506-7046) | LF | 1,150 | $2.69 | $0.72 | $1.01 | $0.78 | $0.75 | $1.00 | $0.75 |
| 61 | Driveways (concrete) (530-7006) | SY | 4,856 | $109.00 | $138.99 | $137.00 | $145.00 | $106.32 | $155.00 | $115.00 |
| 62 | Driveways (ACP) (530-7010) | SY | 1,327 | $49.50 | $69.19 | $136.00 | $133.00 | $45.20 | $70.00 | $90.00 |
| 63 | Turnouts (ACP) (530-7018) | SY | 669 | $139.83 | $81.92 | $122.00 | $135.00 | $52.04 | $42.00 | $95.00 |
| 64 | Metal W-beam guard fence (timber post) (540-7001) | LF | 4,000 | $13.90 | $23.91 | $27.00 | $25.90 | $25.39 | $31.00 | $30.00 |
| 65 | Remove metal beam guard fence (542-7001) | LF | 1,456 | $4.75 | $2.39 | $3.00 | $2.60 | $2.54 | $3.30 | $5.00 |
| 66 | Remove downstream anchor terminal (542-7003) | EACH | 7 | $310.47 | $239.07 | $300.00 | $259.00 | $253.94 | $250.00 | $275.00 |
| 67 | Guardrail end treatment (install) (544-7001) | EACH | 26 | $2,079.84 | $3,060.15 | $3,325.00 | $3,310.00 | $3,250.44 | $3,600.00 | $4,000.00 |
| 68 | Guardrail end treatment (remove) (544-7003) | EACH | 7 | $535.25 | $239.07 | $300.00 | $259.00 | $253.94 | $365.00 | $300.00 |
| 69 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 3 | $645.40 | $712.44 | $926.85 | $657.00 | $675.05 | $700.00 | $640.00 |
| 70 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 29 | $402.72 | $329.92 | $401.63 | $238.00 | $244.51 | $250.00 | $230.00 |
| 71 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 3 | $329.17 | $372.96 | $432.53 | $279.00 | $287.03 | $300.00 | $275.00 |
| 72 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 41 | $806.96 | $688.54 | $722.94 | $662.00 | $680.37 | $700.00 | $650.00 |
| 73 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 3 | $993.00 | $922.83 | $988.63 | $962.00 | $988.66 | $1,025.00 | $940.00 |
| 74 | Remove SM RD SN sup&AM (644-7073) | EACH | 44 | $152.50 | $114.76 | $92.68 | $98.20 | $100.99 | $105.00 | $100.00 |
| 75 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 58,509 | $0.35 | $0.29 | $0.30 | $0.31 | $0.30 | $0.33 | $0.30 |
| 76 | Work zone pavement marking non-removing (Y)6"(broken) (662-7036) | LF | 14,294 | $0.40 | $0.33 | $0.35 | $0.36 | $0.35 | $0.37 | $0.35 |
| 77 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 57,174 | $0.39 | $0.29 | $0.30 | $0.31 | $0.30 | $0.33 | $0.30 |
| 78 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 9,082 | $1.54 | $2.83 | $0.95 | $1.80 | $1.63 | $1.50 | $2.30 |
| 79 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 7,504 | $1.34 | $2.86 | $0.95 | $1.80 | $1.63 | $1.50 | $2.30 |
| 80 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 2,675 | $1.40 | $1.15 | $1.20 | $1.25 | $1.20 | $1.32 | $1.20 |
| 81 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 84 | $10.47 | $14.34 | $15.00 | $15.50 | $15.00 | $16.00 | $15.00 |
| 82 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 57 | $207.47 | $172.13 | $180.00 | $186.00 | $180.00 | $195.00 | $180.00 |
| 83 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 6 | $247.57 | $191.26 | $200.00 | $207.00 | $200.00 | $220.00 | $200.00 |
| 84 | Reflectorized pavement marking type I (W)(RR crossing)(100MIL) (666-7081) | EACH | 4 | $579.88 | $1,195.38 | $1,250.00 | $1,290.00 | $1,250.00 | $1,350.00 | $1,250.00 |
| 85 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 15,254 | $1.12 | $0.23 | $0.24 | $0.25 | $0.24 | $0.25 | $0.24 |
| 86 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 71,788 | $0.87 | $0.19 | $0.20 | $0.21 | $0.20 | $0.22 | $0.20 |
| 87 | Reflectorized pavement marking type II (W) 8" (solid) (666-7179) | LF | 4,455 | $0.39 | $0.42 | $0.44 | $0.45 | $0.44 | $0.50 | $0.44 |
| 88 | Reflectorized pavement marking type II (W) 24" (solid) (666-7184) | LF | 84 | $4.92 | $9.56 | $10.00 | $10.30 | $10.00 | $11.00 | $10.00 |
| 89 | Reflectorized pavement marking type II (W) (arrow) (666-7186) | EACH | 57 | $82.00 | $47.81 | $50.00 | $51.70 | $50.00 | $55.00 | $50.00 |
| 90 | Reflectorized pavement marking type II (W) (word) (666-7194) | EACH | 6 | $85.49 | $57.38 | $60.00 | $62.10 | $60.00 | $65.00 | $60.00 |
| 91 | Reflectorized pavement marking type II (W) (RR crossing) (666-7198) | EACH | 4 | $205.00 | $133.89 | $140.00 | $145.00 | $140.00 | $155.00 | $140.00 |
| 92 | Reflectorized pavement marking type II (Y) 6" (broken) (666-7211) | LF | 13,586 | $0.34 | $0.23 | $0.24 | $0.25 | $0.24 | $0.25 | $0.24 |
| 93 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 61,128 | $0.89 | $0.22 | $0.23 | $0.24 | $0.23 | $0.25 | $0.23 |
| 94 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 15,254 | $1.11 | $0.44 | $0.46 | $0.48 | $0.46 | $0.50 | $0.46 |
| 95 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 71,788 | $0.81 | $0.44 | $0.46 | $0.48 | $0.46 | $0.50 | $0.46 |
| 96 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 13,586 | $1.00 | $0.44 | $0.46 | $0.48 | $0.46 | $0.50 | $0.46 |
| 97 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 61,128 | $0.81 | $0.44 | $0.46 | $0.48 | $0.46 | $0.50 | $0.46 |
| 98 | Reflectorized pavement marker type I-C (672-7002) | EACH | 838 | $7.33 | $5.26 | $5.50 | $5.70 | $5.50 | $6.00 | $5.50 |
| 99 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 2,823 | $5.92 | $5.26 | $5.50 | $5.70 | $5.50 | $6.00 | $5.50 |
| 100 | Eliminating existing PM & markers (4") (677-7001) | LF | 141,183 | $1.50 | $0.14 | $0.15 | $0.16 | $0.15 | $0.20 | $0.15 |
| 101 | Eliminating existing PM & markers (8") (677-7004) | LF | 1,120 | $1.92 | $0.52 | $0.55 | $0.57 | $0.55 | $0.60 | $0.55 |
| 102 | Tree removal (24" - 30" diameter) (752-7008) | EACH | 31 | $620.00 | $1,577.89 | $1,500.00 | $1,710.00 | $1,430.00 | $2,100.00 | $2,000.00 |
| 103 | Bonding course (3007-7001) | GAL | 11,041 | $3.80 | $4.87 | $4.70 | $3.85 | $3.31 | $4.00 | $3.65 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 8, 2025. Compiled by Mirage Metrics.