TxDOT contract A00206281 bid tabulation
Construct Pedestrian Infrastructure, US 90 (FM 481 to Wood St.). Let by Texas DOT on February 6, 2025, Uvalde, San Antonio District. 10 bids received; low bid $2,879,646 by Relmco, Inc., -11% against the engineer's estimate of $3,252,006.
- Owner
- Texas DOT
- Letting
- 06 FEB 2025
- Pay items
- 58
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Relmco, Inc. | $2,879,646 | Low | -11% |
| 2 | E-Z Bel Construction, LLC | $2,988,997 | +4.0% | -8.0% |
| 3 | Talbert Companies LLC | $3,006,661 | +4.0% | -8.0% |
| 4 | Dan Williams Company | $3,073,918 | +7.0% | -5.0% |
| 5 | Ti-Zack Concrete, LLC | $2,944,584 | +2.0% | -9.0% |
| 6 | STX Civil | $3,121,470 | +8.0% | -4.0% |
| 7 | 3LW Civil LLC | $3,594,670 | +25% | +11% |
| 8 | Lakey, Inc. | $3,710,985 | +29% | +14% |
| 9 | Grey Sky Construction LLC | $4,528,196 | +57% | +39% |
| 10 | CK Newberry, LLC | $4,528,930 | +57% | +39% |
Engineer's estimate: $3,252,006.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Relmco, Inc. | 2. E-Z Bel Construction, LLC | 3. Talbert Companies LLC | 4. Dan Williams Company | 5. Ti-Zack Concrete, LLC | 6. STX Civil |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparation row (tree prune and trim) (100-7010) | STA | 5 | $1,000.00 | $15,000 | $15,000 | $5,007.20 | $8,500.00 | $110.00 | $8,000.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 3,057 | $18.00 | $25.00 | $9.00 | $22.00 | $26.50 | $24.61 | $19.00 |
| 3 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 6,901 | $20.00 | $18.00 | $20.00 | $22.00 | $24.00 | $1.00 | $15.00 |
| 4 | Remove (6"-10") TRT/untrt base & asphalt pavement (105-7006) | SY | 2,950 | $15.00 | $8.00 | $10.00 | $24.20 | $22.00 | $25.51 | $20.00 |
| 5 | Excavation (special) (110-7003) | CY | 150 | $18.00 | $50.00 | $35.00 | $38.50 | $20.00 | $100.32 | $45.00 |
| 6 | Embankment (final)(OC)(type B) (132-7003) | CY | 75 | $100.00 | $100.00 | $30.00 | $28.60 | $20.00 | $100.32 | $35.00 |
| 7 | Furn & place topsoil (4") (160-7002) | SY | 3,897 | $9.00 | $5.00 | $5.05 | $4.95 | $6.00 | $7.72 | $4.50 |
| 8 | Block sodding (162-7002) | SY | 3,897 | $12.00 | $9.00 | $7.25 | $10.51 | $8.00 | $8.80 | $9.00 |
| 9 | D-GR HMA type-C PG64-22 (341-7015) | TON | 50 | $200.00 | $400.00 | $600.00 | $302.50 | $345.00 | $275.00 | $230.00 |
| 10 | Cut & restore asphalt paving (400-7008) | SY | 922 | $125.00 | $100.00 | $90.00 | $110.00 | $80.00 | $126.50 | $125.00 |
| 11 | Riprap (concrete)(4 in) (432-7001) | CY | 5 | $2,000.00 | $630.00 | $1,150.00 | $542.66 | $1,000.00 | $761.08 | $625.00 |
| 12 | Inlet (complete)(armor curb slot) (465-7335) | EACH | 1 | $12,000 | $5,512.50 | $20,000 | $3,520.00 | $8,500.00 | $5,500.00 | $6,500.00 |
| 13 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 1 | $12,000 | $17,693 | $20,000 | $16,500 | $17,500 | $16,500 | $15,000 |
| 14 | Grate & frame (471-7003) | EACH | 8 | $1,500.00 | $4,725.00 | $5,000.00 | $2,200.00 | $3,750.00 | $2,750.00 | $5,000.00 |
| 15 | Adjusting manholes (479-7001) | EACH | 11 | $2,500.00 | $1,942.50 | $1,300.00 | $1,980.00 | $1,500.00 | $684.00 | $2,250.00 |
| 16 | Adjusting manholes (water valve box) (479-7007) | EACH | 7 | $800.00 | $1,155.00 | $1,300.00 | $1,100.00 | $1,500.00 | $508.11 | $700.00 |
| 17 | Mobilization (500-7001) | LS | 1 | $530,132 | $280,000 | $250,000 | $338,507 | $300,000 | $258,512 | $255,000 |
| 18 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $10,000 | $5,500.00 | $4,000.00 | $4,950.00 | $17,000 | $1,100.00 | $5,000.00 |
| 19 | Portable changeable message sign (503-7002) | EACH | 2 | $10,000 | $15,000 | $24,000 | $6,623.09 | $15,000 | $1.10 | $5,000.00 |
| 20 | TMA (stationary) (505-7001) | DAY | 368 | $250.00 | $250.00 | $189.00 | $220.00 | $110.00 | $1.10 | $65.00 |
| 21 | TMA (mobile operation) (505-7003) | DAY | 50 | $300.00 | $250.00 | $21.00 | $385.00 | $0.01 | $1.10 | $200.00 |
| 22 | Construction perimeter fence (506-7034) | LF | 4,575 | $4.00 | $5.00 | $5.00 | $3.58 | $6.50 | $1.10 | $5.00 |
| 23 | Sandbags for erosion control (506-7035) | EACH | 50 | $50.00 | $25.00 | $9.00 | $24.53 | $12.00 | $1.10 | $10.00 |
| 24 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 9,150 | $6.00 | $4.68 | $5.25 | $4.68 | $5.00 | $1.10 | $8.00 |
| 25 | Biodegradable erosion control logs (remove) (506-7046) | LF | 9,150 | $2.00 | $1.32 | $0.80 | $1.32 | $1.50 | $1.10 | $1.00 |
| 26 | Concrete curb (type I) (529-7001) | LF | 1,044 | $20.00 | $16.50 | $59.00 | $27.50 | $32.50 | $54.99 | $30.00 |
| 27 | Driveways (concrete) (530-7006) | SY | 5,967 | $115.00 | $97.02 | $115.00 | $99.00 | $95.00 | $124.31 | $125.00 |
| 28 | Concrete sidewalks (4") (531-7001) | SY | 7,446 | $75.00 | $76.13 | $97.00 | $93.50 | $72.00 | $115.44 | $85.00 |
| 29 | Curb ramps (type 1) (531-7005) | EACH | 32 | $2,200.00 | $2,315.25 | $3,000.00 | $2,090.00 | $2,250.00 | $2,658.01 | $2,500.00 |
| 30 | Curb ramps (type 2) (531-7006) | EACH | 4 | $2,200.00 | $2,320.50 | $3,000.00 | $2,640.00 | $2,250.00 | $2,658.01 | $2,550.00 |
| 31 | Curb ramps (type 3) (531-7007) | EACH | 13 | $2,600.00 | $2,782.50 | $3,500.00 | $2,200.00 | $2,250.00 | $2,658.01 | $2,650.00 |
| 32 | Curb ramps (type 7) (531-7010) | EACH | 45 | $2,200.00 | $2,740.50 | $2,800.00 | $2,200.00 | $2,250.00 | $2,658.01 | $2,750.00 |
| 33 | Curb ramps (type 10) (531-7011) | EACH | 1 | $2,600.00 | $3,097.50 | $5,000.00 | $2,970.00 | $2,250.00 | $2,658.01 | $2,650.00 |
| 34 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 160 | $40.00 | $27.50 | $26.00 | $27.50 | $25.00 | $27.50 | $60.00 |
| 35 | Electrical conductor (no.8) bare (620-7007) | LF | 160 | $3.00 | $1.93 | $2.50 | $1.93 | $1.75 | $1.93 | $10.50 |
| 36 | Ground box type D (162922) (624-7007) | EACH | 27 | $1,200.00 | $1,650.00 | $1,100.00 | $1,430.00 | $1,800.00 | $825.00 | $2,975.00 |
| 37 | Ground box type D (162922)W/apron (624-7008) | EACH | 5 | $1,500.00 | $1,650.00 | $1,600.00 | $1,650.00 | $1,800.00 | $1,650.00 | $4,450.00 |
| 38 | Remove ground box (624-7013) | EACH | 32 | $200.00 | $330.00 | $300.00 | $330.00 | $500.00 | $330.00 | $1,490.00 |
| 39 | Install small roadside sign support and assembly type 10BWG(1)SB(P) (644-7009) | EACH | 2 | $1,000.00 | $1,320.00 | $500.00 | $1,375.00 | $1,500.00 | $797.50 | $1,700.00 |
| 40 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 53 | $800.00 | $500.00 | $250.00 | $646.25 | $1,250.00 | $440.00 | $650.00 |
| 41 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $350.00 | $300.00 | $500.00 | $137.50 | $200.00 | $27.50 | $50.00 |
| 42 | Isrsa TYS80(1)SA(P) (excluding sign) (644-7092) | EACH | 2 | $650.00 | $1,800.00 | $500.00 | $1,045.00 | $2,250.00 | $1,650.00 | $1,285.00 |
| 43 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 2,198 | $4.50 | $19.80 | $9.75 | $10.73 | $16.00 | $10.73 | $13.00 |
| 44 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 136 | $4.00 | $2.20 | $3.00 | $3.30 | $5.00 | $3.30 | $4.00 |
| 45 | Eliminating existing PM & markers (24") (677-7008) | LF | 2,567 | $4.00 | $3.30 | $5.00 | $5.50 | $4.00 | $5.50 | $7.00 |
| 46 | Pavement surface preparation for marking (6") (678-7002) | LF | 136 | $1.00 | $0.11 | $1.00 | $1.10 | $0.01 | $1.10 | $1.50 |
| 47 | Pavement surface preparation for marking (24") (678-7008) | LF | 2,198 | $0.50 | $0.55 | $3.00 | $3.30 | $0.06 | $3.30 | $4.00 |
| 48 | Install highway traffic signal (upgrade) (680-7011) | EACH | 8 | $15,000 | $7,150.00 | $380.00 | $7,150.00 | $10,000 | $7,150.00 | $1.50 |
| 49 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 8 | $500.00 | $775.50 | $940.00 | $797.50 | $800.00 | $797.50 | $2,250.00 |
| 50 | Traffic signal CBL (type A)(12 AWG)(2 conductor) (684-7007) | LF | 4,000 | $2.00 | $2.59 | $2.50 | $2.59 | $2.35 | $2.59 | $7.50 |
| 51 | Traffic signal CBL (type A)(12 AWG)(4 conductor) (684-7009) | LF | 240 | $4.00 | $2.92 | $3.50 | $2.92 | $2.65 | $2.92 | $15.00 |
| 52 | Pedestrian pole assembly (687-7001) | EACH | 8 | $2,800.00 | $3,630.00 | $2,100.00 | $3,630.00 | $7,500.00 | $3,630.00 | $7,400.00 |
| 53 | Pedestrian detect push button (APS) (688-7001) | EACH | 18 | $950.00 | $1,276.00 | $1,550.00 | $1,276.00 | $1,250.00 | $1,276.00 | $3,000.00 |
| 54 | Pedestrian detector controller unit (688-7003) | EACH | 8 | $4,366.00 | $4,950.00 | $280.00 | $4,950.00 | $8,000.00 | $4,950.00 | $1.50 |
| 55 | Removal of cables (690-7009) | LF | 1,500 | $2.00 | $2.20 | $2.00 | $2.20 | $2.00 | $2.20 | $3.00 |
| 56 | Removal of signal head assembly (690-7024) | EACH | 10 | $400.00 | $203.50 | $140.00 | $203.50 | $185.00 | $203.50 | $225.00 |
| 57 | Removal of pedestrian push buttons (690-7030) | EACH | 20 | $125.00 | $55.00 | $90.00 | $55.00 | $50.00 | $55.00 | $150.00 |
| 58 | LED roadside sign (6066-7001) | EACH | 2 | $12,000 | $4,757.50 | $4,000.00 | $4,757.50 | $10,000 | $4,757.50 | $9,700.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of February 6, 2025. Compiled by Mirage Metrics.