TxDOT contract A00198973 bid tabulation
Rehabilitate Bridge, Various (Various Locations in Galveston County to .). Let by Texas DOT on November 5, 2025, Galveston, Houston District. 8 bids received; low bid $2,839,710 by Garret Shields Infrastructure, -19% against the engineer's estimate of $3,514,974.
- Owner
- Texas DOT
- Letting
- 05 NOV 2025
- Pay items
- 36
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Garret Shields Infrastructure | $2,839,710 | Low | -19% |
| 2 | Ragle Construction, Inc. | $2,979,482 | +5.0% | -15% |
| 3 | Structural Integrity Group LLC | $3,609,722 | +27% | +3.0% |
| 4 | Southern Road & Bridge, LLC | $3,977,683 | +40% | +13% |
| 5 | MC2 Civil, LLC | $4,055,540 | +43% | +15% |
| 6 | Built Right Construction of Oklahoma, LLC | $4,102,975 | +44% | +17% |
| 7 | Forde Construction Company, Inc. | $4,614,302 | +62% | +31% |
| 8 | SCR Civil Construction, LLC | $4,723,889 | +66% | +34% |
Engineer's estimate: $3,514,974.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Garret Shields Infrastructure | 2. Ragle Construction, Inc. | 3. Structural Integrity Group LLC | 4. Southern Road & Bridge, LLC | 5. MC2 Civil, LLC | 6. Built Right Construction of Oklahoma, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 365 | $30.00 | $50.00 | $35.00 | $197.00 | $320.00 | $300.00 | $50.00 |
| 2 | Excavation (channel) (110-7002) | CY | 132.50 | $35.00 | $100.00 | $110.00 | $160.00 | $44.00 | $200.00 | $150.00 |
| 3 | Embankment (final)(OC)(type A) (132-7001) | CY | 400.70 | $42.00 | $50.00 | $105.00 | $83.00 | $75.00 | $250.00 | $35.00 |
| 4 | Cem stabil BKFL (400-7010) | CY | 317 | $246.00 | $300.00 | $140.00 | $375.00 | $130.00 | $200.00 | $400.00 |
| 5 | Flowable backfill (401-7001) | CY | 450.10 | $655.00 | $500.00 | $285.00 | $397.00 | $525.00 | $600.00 | $400.00 |
| 6 | Sheet piling (PZ - 40) (407-7004) | SF | 900 | $113.00 | $80.00 | $75.00 | $130.00 | $115.00 | $200.00 | $100.00 |
| 7 | Class A concrete (miscellaneous) (420-7002) | CY | 131.20 | $175.00 | $1,000.00 | $350.00 | $910.00 | $2,800.00 | $550.00 | $1,000.00 |
| 8 | Class C concrete (cap) (420-7022) | CY | 6 | $921.00 | $2,000.00 | $2,120.00 | $3,200.00 | $3,500.00 | $8,000.00 | $2,500.00 |
| 9 | Concrete structure repair (epoxy mortar) (429-7002) | SF | 46 | $140.00 | $200.00 | $150.00 | $155.00 | $405.00 | $450.00 | $300.00 |
| 10 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 4,637 | $236.00 | $200.00 | $115.00 | $298.00 | $385.00 | $100.00 | $285.00 |
| 11 | Riprap (concrete)(4 in) (432-7001) | CY | 9.90 | $475.00 | $800.00 | $725.00 | $1,165.00 | $125.00 | $1,250.00 | $1,000.00 |
| 12 | Riprap (stone common)(grout)(18 in) (432-7039) | CY | 869 | $405.00 | $200.00 | $360.00 | $401.00 | $125.00 | $300.00 | $350.00 |
| 13 | Riprap (stone protection)(12 in) (432-7041) | CY | 197.30 | $190.00 | $250.00 | $275.00 | $330.00 | $125.00 | $450.00 | $300.00 |
| 14 | Riprap (stone protection)(24 in) (432-7045) | CY | 297 | $204.00 | $250.00 | $350.00 | $330.00 | $125.00 | $1,500.00 | $300.00 |
| 15 | Cleaning and sealing existing joints (438-7001) | LF | 47 | $45.00 | $50.00 | $60.00 | $45.00 | $75.00 | $200.00 | $60.00 |
| 16 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 404 | $42.00 | $50.00 | $20.00 | $40.00 | $75.00 | $150.00 | $60.00 |
| 17 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 90 | $45.00 | $50.00 | $25.00 | $45.00 | $75.00 | $200.00 | $65.00 |
| 18 | Rail (type T631) (450-7020) | LF | 120 | $105.00 | $150.00 | $240.00 | $175.00 | $305.00 | $500.00 | $250.00 |
| 19 | Set (type I)(S= 5 FT)(HW= 3 FT)(4:1)(C) (467-7096) | EACH | 10 | $8,480.00 | $8,000.00 | $500.00 | $2,800.00 | $5,600.00 | $1,000.00 | $3,000.00 |
| 20 | Clean existing culverts (480-7001) | EACH | 1 | $350.00 | $5,000.00 | $4,000.00 | $2,000.00 | $9,500.00 | $100,000 | $35,000 |
| 21 | Mobilization (callout) (500-7002) | EACH | 13 | $29,289 | $10,000 | $35,000 | $13,000 | $5,000.00 | $20,000 | $10,000 |
| 22 | Barricades, signs and traffic handling (502-7004) | EACH | 13 | $2,500.00 | $5,000.00 | $37,900 | $7,000.00 | $10,000 | $20,000 | $4,500.00 |
| 23 | Portable changeable message sign (503-7001) | DAY | 600 | $200.00 | $100.00 | $50.00 | $1.00 | $65.00 | $60.00 | $60.00 |
| 24 | TMA (stationary) (505-7001) | DAY | 240 | $400.00 | $300.00 | $240.00 | $1.00 | $250.00 | $300.00 | $270.00 |
| 25 | Excavation (erosion & sediment control, in vehicle) (506-7027) | CY | 60 | $48.00 | $50.00 | $10.00 | $175.00 | $25.00 | $300.00 | $400.00 |
| 26 | Embankment (erosion & sediment control, in vehicle) (506-7028) | CY | 60 | $50.00 | $50.00 | $10.00 | $150.00 | $250.00 | $300.00 | $400.00 |
| 27 | Temporary sediment control fence (install) (506-7039) | LF | 1,280 | $4.00 | $5.00 | $5.00 | $1.00 | $5.00 | $5.00 | $6.00 |
| 28 | Temporary sediment control fence (remove) (506-7041) | LF | 1,280 | $2.00 | $1.00 | $1.00 | $1.00 | $2.00 | $1.00 | $3.00 |
| 29 | Pothole repair(standard)(0"-5" deep) (700-7001) | SY | 1 | $200.00 | $1,000.00 | $1,000.00 | $1,200.00 | $8,500.00 | $1,000.00 | $1,000.00 |
| 30 | Replace timber post W/O concrete FND (770-7006) | EACH | 50 | $69.00 | $100.00 | $105.00 | $150.00 | $425.00 | $500.00 | $150.00 |
| 31 | Concrete rail repair (miscellaneous) (778-7002) | LF | 2 | $300.00 | $1,000.00 | $950.00 | $9,500.00 | $2,500.00 | $2,000.00 | $500.00 |
| 32 | CNC crack repair (discrete)(inject) (780-7002) | LF | 3,189 | $90.00 | $50.00 | $25.00 | $75.00 | $6.00 | $120.00 | $130.00 |
| 33 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 505 | $60.00 | $50.00 | $25.00 | $45.00 | $6.00 | $25.00 | $60.00 |
| 34 | Replacing elastomeric bearing pads (787-7001) | EACH | 14 | $9,000.00 | $5,000.00 | $10,000 | $10,500 | $1,500.00 | $10,000 | $10,000 |
| 35 | Concrete beam repair (788-7001) | EACH | 60 | $3,022.00 | $2,000.00 | $3,500.00 | $500.00 | $2,850.00 | $3,500.00 | $7,500.00 |
| 36 | Inwater piling encapsulation (4048-7002) | LF | 63 | $500.00 | $2,500.00 | $750.00 | $3,100.00 | $5,858.00 | $3,000.00 | $3,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of November 5, 2025. Compiled by Mirage Metrics.