TxDOT contract A00184795 bid tabulation

Interstate Designation, US 77 (11.40 Miles North of Norias Rd to 9.6 Miles North of Norias Rd). Let by Texas DOT on April 4, 2025, Kenedy, Pharr District. 5 bids received; low bid $61,607,900 by Foremost Paving, Inc., -15% against the engineer's estimate of $72,543,107.

Owner
Texas DOT
Letting
04 APR 2025
Pay items
147
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Foremost Paving, Inc.$61,607,900Low-15%
2Anderson Columbia Co., Inc.$65,488,636+6.0%-10%
3Posillico Civil, Inc.$66,334,000+8.0%-9.0%
4Pulice Construction, Inc.$68,640,771+11%-5.0%
5CK Newberry, LLC$71,675,592+16%-1.0%
TxDOT contract A00184795: bids by rank

Engineer's estimate: $72,543,107.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Foremost Paving, Inc.2. Anderson Columbia Co., Inc.3. Posillico Civil, Inc.4. Pulice Construction, Inc.5. CK Newberry, LLC
1Preparing row (100-7002)STA126$15,000$8,925.00$1,500.00$19,500$54,365$20,000
2Removing concrete (mowstrip) (104-7005)LF9,744$17.50$6.55$5.00$5.50$7.28$4.00
3Excavation (roadway) (110-7001)CY78,891$6.00$5.45$7.00$4.75$5.89$14.00
4Embankment (final)(DC)(type C) (132-7006)CY500,237$30.00$6.79$33.00$8.25$34.83$10.00
5Furn & place topsoil (vehicle) (160-7007)CY50$50.00$50.53$100.00$50.00$27.10$150.00
6Straw/hay mulch seed(permanent_rural_sand) (164-7025)SY287,403$1.00$0.68$0.70$0.48$0.44$0.50
7Straw/hay mulch seed (temporary_warm) (164-7029)SY143,702$1.00$0.30$0.30$0.47$0.40$0.50
8Straw/hay mulch seed (temporary_cool) (164-7030)SY143,702$1.00$0.30$0.30$0.47$0.40$0.50
9Vegetative watering (168-7001)TGL2,338$40.00$64.00$28.00$55.00$54.09$30.00
10FL BS (roadway del)(type E GR 4)(final pos) (247-7277)CY30,645$50.00$44.00$48.00$50.00$56.15$65.00
11Geogrid base reinforcement (type 2) (250-7002)SY51,900$2.00$1.44$1.75$1.50$1.23$1.50
12Rework BS metal (type B)(8")(density control) (251-7028)SY96,553$2.00$1.42$2.34$2.00$3.52$7.00
13Cement (275-7001)TON4,873$200.00$200.00$200.00$210.00$190.16$225.00
14Cement TRT (subgrade)(12") (275-7015)SY183,385$2.75$2.68$3.80$1.65$2.95$2.00
15Cement TRT (existing material & new base)(11") (275-7026)SY64,471$3.00$3.74$4.70$2.00$2.96$2.50
16Cement TRT (existing material & new base)(14") (275-7027)SY111,239$3.00$2.37$3.40$2.20$2.96$3.00
17SLV, haul & stockpile reclaimed asphalt PV (8 to 10") (305-7006)SY96,553$3.50$4.83$6.50$5.35$3.03$6.00
18Prime coat (MC-30) (310-7004)GAL3,381$5.50$9.00$9.00$6.00$3.91$6.00
19SP mixes SP-B sac-B PG64-22 (344-7002)TON40,963$115.00$108.00$107.00$105.00$136.43$130.00
20SP mixes SP-D sac-A PG76-22 (344-7064)TON5,274$130.00$109.00$145.00$125.00$141.29$160.00
21SP mixes SP-D sac-B PG76-22 (344-7065)TON9,141$130.00$129.00$124.00$110.00$137.63$140.00
22Stone-MTRX-asphalt SMA-F sac-A PG76-22 (346-7017)TON9,141$150.00$155.00$158.00$105.00$176.18$180.00
23Flexible pavement structure repair(2") (351-7001)SY1,263$100.00$45.40$14.00$64.00$42.74$50.00
24Plane & text asphalt concrete pavement(1.5") (354-7018)SY891$6.00$31.24$11.00$5.50$13.54$10.00
25Struct excavation (box) (400-7002)CY326$50.00$10.00$10.00$100.00$74.74$20.00
26Struct excavation (pipe) (400-7003)CY103$85.00$10.00$30.00$42.00$74.99$50.00
27Cut & restore concrete paving (400-7007)SY179$125.00$200.00$180.00$300.00$358.58$200.00
28Cem stabil BKFL (400-7010)CY891$250.00$200.00$200.00$75.00$148.54$200.00
29Trench excavation protection (402-7001)LF507$20.00$1.00$10.00$1.00$23.26$10.00
30Temporary special shoring (403-7001)SF327$1.00$100.00$50.00$100.00$61.04$75.00
31Prestressed concrete pil (18 in SQ) (409-7002)LF5,500$200.00$161.00$165.00$215.00$184.41$225.00
32Drilled shaft (non - reinforced) (12 in) (416-7024)LF14$120.00$95.00$36.00$95.00$82.30$200.00
33Drilled shaft (sign mounts) (24 in) (416-7028)LF84$180.00$145.00$300.00$145.00$168.66$250.00
34Drilled shaft (roadway illumination pole) (30 in) (416-7040)LF96$240.00$225.00$235.00$250.00$304.80$325.00
35Class B concrete (flume) (420-7010)CY32$700.00$1,300.00$840.00$400.00$914.89$650.00
36Class C concrete (abutment) (420-7012)CY414$1,800.00$2,402.00$2,500.00$850.00$1,088.50$2,000.00
37Reinforced concrete slab (422-7001)SF30,400$30.00$30.00$32.00$25.00$25.68$45.00
38Retaining wall (MSE) (ashlar stone fin) (423-7002)SF242,247$80.00$98.37$53.70$112.00$34.95$85.00
39Prestressed concrete girder (TX54) (425-7005)LF3,782.50$250.00$295.00$288.00$240.00$204.50$250.00
40Riprap (concrete)(4 in) (432-7001)CY224$500.00$650.00$770.00$435.00$416.56$725.00
41Riprap (mow strip)(4 in) (432-7013)CY904$490.00$671.00$800.00$475.00$426.42$750.00
42Rail (type SSTR) (450-7024)LF14,010.60$65.00$57.85$65.00$60.00$55.79$100.00
43Sealed expansion joint (4 in) (SEJ - M) (454-7004)LF548$225.00$280.00$290.00$185.00$243.88$225.00
44Concrete box culvert (3 FT X 3 FT) (462-7002)LF203$400.00$700.00$440.00$495.00$361.97$400.00
45RC pipe (CL III)(18 in)(mod) (464-7065)LF148$100.00$100.00$430.00$490.00$160.90$125.00
46RC pipe (CL III)(24 in)(mod) (464-7066)LF7,709$115.00$102.00$125.00$85.00$100.71$135.00
47RC pipe (CL III)(30 in)(mod) (464-7067)LF1,025$150.00$130.00$185.00$110.00$131.12$150.00
48Inlet (complete)(PSL)(RC)(3FTX3FT) (465-7070)EACH16$5,000.00$6,100.00$5,000.00$5,000.00$6,007.66$10,000
49Inlet (complete)(PSL)(RC)(4FTX4FT) (465-7071)EACH4$8,000.00$6,700.00$6,200.00$5,500.00$6,883.94$10,000
50Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126)EACH12$6,500.00$8,400.00$5,300.00$5,750.00$7,291.53$10,000
51Inlet (complete)(PSL)(FG)(4FTX4FT-3FTX3FT) (465-7127)EACH3$8,700.00$9,100.00$6,400.00$6,250.00$8,301.73$10,000
52Inlet(complete)(PSL)(SFG)(4FTX4FT-4FTX4FT) (465-7147)EACH2$9,000.00$11,000$7,300.00$7,500.00$6,819.47$10,000
53Inlet (complete)(drop) (465-7346)EACH8$6,000.00$4,500.00$2,600.00$6,750.00$6,782.23$10,000
54Inlet(complete)(type MSE1) (465-7362)EACH42$6,000.00$17,100$3,900.00$5,500.00$5,434.92$10,000
55Wingwall (PW - 1) (HW=5 FT) (466-7175)EACH1$25,000$70,000$32,000$12,500$22,739$50,000
56Set (type I)(S= 3 FT)(HW= 5 FT)(6:1)(C) (467-7050)EACH1$16,000$32,000$19,000$12,500$15,374$20,000
57Set (type II) (18 in) (RCP) (6: 1) (C) (467-7307)EACH4$2,750.00$1,900.00$2,300.00$2,000.00$2,039.09$2,500.00
58Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH9$3,000.00$2,000.00$2,500.00$2,500.00$2,716.60$2,500.00
59Set (type II) (24 in) (RCP) (6: 1) (C) (467-7327)EACH2$3,000.00$2,600.00$2,500.00$2,750.00$2,486.71$2,750.00
60Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346)EACH1$3,000.00$2,700.00$4,100.00$3,000.00$3,682.21$3,250.00
61Set (type II) (30 in) (RCP) (6: 1) (C) (467-7347)EACH4$4,200.00$3,700.00$3,140.00$3,200.00$4,645.77$3,500.00
62Removing structure (set) (496-7004)EACH18$1,500.00$800.00$590.00$170.00$830.67$1,000.00
63Removing structure (pipe) (496-7007)LF707$25.00$30.00$27.00$12.50$25.03$20.00
64Removing structure (bridge 100 - 499 FT length) (496-7010)EACH1$200,000$40,000$84,000$45,000$81,627$200,000
65Mobilization (500-7001)LS1$7,723,205$5,000,000$5,900,000$6,003,383$6,848,199$7,000,000
66Barricades, signs and traffic handling (502-7001)MO25$20,000$6,500.00$5,000.00$11,000$3,272.44$50,000
67Portable changeable message sign (503-7002)EACH2$22,000$7,500.00$34,200$12,000$19,968$30,000
68TMA (stationary) (505-7001)DAY1,173$200.00$22.00$220.00$58.00$259.90$325.00
69TMA (mobile operation) (505-7003)DAY157$350.00$0.01$735.00$250.00$537.96$325.00
70Rock filter dams (install) (type 2) (506-7002)LF1,590$55.00$36.75$39.00$49.00$53.67$50.00
71Rock filter dams (remove) (506-7011)LF1,590$15.00$21.75$23.00$14.00$15.00$15.00
72Construction exits (install) (type 1) (506-7020)SY156$50.00$50.86$72.00$50.00$52.99$50.00
73Construction exits (remove) (506-7024)SY156$15.00$26.98$40.00$15.00$16.83$15.00
74Temporary sediment control fence (install) (506-7039)LF16,794$3.50$3.25$3.50$4.85$4.19$5.00
75Temporary sediment control fence (remove) (506-7041)LF16,794$1.00$1.45$1.50$1.25$0.94$2.00
76Biodegradable erosion control logs (install) (12") (506-7044)LF1,600$7.50$6.25$6.50$7.00$9.11$7.00
77Biodegradable erosion control logs (remove) (506-7046)LF1,600$2.00$1.65$1.75$2.00$1.11$2.00
78Constructing detours (508-7001)SY49,808$40.00$66.57$78.00$78.00$76.77$80.00
79Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF30,330$45.00$33.29$33.00$62.00$42.83$60.00
80Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF65,430$15.00$4.45$5.00$4.00$4.36$10.00
81Portable concrete traffic barrier (stockpile)(single slope)(type 1) (512-7037)LF180$40.00$11.18$11.00$15.00$7.96$60.00
82Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF30,330$15.00$14.18$17.00$5.00$9.74$15.00
83Portable concrete traffic barrier (pinning) (512-7071)EACH316$5.00$174.87$102.00$30.00$40.36$100.00
84Driveways (ACP) (530-7010)SY378$50.00$123.02$76.00$30.00$66.04$100.00
85Mill rumble strips (asphalt) (shoulder) (533-7001)LF47,225$0.15$0.45$0.25$0.31$0.21$0.20
86Metal W-beam guard fence (timber post) (540-7001)LF2,125$25.00$43.00$24.00$23.00$26.11$24.00
87Metal beam guard fence trans (thrie-beam) (540-7005)EACH14$1,650.00$2,450.00$2,850.00$1,900.00$2,153.93$2,000.00
88Downstream anchor terminal section (540-7015)EACH1$1,650.00$2,000.00$1,590.00$1,500.00$1,209.04$1,500.00
89Remove metal beam guard fence (542-7001)LF700$6.00$9.00$3.70$3.50$2.03$3.50
90RM metal beam guard fence trans (thrie-beam) (542-7004)EACH4$225.00$700.00$290.00$275.00$254.00$275.00
91Cable barrier system (install)(TL-4) (543-7002)LF10,773$15.00$15.60$19.00$17.45$15.85$18.00
92Cable barrier terminal sec (install)(TL-4) (543-7018)EACH8$4,000.00$3,120.00$3,450.00$3,250.00$3,169.94$3,250.00
93Cable barrier (remove) (543-7037)LF8,844$6.00$3.75$5.00$4.50$3.81$5.00
94Cable barrier terminal section (remove) (543-7038)EACH7$400.00$370.00$800.00$750.00$375.92$800.00
95Guardrail end treatment (install) (544-7001)EACH15$3,500.00$2,900.00$3,636.00$3,420.00$2,946.42$3,500.00
96Guardrail end treatment (remove) (544-7003)EACH4$450.00$320.00$290.00$275.00$325.12$300.00
97Crash cushion attenuator (move & reset) (545-7002)EACH13$1,300.00$1,400.00$800.00$750.00$1,422.41$800.00
98Crash cushion attenuator (remove) (545-7004)EACH7$1,300.00$785.00$740.00$700.00$797.56$725.00
99Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH7$15,000$7,800.00$8,760.00$8,250.00$7,924.85$15,000
100Chain link fence (install) (8') (550-7005)LF464$70.00$42.75$50.00$46.00$43.43$50.00
101In RD IL (U/P) (type 2) (150W EQ) LED (610-7016)EACH4$1,400.00$2,460.00$2,600.00$2,760.00$1,524.01$1,500.00
102In RD IL (type SA) 40T-8 (250W EQ) LED (610-7124)EACH12$4,700.00$4,875.00$5,170.00$5,470.00$5,384.83$5,500.00
103Conduit (PVC) (schedule 40) (2") (618-7030)LF3,913$12.00$10.00$11.00$11.20$13.21$13.00
104Conduit (PVC) (schedule 80) (2") (bore) (618-7055)LF331$33.00$28.00$30.00$31.40$40.64$40.00
105Conduit (RM) (3/4") (618-7070)LF380$18.00$21.00$22.00$23.50$21.34$21.00
106Electrical conductor (no.8) bare (620-7007)LF4,840$1.50$1.70$1.80$1.90$1.63$2.00
107Electrical conductor (no.8) insulated (620-7008)LF11,814$1.50$1.75$1.80$1.95$1.78$2.00
108Ground box type A (122311)W/apron (624-7002)EACH12$1,000.00$999.00$1,060.00$1,120.00$1,219.21$1,200.00
109Elc SRV type A 240/480 060(SS)SS(T)TP(O) (628-7062)EACH2$5,000.00$6,500.00$6,900.00$7,295.00$7,112.04$7,000.00
110Aluminum signs (type G) (636-7002)SF771$31.00$30.00$30.00$30.00$29.77$27.00
111Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH34$692.00$790.00$900.00$850.00$802.64$850.00
112Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026)EACH6$915.00$845.00$1,050.00$985.00$858.53$985.00
113Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH13$806.00$1,070.00$1,110.00$1,050.00$1,087.13$1,050.00
114Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH6$875.00$1,100.00$1,380.00$1,300.00$1,117.61$1,300.00
115In bridge MNT clearance sign assembly(type N) (644-7061)EACH2$2,500.00$500.00$2,500.00$2,350.00$2,133.61$2,350.00
116Install small roadside sign support and assembly (rail mount) (644-7063)EACH6$4,000.00$3,995.00$9,400.00$8,850.00$4,058.94$9,000.00
117Relocate SM RD SN sup&AM type S80 (644-7067)EACH13$650.00$785.00$635.00$600.00$797.56$600.00
118Remove SM RD SN sup&AM (644-7073)EACH22$80.00$125.90$80.00$75.00$91.44$100.00
119Install LRSS (struct steel) (647-7001)LB4,448$6.25$5.75$7.00$5.75$6.40$6.00
120Install delineator assembly (D-SW)SZ 1(WFLX)GND (658-7003)EACH76$50.00$53.25$80.00$75.00$54.10$80.00
121Install delineator assembly (D-SW)SZ 1(BRF)CTB (658-7012)EACH137$35.00$22.00$19.00$18.00$22.35$20.00
122Install delineator assembly (D-SW)SZ 1(BRF)GF2 (658-7018)EACH38$30.00$29.25$34.00$32.00$29.72$35.00
123Install delineator assembly (D-SY)SZ 1(BRF)CTB (658-7031)EACH24$30.00$22.00$21.00$20.00$22.35$22.00
124Install delineator assembly (D-SY)SZ 1(BRF)GF2 (658-7036)EACH35$30.00$28.00$34.00$82.00$28.45$32.00
125Work zone pavement marking non-removing (W)(arrow) (662-7018)EACH1$200.00$200.00$210.00$200.00$203.20$200.00
126Work zone pavement marking non-removing(W)(word) (662-7030)EACH1$300.00$300.00$318.00$300.00$304.80$300.00
127Work zone pavement marking removing (reflectorized) type II-C-R (662-7053)EACH306$4.00$5.00$5.30$5.00$5.08$5.58
128Work zone pavement marking removing (W)6"(solid) (662-7068)LF86,773$0.50$0.42$0.45$0.42$0.43$0.50
129Work zone pavement marking removing (W)8"(solid) (662-7072)LF6,136$1.00$0.64$0.70$0.64$0.65$0.70
130Work zone pavement marking removing (W)24"(solid) (662-7077)LF24$0.70$30.00$32.00$30.00$30.48$30.00
131Work zone pavement marking removing (W)6"(BKN W/marker) (662-7080)LF13,988$5.00$0.84$0.90$0.84$0.85$1.00
132Work zone pavement marking removing (Y)6"(solid) (662-7100)LF88,368$0.50$0.42$0.45$0.42$0.43$1.00
133Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH32,767$0.25$1.27$2.00$2.00$3.51$2.00
134Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024)LF4,155$1.50$0.88$0.90$0.88$0.89$1.00
135Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030)LF895$6.50$1.10$1.15$1.10$1.12$1.10
136Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF130$11.00$25.00$27.00$25.00$25.40$25.00
137Type I high perf PM (W)6"(broken)(100MIL) (666-7290)LF10,865$0.65$0.88$0.90$0.88$0.89$1.00
138Type I high perf PM (W)6"(solid)(100MIL) (666-7293)LF46,970$0.78$0.76$0.80$0.76$0.77$0.75
139Type I high perf PM (Y)6"(solid)(100MIL) (666-7305)LF46,135$0.78$0.76$0.80$0.76$0.77$0.75
140Prefabricated PM type C (W)(LN reduct arrow) (668-7100)EACH2$500.00$600.00$635.00$600.00$609.61$600.00
141Reflectorized pavement marker type II-A-A (672-7004)EACH28$5.50$15.00$16.00$15.00$15.24$20.00
142Reflectorized pavement marker type II-C-R (672-7006)EACH754$5.50$7.50$8.00$7.50$7.62$10.00
143Eliminating existing PM & markers (4") (677-7001)LF10,217$0.75$0.50$0.50$0.50$0.51$0.50
144Eliminating existing PM & markers (arrow) (677-7009)EACH1$220.00$100.00$105.00$100.00$101.60$100.00
145Eliminating existing PM & markers (word) (677-7015)EACH1$220.00$100.00$105.00$100.00$101.60$100.00
146Bonding course (3007-7001)GAL30,309$3.50$2.78$4.80$5.50$4.57$4.00
147Intrlck art concrete BLKS (4" min) (4001-7002)SF13,600$12.00$45.00$19.00$8.00$14.83$45.00
TxDOT contract A00184795: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of April 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy