TxDOT contract A00193539 bid tabulation
Hazard Elimination & Safety, SH 302 (FM 866 to .). Let by Texas DOT on January 6, 2026, Ector, Odessa District. 3 bids received; low bid $16,211,726 by Reece Albert, Inc., +37% against the engineer's estimate of $11,813,341.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 112
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Reece Albert, Inc. | $16,211,726 | Low | +37% |
| 2 | Ragle Construction, Inc. | $16,378,565 | +1.0% | +39% |
| 3 | Jones Bros. Dirt & Paving Contractors, Inc. | $16,519,822 | +2.0% | +40% |
Engineer's estimate: $11,813,341.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Reece Albert, Inc. | 2. Ragle Construction, Inc. | 3. Jones Bros. Dirt & Paving Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Remove (0"-12") TRT/untrt base & asphalt pavement (105-7052) | SY | 32,994 | $6.00 | $13.36 | $10.00 | $20.00 |
| 2 | Excavation (roadway) (110-7001) | CY | 25,987 | $14.00 | $7.47 | $50.00 | $31.75 |
| 3 | Embankment (final)(DC)(type B) (132-7004) | CY | 25,556 | $15.00 | $26.79 | $15.00 | $26.50 |
| 4 | Blading (150-7002) | HR | 100 | $150.00 | $214.89 | $157.00 | $400.00 |
| 5 | Broadcast seed (permanent_rural_sand) (164-7001) | SY | 145,688 | $0.25 | $0.21 | $0.19 | $0.21 |
| 6 | Proof rolling (216-7001) | HR | 20 | $100.00 | $181.73 | $133.20 | $150.00 |
| 7 | FL BS (compacted in place)(type A GR 4) (6") (247-7046) | SY | 65,216 | $15.00 | $15.16 | $10.00 | $15.50 |
| 8 | Prime coat (AE-P) (310-7001) | GAL | 13,043 | $5.00 | $6.35 | $6.00 | $4.86 |
| 9 | Asphalt (AC-20-5TR) (316-7007) | GAL | 24,783 | $5.00 | $5.93 | $5.50 | $5.12 |
| 10 | Aggregate (type-PB, GR-4)(sac-A) (316-7136) | CY | 655 | $138.00 | $582.05 | $175.00 | $245.00 |
| 11 | SP mixes SP-B sac-B PG76-22 (344-7008) | TON | 21,522 | $110.00 | $181.22 | $160.00 | $126.00 |
| 12 | Tom-C PG76-22 sac-A (347-7001) | TON | 10,474 | $157.00 | $219.80 | $155.00 | $150.00 |
| 13 | Tack coat (347-7011) | GAL | 6,521 | $5.00 | $2.85 | $6.75 | $4.42 |
| 14 | Flex pavement structure repair (4"-6") (351-7024) | SY | 333 | $200.00 | $107.46 | $165.00 | $340.00 |
| 15 | Cem stabil BKFL (400-7010) | CY | 575 | $200.00 | $209.65 | $109.00 | $352.00 |
| 16 | Trench excavation protection (402-7001) | LF | 313 | $8.00 | $45.72 | $21.00 | $55.00 |
| 17 | Drilled shaft (non - reinforced) (12 in) (416-7024) | LF | 7 | $201.83 | $100.00 | $198.00 | |
| 18 | Drilled shaft (sign mounts) (24 in) (416-7028) | LF | 226 | $200.00 | $257.89 | $200.00 | $253.00 |
| 19 | Drilled shaft (roadway illumination pole) (30 in) (416-7040) | LF | 620 | $458.00 | $476.54 | $425.00 | $467.50 |
| 20 | Class S concrete utility protection pad (420-7149) | CY | 22.14 | $2,421.18 | $1,040.00 | $1,265.00 | |
| 21 | Riprap (concrete)(4 in) (432-7001) | CY | 228 | $650.00 | $572.56 | $673.00 | $990.00 |
| 22 | Riprap (mow strip)(4 in) (432-7013) | CY | 129 | $650.00 | $756.85 | $681.00 | $742.50 |
| 23 | RC pipe (CL III)(18 in) (464-7003) | LF | 356 | $172.54 | $82.50 | $110.00 | |
| 24 | RC pipe (CL III)(24 in) (464-7005) | LF | 2,120 | $125.00 | $182.52 | $125.50 | $165.00 |
| 25 | RC pipe (CL III)(30 in) (464-7007) | LF | 1,132 | $196.96 | $143.50 | $214.50 | |
| 26 | Manh (complete)(PRM)(60IN) (465-7003) | EACH | 3 | $10,499 | $12,742 | $8,410.00 | $15,950 |
| 27 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 2 | $7,414.00 | $8,451.81 | $5,840.00 | $9,350.00 |
| 28 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 2 | $2,589.28 | $2,625.00 | $2,200.00 | |
| 29 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 4 | $2,736.44 | $2,625.00 | $2,475.00 | |
| 30 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 22 | $2,497.00 | $2,833.10 | $3,015.00 | $2,750.00 |
| 31 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 11 | $2,642.00 | $3,079.68 | $3,215.00 | $3,025.00 |
| 32 | Set (type II) (30 in) (RCP) (4: 1) (C) (467-7346) | EACH | 12 | $4,990.06 | $5,770.00 | $5,500.00 | |
| 33 | Removing structure (set) (496-7004) | EACH | 20 | $600.00 | $600.02 | $800.00 | $1,100.00 |
| 34 | Removing structure (wingwall) (496-7005) | EACH | 10 | $1,300.00 | $2,044.04 | $1,500.00 | $1,100.00 |
| 35 | Removing structure (pipe) (496-7037) | EACH | 28 | $898.00 | $771.45 | $3,000.00 | $825.00 |
| 36 | Mobilization (500-7001) | LS | 1 | $668,680 | $1,168,968 | $1,635,000 | $800,000 |
| 37 | Barricades, signs and traffic handling (502-7001) | MO | 18 | $12,500 | $8,503.87 | $72,500 | $30,000 |
| 38 | Portable changeable message sign (503-7002) | EACH | 12 | $6,000.00 | $15,674 | $10,000 | $19,250 |
| 39 | TMA (stationary) (505-7001) | DAY | 360 | $209.00 | $288.99 | $287.00 | $137.50 |
| 40 | TMA (mobile operation) (505-7003) | DAY | 15 | $400.00 | $650.69 | $620.00 | $935.00 |
| 41 | Construction exits (install) (type 1) (506-7020) | SY | 666 | $25.00 | $37.48 | $15.00 | $28.00 |
| 42 | Construction exits (remove) (506-7024) | SY | 666 | $11.00 | $9.00 | $10.00 | $25.00 |
| 43 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 21,357 | $8.00 | $8.41 | $7.50 | $8.25 |
| 44 | Biodegradable erosion control logs (remove) (506-7046) | LF | 21,357 | $1.00 | $1.12 | $1.00 | $1.10 |
| 45 | PTB (fur&inst)(SSCB or CSB)(type 1)or(steel) (512-7085) | LF | 7,740 | $20.00 | $26.46 | $21.00 | $13.20 |
| 46 | PTB (move)(SSCB or CSB)(type 1)or(steel) (512-7086) | LF | 25,800 | $8.00 | $8.25 | $9.50 | $11.00 |
| 47 | PTB (remove)(SSCB or CSB)(type 1)or(steel) (512-7088) | LF | 7,740 | $15.00 | $20.19 | $11.00 | $13.20 |
| 48 | Driveways (ACP) (530-7010) | SY | 221 | $62.00 | $75.73 | $75.00 | $225.00 |
| 49 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 23,600 | $0.20 | $0.36 | $0.11 | $0.39 |
| 50 | Concrete directional island (536-7004) | SY | 6,838 | $100.00 | $99.44 | $130.00 | $275.00 |
| 51 | Metal W-beam guard fence (steel post) (540-7002) | LF | 1,714 | $37.00 | $38.12 | $31.00 | $37.40 |
| 52 | Downstream anchor terminal section (540-7015) | EACH | 5 | $1,562.00 | $1,513.70 | $1,700.00 | $1,485.00 |
| 53 | Cable barrier system (install)(TL-4) (543-7002) | LF | 2,041 | $13.00 | $28.31 | $27.60 | $27.78 |
| 54 | Cable barrier terminal sec (install)(TL-4) (543-7018) | EACH | 11 | $2,919.00 | $7,848.81 | $3,630.00 | $7,700.00 |
| 55 | Cable barrier (remove) (543-7037) | LF | 4,230 | $7.00 | $6.73 | $6.00 | $6.60 |
| 56 | Guardrail end treatment (install) (544-7001) | EACH | 4 | $3,942.00 | $4,485.04 | $3,200.00 | $4,400.00 |
| 57 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 20 | $1,655.00 | $1,672.85 | $1,410.00 | $3,850.00 |
| 58 | Crash cushion attenuator (remove) (545-7004) | EACH | 6 | $1,210.00 | $1,294.68 | $1,181.00 | $1,650.00 |
| 59 | Crash cushion attenuator (install)(L)(N)(TL3) (545-7006) | EACH | 6 | $10,000 | $9,429.14 | $8,500.00 | $30,800 |
| 60 | Remove RD IL asm (trans-base) (610-7009) | EACH | 12 | $450.00 | $840.94 | $750.00 | $825.00 |
| 61 | In RD IL (type SA) 50T-10 (400W EQ) LED (610-7198) | EACH | 60 | $5,000.00 | $8,689.76 | $7,750.00 | $8,525.00 |
| 62 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 13,550 | $11.00 | $7.85 | $7.00 | $7.70 |
| 63 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 2,270 | $39.00 | $28.03 | $25.00 | $27.50 |
| 64 | Electrical conductor (no.8) bare (620-7007) | LF | 16,720 | $1.20 | $1.68 | $1.50 | $1.65 |
| 65 | Electrical conductor (no.8) insulated (620-7008) | LF | 33,440 | $1.50 | $1.96 | $1.75 | $1.93 |
| 66 | Ground box type A (122311) (624-7001) | EACH | 14 | $1,408.00 | $1,513.70 | $1,350.00 | $1,485.00 |
| 67 | Ground box type A (122311)W/apron (624-7002) | EACH | 10 | $2,130.39 | $1,900.00 | $2,090.00 | |
| 68 | Remove ground box (624-7013) | EACH | 8 | $250.00 | $560.63 | $500.00 | $550.00 |
| 69 | Remove electrical services (628-7002) | EACH | 3 | $813.00 | $1,121.26 | $1,000.00 | $1,100.00 |
| 70 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 3 | $11,000 | $16,819 | $15,000 | $16,500 |
| 71 | Aluminum signs (type G) (636-7002) | SF | 1,187 | $30.00 | $39.24 | $32.00 | $38.50 |
| 72 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 33 | $600.00 | $840.94 | $650.00 | $825.00 |
| 73 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 77 | $650.00 | $953.07 | $740.00 | $935.00 |
| 74 | Install small roadside sign support and assembly type 10BWG(1)SA(U) (644-7007) | EACH | 3 | $850.00 | $953.07 | $800.00 | $935.00 |
| 75 | Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025) | EACH | 16 | $850.00 | $1,009.13 | $775.00 | $990.00 |
| 76 | Install small roadside sign support and assembly TYS80(1)SA(P-BM) (644-7026) | EACH | 30 | $900.00 | $1,110.05 | $860.00 | $1,089.00 |
| 77 | Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028) | EACH | 31 | $900.00 | $1,110.05 | $925.00 | $1,089.00 |
| 78 | Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031) | EACH | 14 | $1,000.00 | $1,345.51 | $1,100.00 | $1,320.00 |
| 79 | Install small roadside sign support and assembly TYS80(1)SA(U-BM) (644-7034) | EACH | 4 | $1,345.51 | $1,200.00 | $1,320.00 | |
| 80 | Remove SM RD SN sup&AM (644-7073) | EACH | 95 | $100.00 | $184.54 | $80.00 | $150.00 |
| 81 | Install LRSS (struct steel) (647-7001) | LB | 7,721 | $8.00 | $8.97 | $7.50 | $8.80 |
| 82 | Install delineator assembly (D-SY)SZ 1(BRF)GF1 (658-7034) | EACH | 25 | $42.00 | $39.24 | $45.00 | $38.50 |
| 83 | Work zone pavement marking non-removing (W)6"(broken) (662-7005) | LF | 79,407 | $0.20 | $0.28 | $0.37 | $0.41 |
| 84 | Work zone pavement marking non-removing (W)6"(solid) (662-7008) | LF | 91,200 | $0.20 | $0.24 | $0.36 | $0.40 |
| 85 | Work zone pavement marking non-removing (W)12"(solid) (662-7015) | LF | 384 | $2.00 | $1.68 | $6.50 | $7.15 |
| 86 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 88,083 | $0.20 | $0.24 | $0.36 | $0.40 |
| 87 | Reflectorized pavement marking type I (W)6"(DOT)(100MIL) (666-7009) | LF | 1,262 | $1.20 | $1.35 | $0.85 | $0.94 |
| 88 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 797 | $1.00 | $2.24 | $1.02 | $1.12 |
| 89 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 23,540 | $0.80 | $1.07 | $1.02 | $1.12 |
| 90 | Reflectorized pavement marking type I (W)12"(solid)(100MIL) (666-7030) | LF | 310 | $6.73 | $1.50 | $1.65 | |
| 91 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 7,200 | $0.80 | $0.84 | $0.85 | $0.94 |
| 92 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 43,369 | $0.60 | $0.80 | $0.85 | $0.94 |
| 93 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 33,165 | $0.60 | $0.80 | $0.85 | $0.94 |
| 94 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 500 | $14.00 | $15.70 | $13.25 | $14.58 |
| 95 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 34 | $251.00 | $302.74 | $225.00 | $247.50 |
| 96 | Prefabricated PM type C (W)(uturn arrow) (668-7096) | EACH | 11 | $301.00 | $728.82 | $430.00 | $473.00 |
| 97 | Prefabricated PM type C (W)(LN reduct arrow) (668-7100) | EACH | 6 | $550.00 | $672.76 | $500.00 | $550.00 |
| 98 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 46 | $250.00 | $358.80 | $325.00 | $357.50 |
| 99 | Prefabricated PM type C (W)(symbol) (668-7109) | EACH | 10 | $500.00 | $840.94 | $1,870.00 | $2,057.00 |
| 100 | Prefabricated PM type C (W)(36")(yld tri) (668-7111) | EACH | 30 | $20.00 | $28.03 | $50.00 | $55.00 |
| 101 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 2,197 | $4.50 | $4.77 | $4.50 | $4.95 |
| 102 | Eliminating existing PM & markers (4") (677-7001) | LF | 41,340 | $0.50 | $0.78 | $0.88 | $1.00 |
| 103 | Eliminating existing PM & markers (6") (677-7002) | LF | 225,149 | $0.40 | $0.89 | $0.90 | $0.85 |
| 104 | Bonding course (3007-7001) | GAL | 18,215 | $4.00 | $2.82 | $5.90 | $4.78 |
| 105 | Thermoplastic pipe (PP) (18") (468-7001) | LF | 0 | $0.00 | $0.00 | $0.00 | |
| 106 | Thermoplastic pipe (PP) (24") (468-7002) | LF | 0 | $125.00 | $0.00 | $0.00 | $0.00 |
| 107 | Thermoplastic pipe (PP) (30") (468-7003) | LF | 0 | $0.00 | $0.00 | $0.00 | |
| 108 | Set (type II) (18 in) (TP) (4: 1) (C) (467-7310) | EACH | 0 | $0.00 | $0.00 | $0.00 | |
| 109 | Set (type II) (18 in) (TP) (6: 1) (P) (467-7312) | EACH | 0 | $0.00 | $0.00 | $0.00 | |
| 110 | Set (type II) (24 in) (TP) (4: 1) (C) (467-7330) | EACH | 0 | $2,497.00 | $0.00 | $0.00 | $0.00 |
| 111 | Set (type II) (24 in) (TP) (6: 1) (P) (467-7332) | EACH | 0 | $2,642.00 | $0.00 | $0.00 | $0.00 |
| 112 | Set (type II) (30 in) (TP) (4: 1) (C) (467-7350) | EACH | 0 | $0.00 | $0.00 | $0.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.