TxDOT contract A00201583 bid tabulation
Hazard Elimination & Safety, FM 167 (US 377 to FM 51). Let by Texas DOT on July 2, 2025, Hood, Fort Worth District. 4 bids received; low bid $14,553,382 by Jay Mills Contracting, Incorporated, +0.2% against the engineer's estimate of $14,523,094.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 150
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Jay Mills Contracting, Incorporated | $14,553,382 | Low | 0.0% |
| 2 | Knife River Corporation - South | $14,632,771 | +1.0% | +1.0% |
| 3 | Grey Sky Construction LLC | $16,507,606 | +13% | +14% |
| 4 | Indus Road & Bridge, Inc. | $19,235,370 | +32% | +32% |
Engineer's estimate: $14,523,094.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Jay Mills Contracting, Incorporated | 2. Knife River Corporation - South | 3. Grey Sky Construction LLC | 4. Indus Road & Bridge, Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 208 | $725.00 | $1,500.00 | $1,000.00 | $7,000.00 | $9,203.69 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 5 | $500.00 | $600.00 | $740.00 | $2,000.00 | $600.00 |
| 3 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 3 | $3,000.00 | $750.00 | $1,477.00 | $3,500.00 | $1,500.00 |
| 4 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 2 | $3,000.00 | $1,500.00 | $1,931.00 | $5,000.00 | $2,600.00 |
| 5 | Removing concrete (mowstrip) (104-7005) | LF | 421 | $15.00 | $22.00 | $25.00 | $50.00 | $22.00 |
| 6 | Removing concrete (riprap) (104-7007) | CY | 5 | $80.00 | $100.00 | $170.00 | $200.00 | $120.00 |
| 7 | Removing concrete (driveways) (104-7011) | SY | 2,128 | $25.00 | $27.00 | $51.00 | $20.00 | $30.00 |
| 8 | Excavation (roadway) (110-7001) | CY | 11,190 | $20.00 | $25.00 | $25.00 | $20.00 | $40.00 |
| 9 | Subgr widen (DC) (112-7004) | SY | 2,114 | $50.00 | $9.00 | $20.00 | $30.00 | $22.00 |
| 10 | Embankment (final)(DC)(type B) (132-7004) | CY | 6,941 | $50.00 | $21.00 | $25.00 | $30.00 | $20.00 |
| 11 | Backfill (type A) (134-7001) | STA | 202.60 | $400.00 | $550.00 | $248.00 | $250.00 | $395.00 |
| 12 | Blading (150-7002) | HR | 40 | $50.00 | $250.00 | $148.00 | $150.00 | $200.00 |
| 13 | Compost manuf topsoil (4") (161-7002) | SY | 35,649 | $6.00 | $2.00 | $1.30 | $4.00 | $2.50 |
| 14 | Drill seed (permanent_rural_clay) (164-7042) | ACRE | 7.38 | $850.00 | $2,150.00 | $875.00 | $1,000.00 | $740.00 |
| 15 | Drill seed (temporary_warm) (164-7045) | ACRE | 7.38 | $850.00 | $1,850.00 | $705.00 | $1,000.00 | $740.00 |
| 16 | Drill seed (temporary_cool) (164-7046) | ACRE | 0.70 | $850.00 | $5,000.00 | $1,265.00 | $6,000.00 | $740.00 |
| 17 | Straw/hay mulch seed(temporary_cool) (164-7062) | ACRE | 0.70 | $1,500.00 | $8,000.00 | $5,440.00 | $6,000.00 | $1,200.00 |
| 18 | Vegetative watering (168-7001) | TGL | 2,620 | $30.00 | $35.00 | $1.00 | $20.00 | $1.00 |
| 19 | Proof rolling (216-7001) | HR | 48 | $130.00 | $200.00 | $93.00 | $150.00 | $160.00 |
| 20 | FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176) | CY | 5,179 | $60.00 | $80.00 | $100.00 | $70.00 | $90.00 |
| 21 | FL BS (roadway del)(type A GR 1-2)(final pos) (247-7259) | CY | 333 | $50.00 | $60.00 | $100.00 | $70.00 | $100.00 |
| 22 | Rework BS metal (type C)(9")(density control) (251-7082) | SY | 2,036 | $8.00 | $15.00 | $20.00 | $6.00 | $28.00 |
| 23 | Cement (275-7001) | TON | 401 | $250.00 | $280.00 | $240.00 | $350.00 | $341.00 |
| 24 | Cement TRT (existing material)(6") (275-7002) | SY | 37,483 | $4.25 | $6.00 | $4.00 | $6.00 | $5.00 |
| 25 | Asphalt (RC-250) (316-7016) | GAL | 15,215 | $8.50 | $4.50 | $8.50 | $5.00 | $9.00 |
| 26 | Aggregate (type-B, GR-5)(sac-B) (316-7175) | CY | 428 | $280.00 | $135.00 | $250.00 | $350.00 | $615.00 |
| 27 | D-GR HMA type-B PG64-22 (341-7001) | TON | 7,326 | $175.00 | $135.00 | $143.00 | $165.00 | $142.00 |
| 28 | D-GR HMA type D PG64-22 (341-7043) | TON | 4,394 | $175.00 | $135.00 | $143.00 | $185.00 | $150.00 |
| 29 | D-GR HMA type D PG64-22 (level-UP) (341-7046) | TON | 6,038 | $200.00 | $190.00 | $200.00 | $185.00 | $150.00 |
| 30 | Tack coat (341-7082) | GAL | 15,140 | $5.00 | $0.01 | $0.01 | $6.00 | $6.50 |
| 31 | SP mixes SP-C sac-A PG70-28 (344-7024) | TON | 9,367 | $200.00 | $185.00 | $194.00 | $185.00 | $200.00 |
| 32 | Flexible pavement structure repair(10") (351-7009) | SY | 800 | $95.00 | $120.00 | $123.00 | $100.00 | $600.00 |
| 33 | Plane & text asphalt concrete pavement(2" to 4") (354-7010) | SY | 44,051 | $4.75 | $3.75 | $5.80 | $6.00 | $5.00 |
| 34 | Planing asphalt concrete pavement(11") (354-7060) | SY | 732 | $8.00 | $24.00 | $25.00 | $30.00 | $16.00 |
| 35 | Cut & restoring pavement (400-7006) | SY | 276 | $70.00 | $190.00 | $350.00 | $200.00 | $230.00 |
| 36 | Cem stabil BKFL (400-7010) | CY | 136 | $250.00 | $565.00 | $310.00 | $350.00 | $260.00 |
| 37 | Temporary special shoring (403-7001) | SF | 3,596 | $35.00 | $34.00 | $45.00 | $85.00 | $53.00 |
| 38 | Drilled shaft (24 in) (416-7004) | LF | 600 | $350.00 | $305.00 | $300.00 | $250.00 | $185.00 |
| 39 | Class C concrete (abutment)(HPC) (420-7013) | CY | 30 | $2,000.00 | $2,800.00 | $2,500.00 | $1,500.00 | $1,300.00 |
| 40 | Class C concrete (cap)(HPC) (420-7023) | CY | 24.10 | $2,000.00 | $2,250.00 | $2,500.00 | $1,800.00 | $1,900.00 |
| 41 | Class C concrete (column)(HPC) (420-7039) | CY | 18 | $2,000.00 | $2,250.00 | $1,700.00 | $2,000.00 | $1,900.00 |
| 42 | Reinforced concrete slab (slab beam)(HPC) (422-7008) | SF | 4,846 | $25.00 | $42.25 | $35.00 | $25.00 | $25.00 |
| 43 | Approach slab (422-7013) | CY | 76 | $1,000.00 | $1,350.00 | $850.00 | $1,000.00 | $850.00 |
| 44 | Prestressed concrete slab beam (4SB12) (425-7016) | LF | 1,083.50 | $200.00 | $305.00 | $250.00 | $250.00 | $250.00 |
| 45 | Prestressed concrete slab beam (5SB12) (425-7017) | LF | 98.50 | $250.00 | $345.00 | $250.00 | $250.00 | $375.00 |
| 46 | Penetrating concrete surface treatment (428-7001) | SY | 414 | $75.00 | $17.00 | $35.00 | $25.00 | $35.00 |
| 47 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 9 | $500.00 | $450.00 | $1,000.00 | $1,000.00 | $320.00 |
| 48 | Riprap (concrete)(4 in) (432-7001) | CY | 6.20 | $700.00 | $700.00 | $1,022.00 | $550.00 | $550.00 |
| 49 | Riprap (mow strip)(4 in) (432-7013) | CY | 220 | $600.00 | $725.00 | $559.00 | $550.00 | $700.00 |
| 50 | Riprap (stone protection)(12 in) (432-7041) | CY | 100 | $200.00 | $135.00 | $170.00 | $150.00 | $350.00 |
| 51 | Riprap (stone protection)(24 in) (432-7045) | CY | 1,775 | $190.00 | $280.00 | $186.00 | $180.00 | $220.00 |
| 52 | Cleaning and sealing existing joints (438-7001) | LF | 84 | $80.00 | $95.00 | $110.00 | $100.00 | $35.00 |
| 53 | Rail (type T223)(HPC) (450-7009) | LF | 224 | $150.00 | $295.00 | $160.00 | $250.00 | $140.00 |
| 54 | Armor joint (sealed) (454-7003) | LF | 88 | $150.00 | $235.00 | $190.00 | $1,000.00 | $270.00 |
| 55 | Concrete box culvert (5 FT X 3 FT) (462-7007) | LF | 202 | $525.00 | $485.00 | $368.00 | $720.00 | $420.00 |
| 56 | Concrete box culvert (6 FT X 4 FT) (462-7012) | LF | 104 | $800.00 | $650.00 | $1,035.00 | $1,000.00 | $620.00 |
| 57 | Concrete box culvert (8 FT X 4 FT) (462-7021) | LF | 58 | $945.00 | $1,050.00 | $780.00 | $1,350.00 | $800.00 |
| 58 | Concrete box culvert (8 FT X 8 FT) (462-7025) | LF | 140 | $1,250.00 | $1,250.00 | $955.00 | $1,500.00 | $950.00 |
| 59 | Concrete box culvert (10 FT X 5 FT) (462-7033) | LF | 46 | $1,600.00 | $1,550.00 | $1,144.00 | $2,000.00 | $1,250.00 |
| 60 | Concrete box culvert (5 FT X 3 FT)(extend) (462-7062) | LF | 70 | $525.00 | $800.00 | $725.00 | $1,000.00 | $1,050.00 |
| 61 | Concrete box culvert (8 FT X 4 FT)(extend) (462-7076) | LF | 49 | $945.00 | $1,450.00 | $851.00 | $1,500.00 | $1,250.00 |
| 62 | Concrete box culvert (8 FT X 8 FT)(extend) (462-7080) | LF | 78 | $1,250.00 | $1,800.00 | $885.00 | $1,650.00 | $1,700.00 |
| 63 | Concrete box culvert (10 FT X 5 FT)(extend) (462-7088) | LF | 19 | $1,600.00 | $1,750.00 | $1,155.00 | $2,000.00 | $1,890.00 |
| 64 | RC pipe (CL III)(18 in) (464-7003) | LF | 1,406 | $120.00 | $82.00 | $73.85 | $85.00 | $68.00 |
| 65 | RC pipe (CL III)(24 in) (464-7005) | LF | 552 | $130.00 | $105.00 | $170.50 | $95.00 | $185.00 |
| 66 | RC pipe (CL III)(30 in) (464-7007) | LF | 118 | $160.00 | $130.00 | $227.00 | $105.00 | $220.00 |
| 67 | RC pipe (CL IV)(24 in) (464-7021) | LF | 248 | $130.00 | $120.00 | $205.00 | $110.00 | $215.00 |
| 68 | Headwall (CH - PW - 0) (diameter= 30 in) (466-7103) | EACH | 2 | $13,000 | $9,000.00 | $10,245 | $8,500.00 | $11,000 |
| 69 | Wingwall (FW - 0) (HW=5 FT) (466-7147) | EACH | 1 | $20,500 | $10,000 | $10,365 | $12,500 | $20,000 |
| 70 | Wingwall (PW - 2) (HW=4 FT) (466-7188) | EACH | 4 | $14,000 | $10,000 | $9,570.00 | $15,000 | $30,000 |
| 71 | Wingwall (PW - 2) (HW=5 FT) (466-7189) | EACH | 3 | $18,000 | $17,000 | $11,240 | $16,500 | $25,000 |
| 72 | Wingwall (PW - 2) (HW=6 FT) (466-7190) | EACH | 2 | $22,500 | $18,000 | $12,950 | $25,000 | $35,000 |
| 73 | Wingwall (PW - 2) (HW=9 FT) (466-7193) | EACH | 2 | $51,000 | $18,000 | $25,305 | $45,000 | $42,000 |
| 74 | Set (type I) (36 in) (3: 1) (C) (467-7017) | EACH | 4 | $7,500.00 | $10,000 | $14,205 | $3,500.00 | $22,000 |
| 75 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 80 | $1,900.00 | $1,500.00 | $1,080.00 | $1,000.00 | $3,000.00 |
| 76 | Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325) | EACH | 2 | $2,400.00 | $1,350.00 | $2,273.00 | $2,000.00 | $2,900.00 |
| 77 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 6 | $3,250.00 | $1,500.00 | $2,500.00 | $2,000.00 | $3,500.00 |
| 78 | Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328) | EACH | 39 | $2,200.00 | $1,650.00 | $2,841.00 | $2,000.00 | $3,600.00 |
| 79 | Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348) | EACH | 4 | $3,800.00 | $2,550.00 | $4,091.00 | $3,000.00 | $4,300.00 |
| 80 | Set (type I)(S= 5 FT)(HW= 4 FT)(6:1) (P) (467-7479) | EACH | 4 | $12,000 | $12,750 | $20,455 | $12,000 | $27,000 |
| 81 | Clean existing culverts (480-7001) | EACH | 11 | $3,000.00 | $3,700.00 | $2,275.00 | $2,500.00 | $3,000.00 |
| 82 | Removing structure (set) (496-7004) | EACH | 43 | $894.62 | $250.00 | $740.00 | $500.00 | $1,000.00 |
| 83 | Removing structure (wingwall) (496-7005) | EACH | 8 | $2,137.00 | $1,150.00 | $1,175.00 | $2,500.00 | $10,000 |
| 84 | Removing structure (pipe) (496-7007) | LF | 392 | $50.83 | $25.00 | $45.45 | $50.00 | $50.00 |
| 85 | Removing structure (bridge 0 - 99 FT length) (496-7009) | EACH | 1 | $70,000 | $90,000 | $70,000 | $50,000 | $130,000 |
| 86 | Remove STR (driveway culvert) (496-7038) | EACH | 49 | $100.00 | $250.00 | $1,705.00 | $500.00 | $45.00 |
| 87 | Removing rock riprap (496-7040) | LF | 10 | $113.00 | $85.00 | $113.00 | $100.00 | $75.00 |
| 88 | Removing structure (masonary) (496-7041) | LF | 126 | $20.00 | $25.00 | $42.00 | $100.00 | $78.00 |
| 89 | Removing structure (wood STR) (496-7042) | LF | 30 | $30.00 | $15.00 | $75.00 | $100.00 | $45.00 |
| 90 | Mobilization (500-7001) | LS | 1 | $1,200,000 | $1,150,000 | $1,463,000 | $1,500,000 | $1,900,000 |
| 91 | Barricades, signs and traffic handling (502-7001) | MO | 21 | $9,500.00 | $30,000 | $10,000 | $15,000 | $35,000 |
| 92 | Portable changeable message sign (503-7001) | DAY | 42 | $95.00 | $125.00 | $150.00 | $150.00 | $150.00 |
| 93 | Portable changeable message sign (503-7002) | EACH | 4 | $9,000.00 | $20,000 | $20,000 | $20,000 | $40,000 |
| 94 | TMA (stationary) (505-7001) | DAY | 120 | $280.00 | $335.00 | $300.00 | $250.00 | $400.00 |
| 95 | Rock filter dams (remove) (506-7011) | LF | 140 | $15.00 | $56.00 | $63.00 | $30.00 | $70.00 |
| 96 | Construction exits (install) (type 2) (506-7021) | SY | 100 | $40.00 | $33.00 | $180.00 | $50.00 | $170.00 |
| 97 | Earthwork (erosion & sediment control, in vehicle) (506-7029) | CY | 100 | $60.00 | $60.00 | $95.00 | $50.00 | $100.00 |
| 98 | Temporary sediment control fence (install) (506-7039) | LF | 6,287 | $4.50 | $3.75 | $8.65 | $4.00 | $7.00 |
| 99 | Temporary sediment control fence (remove) (506-7041) | LF | 6,287 | $1.00 | $2.25 | $1.80 | $2.00 | $2.00 |
| 100 | Rock filter dams (install) (type 2) 6:1 (506-7048) | LF | 140 | $70.00 | $74.00 | $171.00 | $30.00 | $170.00 |
| 101 | Constructing detours (508-7001) | SY | 7,500 | $70.00 | $50.00 | $75.00 | $35.00 | $125.00 |
| 102 | One-way traffic control (port traffic signal) (510-7003) | MO | 5 | $5,000.00 | $6,500.00 | $7,385.00 | $9,500.00 | $4,400.00 |
| 103 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 1,800 | $60.00 | $88.00 | $102.00 | $100.00 | $120.00 |
| 104 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 5,000 | $10.00 | $18.00 | $16.00 | $20.00 | $12.00 |
| 105 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 1,800 | $15.00 | $23.00 | $23.00 | $20.00 | $14.00 |
| 106 | Intersections (ACP) (530-7002) | SY | 974 | $130.00 | $185.00 | $171.00 | $55.00 | $175.00 |
| 107 | Driveways (concrete) (530-7006) | SY | 1,193 | $100.00 | $155.00 | $126.00 | $85.00 | $185.00 |
| 108 | Driveways (ACP) (530-7010) | SY | 941 | $55.00 | $56.00 | $60.00 | $45.00 | $140.00 |
| 109 | Driveways (surface treat) (530-7016) | SY | 3,942 | $40.00 | $50.00 | $30.00 | $45.00 | $36.00 |
| 110 | Turnouts (ACP) (530-7018) | SY | 592 | $75.00 | $95.00 | $120.00 | $55.00 | $165.00 |
| 111 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 27,412 | $0.25 | $0.26 | $0.35 | $0.30 | $0.20 |
| 112 | Mill rumble strips (asphalt) (centerline) (533-7002) | LF | 14,779 | $0.28 | $0.26 | $0.35 | $0.30 | $0.25 |
| 113 | Metal W-beam guard fence (timber post) (540-7001) | LF | 1,780.50 | $30.00 | $28.00 | $28.40 | $30.00 | $34.00 |
| 114 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 8 | $3,232.00 | $2,550.00 | $3,357.00 | $1,850.00 | $2,400.00 |
| 115 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 250 | $40.00 | $97.00 | $99.00 | $110.00 | $130.00 |
| 116 | Remove metal beam guard fence (542-7001) | LF | 1,105 | $4.50 | $3.50 | $3.40 | $3.00 | $9.00 |
| 117 | Remove terminal anchor section (542-7002) | EACH | 2 | $500.00 | $278.00 | $284.00 | $500.00 | $600.00 |
| 118 | Guardrail end treatment (install) (544-7001) | EACH | 20 | $3,500.00 | $3,650.00 | $3,700.00 | $3,850.00 | $4,300.00 |
| 119 | Guardrail end treatment (remove) (544-7003) | EACH | 6 | $500.00 | $280.00 | $285.00 | $1,500.00 | $2,100.00 |
| 120 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 50 | $2,000.00 | $2,700.00 | $2,102.00 | $4,500.00 | $3,800.00 |
| 121 | Crash cushion attenuator (remove) (545-7004) | EACH | 4 | $1,500.00 | $3,450.00 | $995.00 | $2,500.00 | $2,000.00 |
| 122 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 4 | $9,500.00 | $15,500 | $9,640.00 | $30,000 | $12,000 |
| 123 | Gate (install)(6'X16') (550-7013) | EACH | 2 | $3,000.00 | $2,500.00 | $2,275.00 | $20,000 | $1,000.00 |
| 124 | Wire fence (type C) (552-7003) | LF | 50 | $50.00 | $50.00 | $52.25 | $20.00 | $22.00 |
| 125 | Wire fence (special) (552-7005) | LF | 50 | $75.00 | $60.00 | $53.40 | $100.00 | $95.00 |
| 126 | Mailbox install-M (TWG-post) type 1 (560-7001) | EACH | 3 | $350.00 | $675.00 | $680.00 | $1,500.00 | $700.00 |
| 127 | Mailbox install-S (TWG-post) type 2 (560-7002) | EACH | 36 | $340.00 | $325.00 | $312.00 | $1,500.00 | $350.00 |
| 128 | Mailbox install-D (TWG-post) type 2 (560-7003) | EACH | 2 | $370.00 | $325.00 | $324.00 | $1,500.00 | $550.00 |
| 129 | Mailbox install-M (TWW-post) type 4 (560-7010) | EACH | 5 | $370.00 | $900.00 | $910.00 | $1,500.00 | $800.00 |
| 130 | Relocate existing mailbox (560-7012) | EACH | 46 | $500.00 | $625.00 | $615.00 | $1,100.00 | $400.00 |
| 131 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 33 | $850.00 | $750.00 | $761.00 | $1,500.00 | $750.00 |
| 132 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 20 | $1,000.00 | $925.00 | $926.00 | $1,500.00 | $900.00 |
| 133 | Install small roadside sign support and assembly type 10BWG(1)SA(T-exal) (644-7006) | EACH | 2 | $710.00 | $1,100.00 | $1,091.00 | $1,500.00 | $1,000.00 |
| 134 | Remove SM RD SN sup&AM (644-7073) | EACH | 4 | $130.00 | $170.00 | $171.00 | $500.00 | $170.00 |
| 135 | Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013) | EACH | 48 | $25.50 | $17.00 | $17.00 | $100.00 | $23.00 |
| 136 | Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019) | EACH | 21 | $35.00 | $32.00 | $32.00 | $100.00 | $35.00 |
| 137 | Install object marker assembly (OM-2X)(WC)GND (658-7055) | EACH | 17 | $70.00 | $73.00 | $75.00 | $100.00 | $95.00 |
| 138 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 82,622 | $0.80 | $0.01 | $0.91 | $1.00 | $1.30 |
| 139 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 39,686 | $0.80 | $0.01 | $0.91 | $1.00 | $1.30 |
| 140 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 4,129 | $1.50 | $1.20 | $1.14 | $5.00 | $1.00 |
| 141 | Work zone pavement marking SHT terminal (tab)type Y (662-7113) | EACH | 1,986 | $1.50 | $1.20 | $1.14 | $5.00 | $1.00 |
| 142 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 1,986 | $1.50 | $1.70 | $1.14 | $5.00 | $1.20 |
| 143 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 650 | $2.00 | $15.00 | $7.39 | $20.00 | $12.00 |
| 144 | Reflectorized pavement marking type I (W)(RR crossing)(100MIL) (666-7081) | EACH | 2 | $1,017.00 | $1,300.00 | $852.30 | $1,500.00 | $900.00 |
| 145 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 41,311 | $1.35 | $0.85 | $1.14 | $1.00 | $0.90 |
| 146 | Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420) | LF | 665 | $1.50 | $0.95 | $2.27 | $1.00 | $1.30 |
| 147 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 39,686 | $1.35 | $0.85 | $1.14 | $1.00 | $0.70 |
| 148 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 531 | $7.90 | $9.50 | $6.82 | $6.00 | $7.00 |
| 149 | Full - width mowing (730-7019) | CYC | 5 | $3,500.00 | $3,200.00 | $4,545.00 | $5,000.00 | $3,800.00 |
| 150 | Litter removal (734-7002) | CYC | 15 | $2,500.00 | $2,700.00 | $2,000.00 | $5,000.00 | $2,400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.