TxDOT contract A00201583 bid tabulation

Hazard Elimination & Safety, FM 167 (US 377 to FM 51). Let by Texas DOT on July 2, 2025, Hood, Fort Worth District. 4 bids received; low bid $14,553,382 by Jay Mills Contracting, Incorporated, +0.2% against the engineer's estimate of $14,523,094.

Owner
Texas DOT
Letting
02 JUL 2025
Pay items
150
Data through
19 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jay Mills Contracting, Incorporated$14,553,382Low0.0%
2Knife River Corporation - South$14,632,771+1.0%+1.0%
3Grey Sky Construction LLC$16,507,606+13%+14%
4Indus Road & Bridge, Inc.$19,235,370+32%+32%
TxDOT contract A00201583: bids by rank

Engineer's estimate: $14,523,094.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Jay Mills Contracting, Incorporated2. Knife River Corporation - South3. Grey Sky Construction LLC4. Indus Road & Bridge, Inc.
1Preparing row (100-7002)STA208$725.00$1,500.00$1,000.00$7,000.00$9,203.69
2Preparation row (tree remove) (0"-12" diameter) (100-7003)EACH5$500.00$600.00$740.00$2,000.00$600.00
3Preparation row (tree remove) (12"-24" diameter) (100-7004)EACH3$3,000.00$750.00$1,477.00$3,500.00$1,500.00
4Preparation row (tree remove) (24"-36" diameter) (100-7005)EACH2$3,000.00$1,500.00$1,931.00$5,000.00$2,600.00
5Removing concrete (mowstrip) (104-7005)LF421$15.00$22.00$25.00$50.00$22.00
6Removing concrete (riprap) (104-7007)CY5$80.00$100.00$170.00$200.00$120.00
7Removing concrete (driveways) (104-7011)SY2,128$25.00$27.00$51.00$20.00$30.00
8Excavation (roadway) (110-7001)CY11,190$20.00$25.00$25.00$20.00$40.00
9Subgr widen (DC) (112-7004)SY2,114$50.00$9.00$20.00$30.00$22.00
10Embankment (final)(DC)(type B) (132-7004)CY6,941$50.00$21.00$25.00$30.00$20.00
11Backfill (type A) (134-7001)STA202.60$400.00$550.00$248.00$250.00$395.00
12Blading (150-7002)HR40$50.00$250.00$148.00$150.00$200.00
13Compost manuf topsoil (4") (161-7002)SY35,649$6.00$2.00$1.30$4.00$2.50
14Drill seed (permanent_rural_clay) (164-7042)ACRE7.38$850.00$2,150.00$875.00$1,000.00$740.00
15Drill seed (temporary_warm) (164-7045)ACRE7.38$850.00$1,850.00$705.00$1,000.00$740.00
16Drill seed (temporary_cool) (164-7046)ACRE0.70$850.00$5,000.00$1,265.00$6,000.00$740.00
17Straw/hay mulch seed(temporary_cool) (164-7062)ACRE0.70$1,500.00$8,000.00$5,440.00$6,000.00$1,200.00
18Vegetative watering (168-7001)TGL2,620$30.00$35.00$1.00$20.00$1.00
19Proof rolling (216-7001)HR48$130.00$200.00$93.00$150.00$160.00
20FL BS (compacted in place)(tya GR1-2)(final pos) (247-7176)CY5,179$60.00$80.00$100.00$70.00$90.00
21FL BS (roadway del)(type A GR 1-2)(final pos) (247-7259)CY333$50.00$60.00$100.00$70.00$100.00
22Rework BS metal (type C)(9")(density control) (251-7082)SY2,036$8.00$15.00$20.00$6.00$28.00
23Cement (275-7001)TON401$250.00$280.00$240.00$350.00$341.00
24Cement TRT (existing material)(6") (275-7002)SY37,483$4.25$6.00$4.00$6.00$5.00
25Asphalt (RC-250) (316-7016)GAL15,215$8.50$4.50$8.50$5.00$9.00
26Aggregate (type-B, GR-5)(sac-B) (316-7175)CY428$280.00$135.00$250.00$350.00$615.00
27D-GR HMA type-B PG64-22 (341-7001)TON7,326$175.00$135.00$143.00$165.00$142.00
28D-GR HMA type D PG64-22 (341-7043)TON4,394$175.00$135.00$143.00$185.00$150.00
29D-GR HMA type D PG64-22 (level-UP) (341-7046)TON6,038$200.00$190.00$200.00$185.00$150.00
30Tack coat (341-7082)GAL15,140$5.00$0.01$0.01$6.00$6.50
31SP mixes SP-C sac-A PG70-28 (344-7024)TON9,367$200.00$185.00$194.00$185.00$200.00
32Flexible pavement structure repair(10") (351-7009)SY800$95.00$120.00$123.00$100.00$600.00
33Plane & text asphalt concrete pavement(2" to 4") (354-7010)SY44,051$4.75$3.75$5.80$6.00$5.00
34Planing asphalt concrete pavement(11") (354-7060)SY732$8.00$24.00$25.00$30.00$16.00
35Cut & restoring pavement (400-7006)SY276$70.00$190.00$350.00$200.00$230.00
36Cem stabil BKFL (400-7010)CY136$250.00$565.00$310.00$350.00$260.00
37Temporary special shoring (403-7001)SF3,596$35.00$34.00$45.00$85.00$53.00
38Drilled shaft (24 in) (416-7004)LF600$350.00$305.00$300.00$250.00$185.00
39Class C concrete (abutment)(HPC) (420-7013)CY30$2,000.00$2,800.00$2,500.00$1,500.00$1,300.00
40Class C concrete (cap)(HPC) (420-7023)CY24.10$2,000.00$2,250.00$2,500.00$1,800.00$1,900.00
41Class C concrete (column)(HPC) (420-7039)CY18$2,000.00$2,250.00$1,700.00$2,000.00$1,900.00
42Reinforced concrete slab (slab beam)(HPC) (422-7008)SF4,846$25.00$42.25$35.00$25.00$25.00
43Approach slab (422-7013)CY76$1,000.00$1,350.00$850.00$1,000.00$850.00
44Prestressed concrete slab beam (4SB12) (425-7016)LF1,083.50$200.00$305.00$250.00$250.00$250.00
45Prestressed concrete slab beam (5SB12) (425-7017)LF98.50$250.00$345.00$250.00$250.00$375.00
46Penetrating concrete surface treatment (428-7001)SY414$75.00$17.00$35.00$25.00$35.00
47Concrete structure repair(deck rep(part depth)) (429-7003)SF9$500.00$450.00$1,000.00$1,000.00$320.00
48Riprap (concrete)(4 in) (432-7001)CY6.20$700.00$700.00$1,022.00$550.00$550.00
49Riprap (mow strip)(4 in) (432-7013)CY220$600.00$725.00$559.00$550.00$700.00
50Riprap (stone protection)(12 in) (432-7041)CY100$200.00$135.00$170.00$150.00$350.00
51Riprap (stone protection)(24 in) (432-7045)CY1,775$190.00$280.00$186.00$180.00$220.00
52Cleaning and sealing existing joints (438-7001)LF84$80.00$95.00$110.00$100.00$35.00
53Rail (type T223)(HPC) (450-7009)LF224$150.00$295.00$160.00$250.00$140.00
54Armor joint (sealed) (454-7003)LF88$150.00$235.00$190.00$1,000.00$270.00
55Concrete box culvert (5 FT X 3 FT) (462-7007)LF202$525.00$485.00$368.00$720.00$420.00
56Concrete box culvert (6 FT X 4 FT) (462-7012)LF104$800.00$650.00$1,035.00$1,000.00$620.00
57Concrete box culvert (8 FT X 4 FT) (462-7021)LF58$945.00$1,050.00$780.00$1,350.00$800.00
58Concrete box culvert (8 FT X 8 FT) (462-7025)LF140$1,250.00$1,250.00$955.00$1,500.00$950.00
59Concrete box culvert (10 FT X 5 FT) (462-7033)LF46$1,600.00$1,550.00$1,144.00$2,000.00$1,250.00
60Concrete box culvert (5 FT X 3 FT)(extend) (462-7062)LF70$525.00$800.00$725.00$1,000.00$1,050.00
61Concrete box culvert (8 FT X 4 FT)(extend) (462-7076)LF49$945.00$1,450.00$851.00$1,500.00$1,250.00
62Concrete box culvert (8 FT X 8 FT)(extend) (462-7080)LF78$1,250.00$1,800.00$885.00$1,650.00$1,700.00
63Concrete box culvert (10 FT X 5 FT)(extend) (462-7088)LF19$1,600.00$1,750.00$1,155.00$2,000.00$1,890.00
64RC pipe (CL III)(18 in) (464-7003)LF1,406$120.00$82.00$73.85$85.00$68.00
65RC pipe (CL III)(24 in) (464-7005)LF552$130.00$105.00$170.50$95.00$185.00
66RC pipe (CL III)(30 in) (464-7007)LF118$160.00$130.00$227.00$105.00$220.00
67RC pipe (CL IV)(24 in) (464-7021)LF248$130.00$120.00$205.00$110.00$215.00
68Headwall (CH - PW - 0) (diameter= 30 in) (466-7103)EACH2$13,000$9,000.00$10,245$8,500.00$11,000
69Wingwall (FW - 0) (HW=5 FT) (466-7147)EACH1$20,500$10,000$10,365$12,500$20,000
70Wingwall (PW - 2) (HW=4 FT) (466-7188)EACH4$14,000$10,000$9,570.00$15,000$30,000
71Wingwall (PW - 2) (HW=5 FT) (466-7189)EACH3$18,000$17,000$11,240$16,500$25,000
72Wingwall (PW - 2) (HW=6 FT) (466-7190)EACH2$22,500$18,000$12,950$25,000$35,000
73Wingwall (PW - 2) (HW=9 FT) (466-7193)EACH2$51,000$18,000$25,305$45,000$42,000
74Set (type I) (36 in) (3: 1) (C) (467-7017)EACH4$7,500.00$10,000$14,205$3,500.00$22,000
75Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308)EACH80$1,900.00$1,500.00$1,080.00$1,000.00$3,000.00
76Set (type II) (24 in) (RCP) (3: 1) (C) (467-7325)EACH2$2,400.00$1,350.00$2,273.00$2,000.00$2,900.00
77Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326)EACH6$3,250.00$1,500.00$2,500.00$2,000.00$3,500.00
78Set (type II) (24 in) (RCP) (6: 1) (P) (467-7328)EACH39$2,200.00$1,650.00$2,841.00$2,000.00$3,600.00
79Set (type II) (30 in) (RCP) (6: 1) (P) (467-7348)EACH4$3,800.00$2,550.00$4,091.00$3,000.00$4,300.00
80Set (type I)(S= 5 FT)(HW= 4 FT)(6:1) (P) (467-7479)EACH4$12,000$12,750$20,455$12,000$27,000
81Clean existing culverts (480-7001)EACH11$3,000.00$3,700.00$2,275.00$2,500.00$3,000.00
82Removing structure (set) (496-7004)EACH43$894.62$250.00$740.00$500.00$1,000.00
83Removing structure (wingwall) (496-7005)EACH8$2,137.00$1,150.00$1,175.00$2,500.00$10,000
84Removing structure (pipe) (496-7007)LF392$50.83$25.00$45.45$50.00$50.00
85Removing structure (bridge 0 - 99 FT length) (496-7009)EACH1$70,000$90,000$70,000$50,000$130,000
86Remove STR (driveway culvert) (496-7038)EACH49$100.00$250.00$1,705.00$500.00$45.00
87Removing rock riprap (496-7040)LF10$113.00$85.00$113.00$100.00$75.00
88Removing structure (masonary) (496-7041)LF126$20.00$25.00$42.00$100.00$78.00
89Removing structure (wood STR) (496-7042)LF30$30.00$15.00$75.00$100.00$45.00
90Mobilization (500-7001)LS1$1,200,000$1,150,000$1,463,000$1,500,000$1,900,000
91Barricades, signs and traffic handling (502-7001)MO21$9,500.00$30,000$10,000$15,000$35,000
92Portable changeable message sign (503-7001)DAY42$95.00$125.00$150.00$150.00$150.00
93Portable changeable message sign (503-7002)EACH4$9,000.00$20,000$20,000$20,000$40,000
94TMA (stationary) (505-7001)DAY120$280.00$335.00$300.00$250.00$400.00
95Rock filter dams (remove) (506-7011)LF140$15.00$56.00$63.00$30.00$70.00
96Construction exits (install) (type 2) (506-7021)SY100$40.00$33.00$180.00$50.00$170.00
97Earthwork (erosion & sediment control, in vehicle) (506-7029)CY100$60.00$60.00$95.00$50.00$100.00
98Temporary sediment control fence (install) (506-7039)LF6,287$4.50$3.75$8.65$4.00$7.00
99Temporary sediment control fence (remove) (506-7041)LF6,287$1.00$2.25$1.80$2.00$2.00
100Rock filter dams (install) (type 2) 6:1 (506-7048)LF140$70.00$74.00$171.00$30.00$170.00
101Constructing detours (508-7001)SY7,500$70.00$50.00$75.00$35.00$125.00
102One-way traffic control (port traffic signal) (510-7003)MO5$5,000.00$6,500.00$7,385.00$9,500.00$4,400.00
103Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001)LF1,800$60.00$88.00$102.00$100.00$120.00
104Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025)LF5,000$10.00$18.00$16.00$20.00$12.00
105Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049)LF1,800$15.00$23.00$23.00$20.00$14.00
106Intersections (ACP) (530-7002)SY974$130.00$185.00$171.00$55.00$175.00
107Driveways (concrete) (530-7006)SY1,193$100.00$155.00$126.00$85.00$185.00
108Driveways (ACP) (530-7010)SY941$55.00$56.00$60.00$45.00$140.00
109Driveways (surface treat) (530-7016)SY3,942$40.00$50.00$30.00$45.00$36.00
110Turnouts (ACP) (530-7018)SY592$75.00$95.00$120.00$55.00$165.00
111Mill rumble strips (asphalt) (shoulder) (533-7001)LF27,412$0.25$0.26$0.35$0.30$0.20
112Mill rumble strips (asphalt) (centerline) (533-7002)LF14,779$0.28$0.26$0.35$0.30$0.25
113Metal W-beam guard fence (timber post) (540-7001)LF1,780.50$30.00$28.00$28.40$30.00$34.00
114Metal beam guard fence trans (thrie-beam) (540-7005)EACH8$3,232.00$2,550.00$3,357.00$1,850.00$2,400.00
115Metal W - beam guard fence (low fill culvert) (540-7018)LF250$40.00$97.00$99.00$110.00$130.00
116Remove metal beam guard fence (542-7001)LF1,105$4.50$3.50$3.40$3.00$9.00
117Remove terminal anchor section (542-7002)EACH2$500.00$278.00$284.00$500.00$600.00
118Guardrail end treatment (install) (544-7001)EACH20$3,500.00$3,650.00$3,700.00$3,850.00$4,300.00
119Guardrail end treatment (remove) (544-7003)EACH6$500.00$280.00$285.00$1,500.00$2,100.00
120Crash cushion attenuator (move & reset) (545-7002)EACH50$2,000.00$2,700.00$2,102.00$4,500.00$3,800.00
121Crash cushion attenuator (remove) (545-7004)EACH4$1,500.00$3,450.00$995.00$2,500.00$2,000.00
122Crash cushion attenuator (install)(S)(N)(TL3) (545-7014)EACH4$9,500.00$15,500$9,640.00$30,000$12,000
123Gate (install)(6'X16') (550-7013)EACH2$3,000.00$2,500.00$2,275.00$20,000$1,000.00
124Wire fence (type C) (552-7003)LF50$50.00$50.00$52.25$20.00$22.00
125Wire fence (special) (552-7005)LF50$75.00$60.00$53.40$100.00$95.00
126Mailbox install-M (TWG-post) type 1 (560-7001)EACH3$350.00$675.00$680.00$1,500.00$700.00
127Mailbox install-S (TWG-post) type 2 (560-7002)EACH36$340.00$325.00$312.00$1,500.00$350.00
128Mailbox install-D (TWG-post) type 2 (560-7003)EACH2$370.00$325.00$324.00$1,500.00$550.00
129Mailbox install-M (TWW-post) type 4 (560-7010)EACH5$370.00$900.00$910.00$1,500.00$800.00
130Relocate existing mailbox (560-7012)EACH46$500.00$625.00$615.00$1,100.00$400.00
131Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001)EACH33$850.00$750.00$761.00$1,500.00$750.00
132Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004)EACH20$1,000.00$925.00$926.00$1,500.00$900.00
133Install small roadside sign support and assembly type 10BWG(1)SA(T-exal) (644-7006)EACH2$710.00$1,100.00$1,091.00$1,500.00$1,000.00
134Remove SM RD SN sup&AM (644-7073)EACH4$130.00$170.00$171.00$500.00$170.00
135Install delineator assembly (D-SW)SZ 1(BRF)CTB (BI) (658-7013)EACH48$25.50$17.00$17.00$100.00$23.00
136Install delineator assembly (D-SW)SZ 1(BRF)GF2(BI) (658-7019)EACH21$35.00$32.00$32.00$100.00$35.00
137Install object marker assembly (OM-2X)(WC)GND (658-7055)EACH17$70.00$73.00$75.00$100.00$95.00
138Work zone pavement marking removing (W)6"(solid) (662-7068)LF82,622$0.80$0.01$0.91$1.00$1.30
139Work zone pavement marking removing (Y)6"(solid) (662-7100)LF39,686$0.80$0.01$0.91$1.00$1.30
140Work zone pavement marking SHT terminal (tab)type W (662-7112)EACH4,129$1.50$1.20$1.14$5.00$1.00
141Work zone pavement marking SHT terminal (tab)type Y (662-7113)EACH1,986$1.50$1.20$1.14$5.00$1.00
142Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114)EACH1,986$1.50$1.70$1.14$5.00$1.20
143Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036)LF650$2.00$15.00$7.39$20.00$12.00
144Reflectorized pavement marking type I (W)(RR crossing)(100MIL) (666-7081)EACH2$1,017.00$1,300.00$852.30$1,500.00$900.00
145Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411)LF41,311$1.35$0.85$1.14$1.00$0.90
146Reflectorized pavement marking type I (Y)6"(broken)(100MIL) (666-7420)LF665$1.50$0.95$2.27$1.00$1.30
147Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423)LF39,686$1.35$0.85$1.14$1.00$0.70
148Reflectorized pavement marker type II-A-A (672-7004)EACH531$7.90$9.50$6.82$6.00$7.00
149Full - width mowing (730-7019)CYC5$3,500.00$3,200.00$4,545.00$5,000.00$3,800.00
150Litter removal (734-7002)CYC15$2,500.00$2,700.00$2,000.00$5,000.00$2,400.00
TxDOT contract A00201583: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.

Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy