TxDOT contract A00196824 bid tabulation

Intersection Improvement, SH 36 (1.28 Mi S of SH 21 to 0.71 Mi N of CR 122). Let by Texas DOT on August 5, 2026, Burleson, Bryan District. 6 bids received; low bid $4,987,865 by Big Creek Construction, LTD., -6.3% against the engineer's estimate of $5,320,689.

Owner
Texas DOT
Letting
05 AUG 2026
Pay items
125
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Big Creek Construction, LTD.$4,987,865Low-6.0%
2Fluor Enterprises, Inc.$5,427,789+9.0%+2.0%
3Texas Materials Group, Inc.$5,449,952+9.0%+2.0%
4Larry Young Paving, Inc.$5,538,882+11%+4.0%
5Knife River Corporation - South$5,590,058+12%+5.0%
6Brazos Paving, Inc.$6,623,664+33%+24%
TxDOT contract A00196824: bids by rank

Engineer's estimate: $5,320,689.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Big Creek Construction, LTD.2. Fluor Enterprises, Inc.3. Texas Materials Group, Inc.4. Larry Young Paving, Inc.5. Knife River Corporation - South6. Brazos Paving, Inc.
1Preparing row (100-7002)STA83.64$500.00$600.00$142.32$516.00$220.00$175.00$3,070.00
2Removing concrete (driveways) (104-7011)SY116$19.00$25.00$17.00$41.00$24.00$40.00$24.40
3Removing concrete (miscellaneous) (104-7047)CY3$300.00$200.00$316.00$155.00$460.00$150.00$650.00
4Remove (13") TRT/untrt base & asphalt pavement (105-7033)SY17,456$15.00$8.00$7.30$11.50$9.50$7.50$11.15
5Excavation (roadway) (110-7001)CY4,005$12.00$17.00$20.00$35.00$15.00$12.00$27.30
6Embankment (final)(OC)(type C) (132-7005)CY3,317$20.00$17.00$11.50$15.00$9.50$6.00$34.65
7Backfill (type A or B) (134-7004)STA83.64$160.00$250.00$302.00$633.00$240.00$244.50$247.20
8Furn & place topsoil (4") (160-7002)SY47,691$1.00$0.75$0.80$1.10$0.75$1.40$1.60
9Broadcast seed (permanent_rural_sand) (164-7001)SY32,240$0.50$0.19$0.10$0.19$0.25$0.20$0.22
10Broadcast seed (permanent_rural_clay) (164-7002)SY15,451$0.19$0.10$0.19$0.25$0.20$0.22
11Broadcast seed (temporary_warm_cool) (164-7007)SY47,691$0.25$0.16$0.10$0.16$0.25$0.15$0.18
12Vegetative watering (168-7001)TGL477$7.50$17.00$1.00$23.00$38.00$44.00$138.00
13Proof rolling (216-7001)HR3$150.00$77.50$440.00$130.00$90.00$139.25
14FL BS (compacted in place)(type A GR 1-2) (6") (247-7044)SY26,812$12.00$17.00$12.50$20.00$18.00$21.00$20.20
15FL BS (compacted in place)(type A GR 1-2) (14") (247-7353)SY3,428$45.00$35.50$62.00$45.00$56.00$40.75
16Lime (com or QK)(slurry) or QK(dry) (260-7001)TON77$350.00$328.00$328.00$430.00$458.00$406.50
17Lime TRT (existing material)(10") (260-7008)SY3,110$7.00$4.30$10.00$10.00$13.80$15.85
18Cement (275-7001)TON283$210.00$200.00$174.00$190.00$220.00$151.00$299.50
19Cement TRT (existing material)(8") (275-7003)SY28,539$2.50$2.50$3.50$1.45$2.25$1.00$10.15
20Cem TRT(PLNT MX)(CL M)(tya)(GR1-2)(10") (276-7205)SY372$25.00$80.00$54.50$60.00$51.00$50.00$45.25
21Prime coat (AE-P) (310-7001)GAL83$10.00$10.00$10.50$21.00$6.50$10.00$11.65
22Prime coat (MC-30) (310-7004)GAL6,394$5.00$5.50$6.10$6.00$5.75$5.50$6.35
23SP mixes SP-B PG64-22 (344-7001)TON13,346$110.00$90.00$113.00$103.00$110.00$108.00$114.75
24SP mixes SP-C sac-A PG70-22 (344-7020)TON8,890$130.00$110.00$136.00$115.00$130.00$125.00$132.30
25Tack coat (344-7077)GAL9,641$4.10$3.00$4.60$4.00$3.50$4.00$6.90
26Plane & text asphalt concrete pavement(0" to 3") (354-7003)SY4,589$3.00$2.90$4.50$2.00$3.00$3.75
27Planing asphalt concrete pavement(0" to 3") (354-7033)SY1,778$3.00$6.00$5.00$6.00$3.25$5.50$4.25
28Planing asphalt concrete pavement(7") (354-7056)SY874$10.00$10.00$6.70$12.00$13.00$8.50$11.25
29Drilled shaft (traffic signal pole) (36 in) (416-7044)LF13.20$450.00$496.00$414.00$660.00$400.00$582.40
30Class A concrete (collar) (420-7008)EACH2$2,500.00$1,690.00$1,553.00$1,400.00$1,500.00$443.60
31Concrete box culvert (3 FT X 2 FT)(extend) (462-7056)LF22$550.00$850.00$788.00$725.00$460.00$700.00$713.30
32RC pipe (CL III)(18 in) (464-7003)LF766$70.00$80.00$70.00$64.00$65.00$62.00$90.85
33RC pipe (CL III)(24 in) (464-7005)LF16$150.00$152.00$140.00$96.00$135.00$116.40
34RC pipe (CL III)(36 in) (464-7009)LF88$175.00$200.00$253.00$233.00$150.00$225.00$196.75
35Junct box (complete)(JB)(3FT X 3FT)(FTW) (465-7281)EACH1$5,800.00$7,500.00$6,190.00$5,692.00$5,700.00$5,500.00$6,560.00
36Wingwall (PW - 2) (HW=3 FT) (466-7187)EACH1$10,200$10,000$6,760.00$6,210.00$9,400.00$6,000.00$11,226
37Set (type I)(S= 3 FT)(HW= 3 FT)(3:1)(C) (467-7040)EACH3$6,000.00$8,000.00$9,010.00$8,280.00$11,000$8,000.00$8,620.00
38Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH83$1,150.00$1,500.00$1,070.00$984.00$1,900.00$950.00$3,350.00
39Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH3$2,200.00$2,200.00$2,820.00$2,587.00$2,000.00$2,500.00$3,750.00
40Set (type II) (36 in) (RCP) (6: 1) (P) (467-7368)EACH4$6,540.00$7,000.00$5,630.00$5,175.00$5,200.00$5,000.00$7,087.00
41Removing structure (set) (496-7004)EACH12$450.00$500.00$845.00$776.00$390.00$750.00$562.00
42Removing structure (wingwall) (496-7005)EACH6$1,670.00$2,500.00$1,690.00$1,552.00$1,000.00$1,500.00$1,560.00
43Removing structure (pipe) (496-7007)LF776$20.00$20.00$39.50$36.00$24.00$35.00$37.50
44Mobilization (500-7001)LS1$394,125$412,000$447,000$402,190$430,000$410,000$250,644
45Barricades, signs and traffic handling (502-7001)MO18$7,000.00$3,250.00$5,090.00$1,057.00$4,000.00$5,850.00$6,635.00
46Portable changeable message sign (503-7002)EACH5$5,500.00$11,500$1,620.00$4,962.00$1,700.00$2,900.00$19,258
47TMA (stationary) (505-7001)DAY231$245.00$250.00$485.00$433.00$250.00$575.00$360.00
48TMA (mobile operation) (505-7003)DAY22$300.00$550.00$656.00$433.00$690.00$932.00$744.00
49Rock filter dams (install) (type 2) (506-7002)LF1,080$35.00$36.00$47.50$37.00$45.00$36.00$43.15
50Rock filter dams (remove) (506-7011)LF1,171$12.50$10.00$7.20$10.35$13.00$10.00$12.00
51Temporary sediment control fence (install) (506-7039)LF944$3.60$5.00$3.90$4.00$4.50$3.50$4.20
52Temporary sediment control fence (remove) (506-7041)LF944$1.25$1.00$0.95$1.00$1.25$1.00$1.20
53Rock filter dams (install) (type 2) 6:1 (506-7048)LF91$45.00$132.00$42.00$50.00$40.00$48.00
54Constructing detours (508-7001)SY60$100.00$250.00$174.00$191.00$170.00$171.00$73.50
55Driveways (concrete) (530-7006)SY95$125.00$150.00$248.00$233.00$130.00$258.00$113.70
56Driveways (ACP) (530-7010)SY3,257$48.00$38.00$56.00$34.00$49.00$75.00$47.75
57Concrete sidewalks (4") (531-7001)SY3$100.00$500.00$204.00$191.00$110.00$185.00$458.75
58Mill rumble strips (asphalt) (shoulder) (533-7001)LF20,911$0.23$0.32$0.15$0.60$0.25$0.10$0.25
59Mill rumble strips (asphalt) (centerline) (533-7002)LF16,315$0.23$0.35$0.15$0.60$0.25$0.15$0.30
60Concrete directional island (536-7004)SY485$125.00$220.00$207.00$170.00$210.00$196.50
61Mailbox install-M (TWG-post) type 1 (560-7001)EACH4$650.00$550.00$561.00$569.00$700.00$550.00$650.50
62Mailbox install-S (WC-post) type 3 (560-7004)EACH20$250.00$200.00$168.00$171.00$250.00$165.00$180.00
63Mailbox install-D (WC-post) type 3 (560-7005)EACH3$250.00$225.00$179.00$181.00$330.00$175.00$209.65
64Replace luminaire W/(250W EQ) LED (610-7012)EACH2$1,000.00$419.00$725.00$610.00$700.00$492.00
65Tray cable (4 conductor) (8 AWG) (621-7008)LF326$7.00$7.10$3.10$8.50$3.00$8.35
66Zinc-coat steel wire strand (3/16") (625-7001)LF286$3.00$2.10$3.10$4.75$3.00$2.50
67Zinc-coat steel wire strand (5/16") (625-7003)LF163$3.00$2.50$4.14$5.25$4.00$2.90
68Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH33$700.00$650.00$663.00$673.00$660.00$650.00$756.00
69Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH15$750.00$765.00$776.00$800.00$750.00$924.00
70Install small roadside sign support and assembly TYS80(1)SA(T) (644-7028)EACH2$1,000.00$1,020.00$1,035.00$1,300.00$1,000.00$1,400.00
71Install small roadside sign support and assembly TYS80(1)SA(U) (644-7031)EACH1$1,250.00$1,280.00$1,294.00$1,000.00$1,250.00$1,284.00
72Remove SM RD SN sup&AM (644-7073)EACH57$132.00$100.00$102.00$104.00$100.00$100.00$137.80
73Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH4$100.00$60.00$61.00$62.00$110.00$60.00$80.25
74Replace delineator assembly (D-SW)SZ 1(WFLX)GF2 (658-7160)EACH6$20.00$20.50$21.00$35.00$20.00$62.30
75Replace delineator assembly (D-SW)SZ 1(BRF)CTB (658-7177)EACH4$20.00$16.50$27.00$31.00$16.00$68.30
76Replace object marker assembly (OM-2Z)(WFLX)SRFHH (658-7292)EACH4$250.00$255.00$259.00$330.00$250.00$275.50
77Install OM SM RD sign (1-OM-PW)Y (658-7317)EACH23$42.00$25.00$10.00$10.35$31.00$10.00$6.00
78Install OM SM RD sign (1-OM-PW)R (658-7318)EACH3$28.00$25.00$12.00$12.42$31.00$12.00$6.00
79Work zone pavement marking non-removing (W)6"(solid) (662-7008)LF38,043$0.25$0.27$0.25$0.25$0.25$0.25$0.35
80Work zone pavement marking non-removing (W)8"(solid) (662-7012)LF1,674$0.75$0.40$0.40$1.00$0.40$1.00
81Work zone pavement marking non-removing (Y)6"(solid) (662-7038)LF40,081$0.32$0.27$0.25$0.25$0.25$0.25$0.35
82Work zone pavement marking removing (reflectorized) type I-C (662-7049)EACH1,592$4.15$4.00$2.10$2.00$4.75$2.00$4.60
83Work zone pavement marking removing (reflectorized) type II-A-A (662-7051)EACH3,184$4.15$4.00$2.10$2.00$4.75$2.00$4.60
84Work zone pavement marking removing (traffic BTN) type W (662-7057)EACH4,780$3.00$4.25$1.30$1.25$5.25$1.20$5.00
85Work zone pavement marking removing (traffic BTN) type Y (662-7059)EACH6,372$2.00$4.25$1.30$1.25$5.25$1.20$5.00
86Work zone pavement marking removing (Y)6"(solid) (662-7100)LF391$2.50$2.10$2.00$2.50$2.00$2.40
87Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH28$1.40$1.50$2.00$1.00$0.75$1.50$1.80
88Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH1,968$1.30$1.50$5.00$1.00$0.75$1.50$1.80
89Reflectorized pavement marking type I (W)8"(DOT)(060MIL) (666-7016)LF70$3.00$1.10$1.00$3.25$1.00$3.00
90Reflectorized pavement marking type I (W)8"(DOT)(090MIL) (666-7017)LF460$1.50$2.00$1.10$1.00$2.00$1.00$1.80
91Reflectorized pavement marking type I (W)8"(solid)(060MIL) (666-7022)LF1,427$1.00$0.90$0.88$1.00$0.85$1.00
92Reflectorized pavement marking type I (W)8"(solid)(090MIL) (666-7023)LF4,010$1.10$1.20$1.10$1.10$1.50$1.05$1.35
93Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035)LF72$7.00$18.00$8.50$8.30$22.00$8.00$21.10
94Reflectorized pavement marking type I (W)(arrow)(060MIL) (666-7040)EACH1$150.00$212.00$207.00$190.00$200.00$180.00
95Reflectorized pavement marking type I (W)(arrow)(090MIL) (666-7041)EACH16$170.00$180.00$233.00$228.00$220.00$220.00$210.00
96Reflectorized pavement marking type I (W)(word)(060MIL) (666-7064)EACH1$180.00$212.00$207.00$220.00$200.00$210.00
97Reflectorized pavement marking type I (W)(word)(090MIL) (666-7065)EACH10$200.00$200.00$233.00$228.00$250.00$220.00$240.00
98Ref pavement marking type I(W)18"(yld tri)(090MIL) (666-7086)EACH16$50.00$53.00$52.00$57.00$50.00$54.00
99Reflectorized pavement marking type II (W) 8" (DOT) (666-7177)LF310$0.75$0.50$0.47$1.00$0.45$0.90
100Reflectorized pavement marking type II (W) 8" (solid) (666-7179)LF3,517$0.60$0.60$0.57$0.75$0.55$0.65
101Reflectorized pavement marking type II (W) (arrow) (666-7186)EACH9$100.00$79.50$78.00$110.00$75.00$108.00
102Reflectorized pavement marking type II (W) (word) (666-7194)EACH7$100.00$79.50$78.00$130.00$75.00$120.00
103Reflectorized pavement marking type II (W) 18" (yld tri) (666-7200)EACH57$40.00$37.00$36.00$44.00$35.00$42.00
104Reflectorized pavement marking type II (Y) 6" (solid) (666-7213)LF4,543$0.40$0.35$0.36$0.50$0.35$0.45
105Reflectorized pavement marking type I (W)6"(broken)(060MIL) (666-7406)LF2,970$0.70$0.55$0.52$1.00$0.50$0.85
106Reflectorized pavement marking type I (W)6"(solid)(060MIL) (666-7409)LF11,876$0.70$0.55$0.52$0.75$0.50$0.75
107Reflectorized pavement marking type I (W)6"(solid)(090MIL) (666-7410)LF19,021$0.60$0.70$0.60$0.59$0.75$0.60$0.80
108Reflectorized pavement marking type I (Y)6"(broken)(090MIL) (666-7419)LF3,186$0.60$0.70$0.60$0.59$1.00$0.60$0.85
109Reflectorized pavement marking type I (Y)6"(solid)(060MIL) (666-7421)LF7,970$0.65$0.55$0.52$0.75$0.50$0.75
110Reflectorized pavement marking type I (Y)6"(solid)(090MIL) (666-7422)LF24,659$0.60$0.75$0.60$0.59$0.75$0.60$0.80
111Reflectorized pavement marker type I-C (672-7002)EACH28$5.00$25.00$6.40$6.20$94.00$6.00$90.00
112Reflectorized pavement marker type II-A-A (672-7004)EACH15,472$3.00$0.25$0.01$4.65$1.50$4.50$1.40
113Reflectorized pavement marker type II-C-R (672-7006)EACH149$10.00$6.40$6.20$44.00$6.00$42.00
114Eliminating existing PM & markers (4") (677-7001)LF12,500$0.40$0.60$0.55$0.52$0.75$0.50$0.75
115Eliminating existing PM & markers (8") (677-7004)LF1,775$1.00$0.80$0.78$1.00$0.75$1.00
116Eliminating existing PM & markers (arrow) (677-7009)EACH4$60.00$79.50$78.00$75.00$75.00$72.00
117Eliminating existing PM & markers (word) (677-7015)EACH4$70.00$79.50$78.00$88.00$75.00$83.85
118Vehicle signal section (12")LED(yel) (682-7003)EACH2$550.00$391.00$561.00$610.00$542.00$460.00
119Vehicle signal section (12")LED(red) (682-7005)EACH2$550.00$391.00$561.00$610.00$542.00$460.00
120Backplate W/reflectorized border (1SEC) (682-7048)EACH4$200.00$203.00$207.00$200.00$200.00$240.00
121Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031)LF143$4.00$3.00$4.15$6.75$4.00$3.50
122Traffic signal CBL (type B)(12 AWG)(3 conductor) (684-7060)LF540$4.00$1.10$4.15$5.25$4.00$1.30
123Remove traffic signal CBL (684-7085)LF745$1.00$1.60$0.62$1.00$0.60$1.90
124Ins traffic signal PL AM (S)STR(type B)lum (686-7008)EACH1$16,000$12,765$12,420$10,500$12,000$15,070
125Remove traffic signal PL (686-7313)EACH1$1,000.00$4,610.00$310.50$4,200.00$300.00$5,420.00
TxDOT contract A00196824: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy