TxDOT contract A00200904 bid tabulation
Bridge Replacement, COUNTY ROAD 2018 (AT HACKBERRY BRANCH to STR# 201760AA0367001). Let by Texas DOT on March 5, 2026, Newton, Beaumont District. 8 bids received; low bid $1,485,796 by Hodges and Son Construction Company, Inc., -17% against the engineer's estimate of $1,795,625.
- Owner
- Texas DOT
- Letting
- 05 MAR 2026
- Pay items
- 54
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Hodges and Son Construction Company, Inc. | $1,485,796 | Low | -17% |
| 2 | R Construction Civil, LLC | $1,744,495 | +17% | -3.0% |
| 3 | Texas Steel Industrial Placing, LLC | $1,775,911 | +20% | -1.0% |
| 4 | Elite Contractors and Equipment LTD | $1,870,206 | +26% | +4.0% |
| 5 | Skyline Bridge LLC | $1,872,638 | +26% | +4.0% |
| 6 | Garret Shields Infrastructure | $2,092,459 | +41% | +17% |
| 7 | Blacksmith Ventures LLC | $2,220,060 | +49% | +24% |
| 8 | Isi Contracting, Inc. | $2,733,806 | +84% | +52% |
Engineer's estimate: $1,795,625.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Hodges and Son Construction Company, Inc. | 2. R Construction Civil, LLC | 3. Texas Steel Industrial Placing, LLC | 4. Elite Contractors and Equipment LTD | 5. Skyline Bridge LLC | 6. Garret Shields Infrastructure |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 13.13 | $5,000.00 | $3,800.00 | $2,150.00 | $2,000.00 | $1,000.00 | $1,808.54 | $1,000.00 |
| 2 | Remove (0"-10") TRT/untrt base & asphalt pavement (105-7050) | SY | 1,302 | $10.00 | $8.00 | $10.00 | $20.00 | $7.00 | $12.00 | $40.00 |
| 3 | Excavation (roadway) (110-7001) | CY | 1,113.40 | $25.00 | $10.00 | $66.00 | $20.00 | $18.00 | $16.37 | $40.00 |
| 4 | Excavation (channel) (110-7002) | CY | 1,439.40 | $30.00 | $12.00 | $37.00 | $20.00 | $23.00 | $19.05 | $40.00 |
| 5 | Embankment (final)(DC)(type A) (132-7002) | CY | 1,948.20 | $50.00 | $15.00 | $32.00 | $30.00 | $25.00 | $34.19 | $40.00 |
| 6 | Furn & place topsoil (4") (160-7002) | SY | 5,770 | $3.50 | $4.00 | $8.00 | $4.00 | $2.00 | $4.00 | $5.00 |
| 7 | Broadcast seed (temporary_warm) (164-7005) | SY | 2,885 | $0.15 | $0.80 | $0.50 | $0.70 | $1.00 | $1.20 | $0.10 |
| 8 | Broadcast seed (temporary_cool) (164-7006) | SY | 2,885 | $0.15 | $0.70 | $0.50 | $0.68 | $1.00 | $1.20 | $0.10 |
| 9 | Hydro mulch seed (permanent_rural_sandy) (164-7017) | SY | 5,770 | $0.75 | $0.55 | $1.00 | $0.54 | $1.00 | $1.14 | $0.10 |
| 10 | Vegetative watering (168-7001) | TGL | 16.44 | $25.00 | $1.00 | $260.00 | $1.00 | $200.00 | $1.00 | $50.00 |
| 11 | Proof rolling (216-7001) | HR | 6 | $100.00 | $20.00 | $645.00 | $100.00 | $200.00 | $120.48 | $200.00 |
| 12 | FL BS (compacted in place)(type A GR 1-2) (10") (247-7090) | SY | 2,878 | $30.00 | $45.00 | $24.00 | $30.00 | $50.00 | $39.35 | $30.00 |
| 13 | Cem stabil BKFL (400-7010) | CY | 259.30 | $130.00 | $200.00 | $69.00 | $200.00 | $180.00 | $287.56 | $200.00 |
| 14 | Temporary special shoring (403-7001) | SF | 320 | $60.00 | $103.00 | $30.00 | $82.00 | $62.82 | $50.00 | |
| 15 | Prestressed concrete pil (16 in SQ) (409-7001) | LF | 1,296 | $250.00 | $145.00 | $294.00 | $260.00 | $225.00 | $308.38 | $250.00 |
| 16 | Class C concrete (abutment) (420-7012) | CY | 96.40 | $1,200.00 | $1,200.00 | $611.00 | $1,100.00 | $2,000.00 | $1,012.08 | $1,200.00 |
| 17 | Class C concrete (rail foundation) (420-7052) | CY | 0.90 | $2,000.00 | $700.00 | $1,000.00 | $2,250.00 | $7,006.58 | $1,000.00 | |
| 18 | Reinforced concrete slab (422-7001) | SF | 3,120 | $27.00 | $30.00 | $26.00 | $25.00 | $26.00 | $25.02 | $30.00 |
| 19 | Reinforced concrete slab (slab beam) (422-7007) | SF | 1,300 | $25.00 | $42.00 | $25.00 | $25.00 | $21.98 | $25.00 | |
| 20 | Prestressed concrete girder (TX28) (425-7001) | LF | 476 | $240.00 | $260.00 | $230.00 | $347.60 | $350.00 | $372.40 | $300.00 |
| 21 | Prestressed concrete slab beam (5SB15) (425-7019) | LF | 247.50 | $305.00 | $270.00 | $372.02 | $330.00 | $402.83 | $350.00 | |
| 22 | Riprap (stone protection)(18 in) (432-7043) | CY | 595 | $195.00 | $190.00 | $218.00 | $175.00 | $195.00 | $167.74 | $200.00 |
| 23 | Riprap (concrete)(CL B)(RR8&RR9) (432-7055) | CY | 100 | $585.00 | $344.00 | $600.00 | $650.00 | $626.36 | $1,000.00 | |
| 24 | Rail (type T223) (450-7008) | LF | 130 | $140.00 | $404.00 | $150.00 | $250.00 | $137.41 | $100.00 | |
| 25 | Rail (type T631LS) (450-7021) | LF | 336 | $67.00 | $67.00 | $167.00 | $75.00 | $72.00 | $78.91 | $100.00 |
| 26 | Type A joint (454-7001) | LF | 104 | $50.00 | $75.00 | $143.00 | $125.00 | $63.00 | $95.69 | $75.00 |
| 27 | RC pipe (CL III)(24 in) (464-7005) | LF | 24 | $85.00 | $166.00 | $130.00 | $120.00 | $212.91 | $120.00 | |
| 28 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 2 | $2,500.00 | $2,000.00 | $1,500.00 | $2,000.00 | $2,515.02 | $2,000.00 | |
| 29 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 3 | $15,000 | $10,000 | $18,800 | $25,000 | $10,000 | $15,494 | $80,000 |
| 30 | Removing structure (pipe) (496-7037) | EACH | 1 | $200.00 | $500.00 | $2,200.00 | $3,000.00 | $1,000.00 | $1,265.04 | $1,000.00 |
| 31 | Mobilization (500-7001) | LS | 1 | $200,000 | $125,000 | $70,000 | $177,575 | $170,000 | $150,000 | $150,000 |
| 32 | Barricades, signs and traffic handling (502-7001) | MO | 13 | $5,000.00 | $2,000.00 | $1,320.00 | $1,500.00 | $3,000.00 | $1,930.00 | $5,000.00 |
| 33 | Rock filter dams (install) (type 1) (506-7001) | LF | 60 | $1.00 | $70.00 | $40.00 | $50.00 | $50.60 | $20.00 | |
| 34 | Rock filter dams (remove) (506-7011) | LF | 60 | $1.00 | $10.00 | $10.00 | $10.00 | $12.05 | $1.00 | |
| 35 | Construction exits (install) (type 1) (506-7020) | SY | 234 | $37.00 | $1.00 | $30.00 | $40.00 | $30.00 | $1.00 | $20.00 |
| 36 | Construction exits (remove) (506-7024) | SY | 234 | $15.00 | $1.00 | $5.00 | $10.00 | $8.00 | $1.00 | $5.00 |
| 37 | Construction perimeter fence (506-7034) | LF | 510 | $8.00 | $1.00 | $6.00 | $5.00 | $8.00 | $7.00 | $5.00 |
| 38 | Temporary sediment control fence (install) (506-7039) | LF | 2,403 | $8.00 | $1.00 | $5.00 | $4.00 | $4.00 | $3.88 | $5.00 |
| 39 | Temporary sediment control fence (remove) (506-7041) | LF | 2,403 | $6.00 | $1.00 | $1.00 | $2.00 | $1.50 | $1.35 | $1.00 |
| 40 | Portable concrete traffic barrier (furnish and install)(low prof)(type 1) (512-7009) | LF | 80 | $40.00 | $30.00 | $70.00 | $80.00 | $119.20 | $80.00 | |
| 41 | Portable concrete traffic barrier (furnish and install)(low prof)(type 2) (512-7010) | LF | 160 | $40.00 | $30.00 | $20.00 | $80.00 | $99.36 | $80.00 | |
| 42 | Portable concrete traffic barrier (move)(low prof)(type 1) (512-7033) | LF | 60 | $30.00 | $11.00 | $20.00 | $50.00 | $13.95 | $40.00 | |
| 43 | Portable concrete traffic barrier (move)(low prof)(type 2) (512-7034) | LF | 120 | $30.00 | $11.00 | $20.00 | $50.00 | $13.95 | $40.00 | |
| 44 | Portable concrete traffic barrier (remove)(low prof)(type 1) (512-7057) | LF | 80 | $30.00 | $5.00 | $20.00 | $80.00 | $36.54 | $40.00 | |
| 45 | Portable concrete traffic barrier (remove)(low prof)(type 2) (512-7058) | LF | 160 | $30.00 | $5.00 | $20.00 | $80.00 | $36.54 | $40.00 | |
| 46 | Driveways (base) (530-7015) | SY | 43 | $45.00 | $134.00 | $70.00 | $140.00 | $76.17 | $40.00 | |
| 47 | Metal W-beam guard fence (timber post) (540-7001) | LF | 250 | $25.00 | $30.00 | $27.00 | $27.00 | $35.00 | $30.12 | $40.00 |
| 48 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 3 | $1,600.00 | $1,700.00 | $1,850.00 | $2,200.00 | $1,897.56 | $1,500.00 | |
| 49 | Downstream anchor terminal section (540-7015) | EACH | 6 | $1,600.00 | $1,500.00 | $1,400.00 | $1,565.00 | $1,500.00 | $1,566.24 | $2,000.00 |
| 50 | Remove metal beam guard fence (542-7001) | LF | 40 | $2.00 | $4.00 | $5.00 | $10.00 | $31.10 | $5.00 | |
| 51 | Guardrail end treatment (install) (544-7001) | EACH | 5 | $3,000.00 | $3,200.00 | $3,400.00 | $2,975.00 | $3,500.00 | $3,795.12 | $3,500.00 |
| 52 | Crash cushion attenuator (install)(L)(N)(TL2) (545-7005) | EACH | 1 | $29,000 | $51,700 | $30,000 | $35,000 | $34,186 | $20,000 | |
| 53 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $50.00 | $225.00 | $300.00 | $150.00 | $198.79 | $500.00 | |
| 54 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 24 | $40.00 | $25.00 | $30.00 | $30.00 | $50.00 | $30.12 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.