TxDOT contract A00197563 bid tabulation

Transportation Non-Roadway, FM 2556 (1330 FT S of FM 2556 & CR 407 Int. to Along FM 2556). Let by Texas DOT on January 6, 2026, Cameron, Pharr District. 7 bids received; low bid $6,565,146 by Mor-Wil, L.L.C., -11% against the engineer's estimate of $7,384,759.

Owner
Texas DOT
Letting
06 JAN 2026
Pay items
75
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Mor-Wil, L.L.C.$6,565,146Low-11%
23LW Civil LLC$6,623,433+1.0%-10%
3Go Underground, Limited Liability Company$7,942,722+21%+8.0%
4Clore Equipment LLC$7,997,844+22%+8.0%
5Foremost Paving, Inc.$8,168,536+24%+11%
6Ioc Company LLC$11,290,746+72%+53%
7Texas Cordia Construction, LLC$14,164,618+116%+92%
TxDOT contract A00197563: bids by rank

Engineer's estimate: $7,384,759.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Mor-Wil, L.L.C.2. 3LW Civil LLC3. Go Underground, Limited Liability Company4. Clore Equipment LLC5. Foremost Paving, Inc.6. Ioc Company LLC
1Preparing row (100-7002)STA9$3,500.00$3,777.78$2,169.44$800.00$75,535$6,500.00$10,000
2Removing concrete (driveways) (104-7011)SY187$25.45$55.67$12.00$22.95$38.70$30.00
3Excavation (roadway) (110-7001)CY12,172$11.00$6.98$23.93$8.00$5.94$17.70$15.00
4Excavation (channel) (110-7002)CY5,370$7.10$27.90$12.00$6.61$17.70$20.00
5Embankment (final)(DC)(type C) (132-7006)CY6,162$6.00$6.62$10.50$12.00$4.63$24.50$15.00
6Furn & place topsoil (vehicle) (160-7007)CY50$32.50$136.00$175.62$24.00$65.18$24.70$100.00
7Drill seed (permanent_rural_clay) (164-7010)SY5,267$1.00$1.03$0.86$0.76$0.83$0.70$0.68
8Drill seed (temporary_warm) (164-7013)SY5,267$0.75$0.76$0.62$0.57$0.71$0.60$0.48
9Hydro mulch seed (permanent_rural_sandy) (164-7017)SY3,350$1.20$1.06$0.90$0.71$0.60$0.84
10Vegetative watering (168-7001)TGL506.14$11.00$85.00$75.00$54.64$59.52$36.00$26.00
11Soil ret BLKT(SL_mod_clay_long) (169-7002)SY4,388$2.50$1.84$1.62$1.37$3.53$2.70$1.25
12FL BS (compacted in place)(type A or B GR 4)(8") (247-7087)SY410$43.12$38.78$21.15$20.29$6.20$38.50
13FL BS (roadway del)(type E GR 4)(final pos) (247-7277)CY383$40.00$26.21$108.17$74.98$67.01$37.70$166.50
14Geogrid base reinforcement (type 2) (250-7002)SY1,187$1.32$8.59$5.24$1.77$2.25$8.80$10.00
15Lime (com or QK)(slurry) (260-7005)TON16.24$340.00$504.00$408.00$350.00$355.60$266.50$345.00
16Lime TRT (existing material)(12") (260-7009)SY1,142$2.25$6.80$22.00$6.00$5.27$20.20$30.00
17Cem TRT(PLNT MX)(CL L)(type E)(GR 4)(8") (276-7187)SY16.04$27.00$127.18$290.70$80.00$153.51$1,373.20$1,000.00
18Prime coat (MC-30) (310-7004)GAL225$5.00$12.09$22.80$12.00$14.43$11.50$15.00
19Asphalt (tier II) (316-7266)GAL338$6.00$47.60$22.80$12.00$10.93$131.00$30.00
20SP mixes SP-D sac-A PG76-22 (344-7064)TON126$130.00$194.29$568.10$119.75$167.82$446.30$600.00
21Struct excavation (special) (400-7005)CY595$91.30$3.43$64.99$85.00$73.53$196.00$120.12
22Cut & restore asphalt paving (400-7008)SY911$100.00$59.71$131.91$55.00$40.87$91.50$117.00
23Cut and restore pavement (flex base) (400-7009)SY245$55.51$131.18$55.00$30.07$30.00$49.18
24Cem stabil BKFL (400-7010)CY368$120.00$68.00$290.66$55.00$46.60$127.40$101.05
25Flowable backfill (401-7001)CY463$217.37$395.74$150.00$165.89$220.50$306.00
26Trench excavation protection (402-7001)LF1,382$3.50$19.68$7.06$30.00$5.00$0.10$5.94
27Temporary special shoring (403-7001)SF6,000$6.80$5.06$40.00$5.00$0.10$97.00
28Riprap (concrete)(CL B)(5 in) (432-7008)CY786$550.00$652.80$547.35$480.00$317.41$784.00$515.00
29Riprap (concrete)(dissipater) (432-7011)CY13$748.00$792.11$2,633.85$798.61$882.00$4,652.92
30Riprap (mow strip)(4 in) (432-7013)CY16$680.00$762.26$480.00$432.28$1,862.00$1,218.79
31Riprap (stone protection)(12 in) (432-7041)CY595$200.00$81.60$443.08$157.86$187.81$196.00$290.00
32Concrete box culvert (9 FT X 5 FT) (462-7027)LF84$939.05$1,653.72$1,593.62$1,150.55$2,058.00$3,235.00
33Concrete box culvert (9 FT X 9 FT) (462-7031)LF752$1,401.60$1,543.62$1,828.79$1,461.91$1,526.90$1,700.00
34Concrete box culvert (10 FT X 9 FT) (462-7037)LF992$2,500.00$1,604.03$1,858.82$1,851.88$1,547.88$2,087.40$2,070.00
35Concrete box culvert (3 FT X 3 FT)(extend) (462-7057)LF84$728.57$640.78$386.82$460.78$1,274.00$970.18
36RC pipe (CL III)(18 in) (464-7003)LF50$68.00$139.85$74.08$82.97$98.00$274.51
37Wingwall (FW - 0) (HW=10 FT) (466-7152)EACH2$30,600$17,429$44,000$30,699$39,200$83,500
38Wingwall (FW - S) (HW=10 FT) (466-7166)EACH2$30,600$17,309$44,000$58,880$49,000$83,500
39Wingwall (SW - 0) (HW=10 FT) (466-7225)EACH4$30,000$15,300$17,309$44,000$36,850$43,120$83,500
40Set (type II) (18 in) (RCP) (3: 1) (C) (467-7305)EACH2$3,400.00$2,850.00$2,000.00$1,742.33$1,176.00$2,970.85
41Removing structure (wingwall) (496-7005)EACH3$4,533.33$3,654.16$3,200.00$2,072.40$3,430.00$3,335.46
42Removing structure (headwall) (496-7006)EACH6$24,000$4,080.00$1,827.08$3,200.00$2,072.41$3,430.00$2,854.70
43Removing structure (pipe) (496-7007)LF558$20.00$36.56$78.05$12.00$19.15$147.00$105.98
44Removing structure (box culvert) (496-7008)LF120$136.00$225.21$22.00$44.52$147.00$108.64
45Remove concrete well & gate (496-7046)EACH1$13,600$7,881.25$2,250.00$8,148.88$9,800.00$7,080.28
46Mobilization (500-7001)LS1$120,362$118,000$722,808$480,000$759,795$500,000$970,000
47Barricades, signs and traffic handling (502-7001)MO28$5,000.00$680.00$649.50$4,200.00$3,647.04$2,200.00$3,662.40
48Portable changeable message sign (503-7001)DAY443$80.00$147.36$78.00$25.00$109.96$48.70$267.09
49Construction exits (install) (type 2) (506-7021)SY546$70.00$62.27$33.60$28.00$13.26$40.90$53.95
50Construction exits (remove) (506-7024)SY546$28.00$29.41$10.20$1.00$1.94$24.10$20.29
51Temporary sediment control fence (install) (506-7039)LF735$5.44$4.80$8.00$7.41$4.50$3.75
52Temporary sediment control fence (remove) (506-7041)LF735$2.72$2.40$1.00$2.33$2.00$1.75
53Biodegradable erosion control logs (install) (12") (506-7044)LF1,450$5.00$7.82$6.90$8.00$4.25$6.70$5.50
54Biodegradable erosion control logs (remove) (506-7046)LF1,450$2.00$1.70$1.50$1.00$1.18$2.00$1.15
55Driveways (concrete) (530-7006)SY187$145.45$109.80$80.00$95.95$88.60$219.33
56Metal W-beam guard fence (timber post) (540-7001)LF445$67.32$36.09$24.44$53.09$29.10$31.01
57Remove metal beam guard fence (542-7001)LF350$13.60$6.51$1.00$9.64$3.00$16.12
58Guardrail end treatment (install) (544-7001)EACH4$5,712.00$4,410.80$2,114.00$4,094.96$3,217.40$3,570.83
59Guardrail end treatment (remove) (544-7003)EACH4$952.00$585.40$1.00$694.36$323.40$537.45
60Install small roadside sign support and assembly TYS80(1)SA(P) (644-7025)EACH2$1,250.00$1,740.80$1,536.00$1,200.00$1,055.44$970.20$1,022.20
61Remove SM RD SN sup&AM (644-7073)EACH2$200.00$1,332.80$1,176.00$1.00$405.94$107.80$98.18
62Install object marker assembly (OM-2Z)(WFLX)GND (658-7058)EACH4$306.00$35.40$822.00$48.71$57.90$213.68
63Install object marker assembly (OM-2Z)(WFLX)GND(BI) (658-7059)EACH4$85.00$272.00$35.22$822.00$48.71$63.70$231.01
64Remove delin & object marker assms (658-7078)EACH2$15.00$612.00$540.00$300.00$27.07$17.70$57.75
65Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH44$0.65$16.32$14.40$18.18$10.83$1.10$13.02
66Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF548$0.65$2.04$1.80$1.10$2.71$3.20$1.50
67Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF78$2.04$1.80$5.00$2.71$3.20$1.50
68Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF601$0.75$2.04$1.80$1.00$2.71$3.20$1.50
69Reflectorized pavement marker type II-A-A (callout) (672-7019)EACH14$100.00$13.60$12.00$250.00$8.12$9.70$10.00
70Eliminating existing PM & markers (4") (677-7001)LF5,687$0.35$1.36$1.20$0.60$1.62$0.60$1.00
71Ditch cleaning and reshaping (foot) (760-7001)LF350$13.60$66.00$12.00$23.47$44.10$85.91
72Bonding course (3007-7001)GAL338$4.00$10.06$22.80$10.00$16.81$2.30$31.57
73Install vertical axial or MX flow pump (5065-7001)EACH1$1,418,426$90,000$1,700,000$950,392$862,400$1,312,000
74Install stainless steel slide gates (5066-7001)EACH1$409,163$90,000$335,000$746,925$686,000$1,350,983
75Install pre-engineered metal canopy (8027-7001)EACH1$61,200$48,000$60,000$568,313$39,200$410,000
TxDOT contract A00197563: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy