TxDOT contract A00206294 bid tabulation
Intersection Improvement, BS 6R (Old Hearne Road to FM 158). Let by Texas DOT on May 1, 2025, Brazos, Bryan District. 4 bids received; low bid $4,454,973 by Larry Young Paving, Inc., -8.8% against the engineer's estimate of $4,885,537.
- Owner
- Texas DOT
- Letting
- 01 MAY 2025
- Pay items
- 152
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Larry Young Paving, Inc. | $4,454,973 | Low | -9.0% |
| 2 | Brazos Paving, Inc. | $4,800,359 | +8.0% | -2.0% |
| 3 | Ti-Zack Concrete, LLC | $5,287,973 | +19% | +8.0% |
| 4 | Knife River Corporation - South | $5,391,744 | +21% | +10% |
Engineer's estimate: $4,885,537.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Larry Young Paving, Inc. | 2. Brazos Paving, Inc. | 3. Ti-Zack Concrete, LLC | 4. Knife River Corporation - South |
|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7001) | ACRE | 1.03 | $25,000 | $11,000 | $17,575 | $11,500 | $43,400 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 6 | $790.00 | $775.00 | $977.50 | $667.00 | |
| 3 | Preparation row (tree remove) (12"-24" diameter) (100-7004) | EACH | 17 | $1,200.00 | $1,214.00 | $1,437.50 | $1,046.00 | |
| 4 | Preparation row (tree remove) (24"-36" diameter) (100-7005) | EACH | 4 | $2,500.00 | $2,325.00 | $6,037.50 | $2,000.00 | |
| 5 | Preparation row (tree remove) (36"-48" diameter) (100-7006) | EACH | 1 | $3,600.00 | $4,650.00 | $8,625.00 | $4,000.00 | |
| 6 | Tree protection (install) (100-7013) | EACH | 160 | $590.00 | $170.00 | $165.00 | $17.25 | $140.00 |
| 7 | Removing concrete (pavement) (104-7001) | SY | 95 | $14.00 | $68.50 | $21.00 | $57.60 | |
| 8 | Removing concrete (medians) (104-7008) | SY | 326 | $14.00 | $85.00 | $24.48 | $29.80 | |
| 9 | Removing concrete (pavers) (104-7010) | SY | 185 | $14.00 | $45.00 | $21.57 | $32.40 | |
| 10 | Removing concrete (driveways) (104-7011) | SY | 529 | $14.00 | $68.70 | $30.17 | $37.74 | |
| 11 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 1,015 | $14.00 | $49.60 | $31.45 | $51.80 | |
| 12 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 2,072 | $13.00 | $15.21 | $11.55 | $79.12 | |
| 13 | Removing concrete (miscellaneous) (104-7046) | SY | 53 | $14.00 | $73.15 | $30.11 | $32.80 | |
| 14 | Remove (5"-9") TRT/untrt base & asphalt pavement (105-7005) | SY | 40 | $20.00 | $105.55 | $39.90 | $42.00 | |
| 15 | Remove (12"-16") TRT/untrt base & asphalt pavement (105-7012) | SY | 2,528 | $29.00 | $28.50 | $18.94 | $22.30 | |
| 16 | Furn & place topsoil (4") (160-7002) | SY | 1,424 | $3.50 | $10.50 | $7.81 | $14.00 | |
| 17 | General use compost (2") (161-7011) | SY | 2,604.40 | $3.00 | $5.25 | $5.15 | $4.80 | $10.00 |
| 18 | Block sodding (162-7002) | SY | 1,424 | $9.75 | $9.70 | $11.45 | $8.33 | |
| 19 | Fertilizer (166-7001) | ACRE | 0.29 | $8,200.00 | $8,000.00 | $937.08 | $2,000.00 | |
| 20 | Vegetative watering (168-7001) | TGL | 14.24 | $77.00 | $54.75 | $276.54 | $70.00 | |
| 21 | Irrigation system (type II) (170-7003) | EACH | 1 | $120,000 | $55,000 | $199,108 | $279,976 | $171,470 |
| 22 | Soil amend (type I) (192-7008) | SY | 2,604.40 | $0.20 | $1.00 | $0.94 | $1.02 | $0.90 |
| 23 | Plant bed preparation (type II) (192-7011) | SY | 2,604.40 | $0.85 | $8.25 | $7.90 | $33.35 | $6.83 |
| 24 | Landscape edge (type I) (192-7017) | LF | 2,407 | $8.90 | $13.00 | $12.85 | $22.68 | $11.06 |
| 25 | Loose aggregate GRND cover (type I) (192-7024) | CY | 602.20 | $215.00 | $150.00 | $143.00 | $231.91 | $123.05 |
| 26 | Plant material (1 gal) (shrub) (192-7044) | EACH | 2,938 | $15.00 | $15.00 | $13.80 | $16.88 | $11.88 |
| 27 | Plant material (3 gal) (shrub) (192-7046) | EACH | 3,150 | $30.00 | $50.00 | $49.20 | $41.58 | $42.22 |
| 28 | Soil amend (type II) (192-7084) | SY | 2,604.40 | $0.20 | $0.75 | $0.65 | $1.02 | $0.54 |
| 29 | Soil amend (type III) (192-7085) | SY | 2,604.40 | $2.00 | $1.25 | $1.15 | $2.91 | $1.00 |
| 30 | Landscape establish (193-7001) | MO | 12 | $6,500.00 | $1,900.00 | $1,860.00 | $10,279 | $1,602.00 |
| 31 | Landscape establish (193-7002) | CYC | 6 | $12,500 | $2,100.00 | $4,020.00 | $17,694 | $3,462.00 |
| 32 | Landscape treat (type III) (193-7036) | CYC | 1 | $2,597.00 | $160.00 | $1,885.00 | $57,803 | $1,700.00 |
| 33 | CM TRT(PT MX)(CL M)(type D)(GR 4)(FN pos) (276-7091) | CY | 191 | $280.00 | $146.60 | $517.50 | $338.20 | |
| 34 | Prime coat (AE-P) (310-7001) | GAL | 239 | $36.00 | $6.80 | $11.50 | $53.00 | |
| 35 | D-GR HMA type D PG64-22 (341-7043) | TON | 9 | $540.00 | $882.00 | $402.50 | $3,834.00 | |
| 36 | SP mixes SP-B PG64-22 (344-7001) | TON | 502 | $260.00 | $155.60 | $294.40 | $354.00 | |
| 37 | SP mixes SP-C sac-A PG76-22 (344-7030) | TON | 1,164 | $200.00 | $152.30 | $294.40 | $270.73 | |
| 38 | Planing asphalt concrete pavement(2") (354-7051) | SY | 2,024 | $5.00 | $6.50 | $11.50 | $14.00 | |
| 39 | Planing asphalt concrete pavement(3") (354-7052) | SY | 6,248 | $5.75 | $7.50 | $13.80 | $6.74 | |
| 40 | Cut & restoring pavement (400-7006) | SY | 4 | $440.00 | $967.00 | $126.50 | $694.00 | |
| 41 | Cem stabil BKFL (400-7010) | CY | 18 | $140.00 | $117.50 | $287.50 | $220.00 | |
| 42 | Trench excavation protection (402-7001) | LF | 13 | $3.25 | $87.80 | $115.00 | $171.00 | |
| 43 | Drilled shaft (traffic signal pole) (24 in) (416-7042) | LF | 60 | $200.00 | $155.10 | $138.23 | $134.00 | |
| 44 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 22 | $270.00 | $220.90 | $196.88 | $190.00 | |
| 45 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 65 | $280.00 | $256.85 | $228.76 | $221.00 | |
| 46 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 88 | $350.00 | $412.20 | $367.39 | $355.00 | |
| 47 | Class A concrete (collar) (420-7008) | EACH | 1 | $5,600.00 | $1,584.60 | $2,593.25 | $2,430.00 | |
| 48 | Riprap (concrete)(5 in) (432-7002) | CY | 2 | $1,000.00 | $886.10 | $784.69 | $1,104.00 | |
| 49 | RC pipe (CL III)(36 in) (464-7009) | LF | 10 | $610.00 | $528.60 | $327.75 | $800.00 | |
| 50 | Inlet (complete)(type AZ)(hou) (465-7316) | EACH | 1 | $11,000 | $12,850 | $18,400 | $9,275.00 | |
| 51 | Adjusting inlets (479-7002) | EACH | 1 | $3,700.00 | $4,037.00 | $2,300.00 | $6,360.00 | |
| 52 | Adjusting inlets (cap) (479-7006) | EACH | 1 | $2,300.00 | $5,105.00 | $1,725.00 | $6,100.00 | |
| 53 | Mobilization (500-7001) | LS | 1 | $425,000 | $388,000 | $285,000 | $489,987 | $322,000 |
| 54 | Barricades, signs and traffic handling (502-7001) | MO | 18 | $11,000 | $3,900.00 | $16,485 | $3,450.00 | $20,500 |
| 55 | Portable changeable message sign (503-7002) | EACH | 2 | $11,000 | $38,320 | $1.15 | $15,000 | |
| 56 | TMA (stationary) (505-7001) | DAY | 83 | $320.00 | $225.00 | $1.15 | $500.00 | |
| 57 | TMA (mobile operation) (505-7003) | DAY | 7 | $1,100.00 | $495.00 | $1.15 | $950.00 | |
| 58 | Biodegradable erosion control logs (install) (8") (506-7043) | LF | 45 | $5.75 | $12.91 | $1.15 | $11.00 | |
| 59 | Biodegradable erosion control logs (remove) (506-7046) | LF | 45 | $1.00 | $6.46 | $1.15 | $5.50 | |
| 60 | Landscape pavers (528-7001) | SY | 592 | $180.00 | $126.60 | $233.45 | $120.00 | |
| 61 | Concrete curb (mono) (type II) (529-7007) | LF | 512 | $15.00 | $19.20 | $60.43 | $43.00 | |
| 62 | Concrete curb & gutter (type II) (529-7009) | LF | 1,869 | $49.00 | $36.20 | $60.43 | $100.60 | |
| 63 | Intersections (concrete) (530-7001) | SY | 134 | $200.00 | $116.20 | $177.93 | $193.00 | |
| 64 | Intersections (ACP) (530-7002) | SY | 724 | $56.00 | $65.80 | $115.00 | $332.90 | |
| 65 | Driveways (concrete) (hes) (530-7007) | SY | 835 | $140.00 | $132.00 | $162.39 | $207.34 | |
| 66 | Concrete sidewalks (6") (531-7003) | SY | 1,488 | $110.00 | $98.60 | $131.85 | $175.00 | |
| 67 | Curb ramps (type 1) (531-7005) | EACH | 2 | $2,100.00 | $1,575.00 | $2,606.78 | $1,730.00 | |
| 68 | Curb ramps (type 6) (531-7009) | EACH | 2 | $2,100.00 | $3,330.00 | $2,606.78 | $2,561.00 | |
| 69 | Curb ramps (type 7) (531-7010) | EACH | 11 | $2,200.00 | $2,545.00 | $2,606.78 | $3,225.00 | |
| 70 | Curb ramps (type 10) (531-7011) | EACH | 2 | $2,200.00 | $2,545.00 | $2,606.78 | $3,337.00 | |
| 71 | Curb ramps (type 21) (531-7013) | EACH | 1 | $2,800.00 | $1,836.00 | $2,606.78 | $1,954.00 | |
| 72 | Concrete median (536-7002) | SY | 21 | $460.00 | $185.00 | $145.12 | $1,280.00 | |
| 73 | Concrete median (nose) (536-7005) | SY | 6 | $520.00 | $218.60 | $168.50 | $735.00 | |
| 74 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 790 | $21.00 | $14.00 | $26.85 | $17.19 | $16.60 |
| 75 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 1,740 | $33.25 | $19.00 | $27.35 | $24.39 | $23.57 |
| 76 | Conduit (PVC) (schedule 80) (3") (618-7060) | LF | 375 | $13.00 | $29.35 | $19.42 | $18.80 | |
| 77 | Conduit (PVC) (schedule 80) (3") (bore) (618-7061) | LF | 90 | $21.00 | $29.85 | $26.62 | $25.72 | |
| 78 | Conduit (PVC) (schedule 80) (4") (618-7064) | LF | 265 | $15.00 | $25.35 | $22.01 | $21.27 | |
| 79 | Conduit (PVC) (schedule 80) (4") (bore) (618-7065) | LF | 800 | $23.00 | $36.80 | $32.81 | $31.70 | |
| 80 | ITS multi-duct CND (PVC-80) (619-7005) | LF | 5,190 | $26.50 | $39.00 | $27.90 | $18.16 | $17.54 |
| 81 | ITS multi-duct CND (PVC-80)(bore) (619-7006) | LF | 21,215 | $25.00 | $22.00 | $20.20 | $18.01 | $17.40 |
| 82 | ITS multi-duct CND (RMC) (619-7008) | LF | 200 | $250.00 | $137.10 | $122.21 | $118.00 | |
| 83 | Fiber optic cable road marker (619-7013) | LF | 46 | $160.00 | $100.00 | $176.20 | $157.03 | $152.00 |
| 84 | Electrical conductor (no.8) insulated (620-7008) | LF | 3,100 | $2.25 | $3.00 | $2.73 | $2.63 | |
| 85 | Electrical conductor (no.6) bare (620-7009) | LF | 2,100 | $2.25 | $3.20 | $2.86 | $2.77 | |
| 86 | Electrical conductor (no.4) bare (620-7011) | LF | 70 | $2.75 | $4.20 | $3.73 | $3.60 | |
| 87 | Electrical conductor (no.4) insulated (620-7012) | LF | 120 | $3.25 | $4.65 | $4.16 | $4.02 | |
| 88 | ITS GND box(pcast) type 2 (366036) (623-7007) | EACH | 11 | $11,000 | $6,900.00 | $8,950.00 | $7,979.07 | $7,709.00 |
| 89 | ITS GND box(pcast) type 2 (366036)W/aprn (623-7008) | EACH | 4 | $6,900.00 | $9,355.00 | $8,338.63 | $8,057.00 | |
| 90 | Ground box type D (162922) (624-7007) | EACH | 18 | $1,500.00 | $1,000.00 | $1,105.00 | $985.44 | $952.00 |
| 91 | Ground box type D (162922)W/apron (624-7008) | EACH | 32 | $1,800.00 | $1,100.00 | $1,509.00 | $1,345.01 | $1,300.00 |
| 92 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 3 | $8,200.00 | $9,553.00 | $8,514.60 | $8,227.00 | |
| 93 | Aluminum signs (type A) (636-7001) | SF | 299 | $61.00 | $45.00 | $31.14 | $33.00 | |
| 94 | Relocate SM RD SN sup&AM type TWT (644-7068) | EACH | 1 | $730.00 | $710.00 | $656.88 | $635.00 | |
| 95 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $200.00 | $194.00 | $86.25 | $84.00 | |
| 96 | Work zone pavement marking removing (W)6"(solid) (662-7068) | LF | 5,050 | $2.75 | $2.70 | $1.27 | $1.22 | |
| 97 | Work zone pavement marking removing (Y)6"(solid) (662-7100) | LF | 5,540 | $2.75 | $2.70 | $1.27 | $1.22 | |
| 98 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,220 | $3.25 | $3.25 | $2.01 | $1.94 | |
| 99 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 1,195 | $12.00 | $11.75 | $10.35 | $10.00 | |
| 100 | Pavement sler 6" (666-7347) | LF | 830 | $1.25 | $1.30 | $0.21 | $1.00 | |
| 101 | Pavement sler 8" (666-7348) | LF | 1,140 | $1.25 | $1.30 | $0.28 | $0.30 | |
| 102 | Pavement sler 24" (666-7352) | LF | 370 | $4.00 | $3.90 | $0.83 | $0.90 | |
| 103 | Pavement sler (arrow) (666-7353) | EACH | 14 | $33.00 | $32.25 | $5.75 | $6.00 | |
| 104 | Pavement sler (word) (666-7354) | EACH | 14 | $33.00 | $32.25 | $5.75 | $6.00 | |
| 105 | Reflectorized pavement marking type I (W)6"(broken)(100MIL) (666-7408) | LF | 390 | $4.00 | $3.90 | $1.32 | $1.30 | |
| 106 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 830 | $2.75 | $2.60 | $1.32 | $1.30 | |
| 107 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 14 | $460.00 | $451.60 | $323.58 | $313.00 | |
| 108 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 14 | $540.00 | $529.00 | $353.03 | $340.00 | |
| 109 | Reflectorized pavement marker type I-C (672-7002) | EACH | 90 | $12.00 | $11.60 | $11.50 | $11.00 | |
| 110 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 4 | $12.00 | $11.60 | $11.50 | $11.00 | |
| 111 | Eliminating existing PM & markers (6") (677-7002) | LF | 4,180 | $2.75 | $2.60 | $3.70 | $3.60 | |
| 112 | Pavement surface preparation for marking (6") (678-7002) | LF | 830 | $1.25 | $1.30 | $0.02 | $1.00 | |
| 113 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,140 | $1.25 | $1.30 | $0.05 | $1.00 | |
| 114 | Pavement surface preparation for marking (24") (678-7008) | LF | 370 | $4.00 | $3.90 | $0.14 | $0.20 | |
| 115 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 14 | $20.00 | $19.37 | $5.75 | $6.00 | |
| 116 | Pavement surface preparation for marking (word) (678-7016) | EACH | 14 | $20.00 | $19.37 | $5.75 | $6.00 | |
| 117 | Install highway traffic signal (isolated) (680-7002) | EACH | 3 | $70,000 | $43,292 | $38,587 | $37,283 | |
| 118 | Removing traffic signals (680-7004) | EACH | 8 | $6,400.00 | $5,120.00 | $1,803.20 | $1,744.00 | |
| 119 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 25 | $250.00 | $331.00 | $294.40 | $285.00 | |
| 120 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 8 | $250.00 | $331.00 | $294.40 | $285.00 | |
| 121 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 25 | $250.00 | $331.00 | $294.40 | $285.00 | |
| 122 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 14 | $250.00 | $331.00 | $294.40 | $285.00 | |
| 123 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 25 | $250.00 | $331.00 | $294.40 | $285.00 | |
| 124 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 8 | $250.00 | $331.00 | $294.40 | $285.00 | |
| 125 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 18 | $590.00 | $845.40 | $753.25 | $728.00 | |
| 126 | Backplate W/reflectorized border(3 sec)aluminum (682-7039) | EACH | 27 | $170.00 | $198.65 | $175.95 | $171.00 | |
| 127 | Backplate W/reflectorized border(4 sec)aluminum (682-7040) | EACH | 6 | $220.00 | $251.80 | $224.25 | $217.00 | |
| 128 | Traffic signal CBL (type A)(14 AWG)(1 conductor) (684-7027) | LF | 26,405 | $1.40 | $1.25 | $2.25 | $2.01 | $1.94 |
| 129 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 2,625 | $2.25 | $3.00 | $2.67 | $2.58 | |
| 130 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 2,335 | $3.00 | $3.50 | $3.08 | $2.98 | |
| 131 | Traffic signal CBL (type A)(14 AWG)(9 conductor) (684-7035) | LF | 985 | $2.50 | $4.11 | $3.66 | $3.53 | |
| 132 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 2,570 | $1.50 | $2.40 | $2.15 | $2.08 | |
| 133 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 1 | $14,000 | $17,008 | $15,159 | $14,647 | |
| 134 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 1 | $14,000 | $17,420 | $15,525 | $15,000 | |
| 135 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $17,000 | $20,136 | $17,948 | $17,341 | |
| 136 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 2 | $18,000 | $21,466 | $19,134 | $18,487 | |
| 137 | Ins traffic signal PL AM(S)1 arm(50')lum (686-7055) | EACH | 3 | $42,000 | $51,127 | $45,571 | $44,030 | |
| 138 | Ins traffic signal PL AM(S)2 arm(40-28')lum (686-7139) | EACH | 1 | $20,000 | $23,700 | $21,117 | $20,400 | |
| 139 | Ins traffic signal PL AM(S)2 arm(50 - 40')lum (686-7191) | EACH | 1 | $44,000 | $52,635 | $46,914 | $45,300 | |
| 140 | Pedestrian pole assembly (687-7001) | EACH | 10 | $1,500.00 | $3,535.00 | $3,148.70 | $3,040.00 | |
| 141 | Pedestrian detect push button (APS) (688-7001) | EACH | 18 | $1,200.00 | $1,281.00 | $1,142.24 | $1,104.00 | |
| 142 | Bonding course (3007-7001) | GAL | 883 | $7.75 | $7.65 | $11.50 | $5.00 | |
| 143 | Bbu system (external battery cabinet) (6007-7001) | EACH | 3 | $8,600.00 | $12,250 | $10,918 | $10,550 | |
| 144 | VDS prosr sys (6017-7001) | EACH | 3 | $14,000 | $17,460 | $15,562 | $15,036 | |
| 145 | VIVDS cam assy var LNS (6017-7003) | EACH | 12 | $6,100.00 | $8,270.00 | $7,370.35 | $7,122.00 | |
| 146 | VDS CNTRL software (6017-7009) | EACH | 3 | $540.00 | $808.00 | $719.90 | $696.00 | |
| 147 | VDS atspm (6017-7010) | EACH | 3 | $4,200.00 | $5,243.00 | $4,672.45 | $4,515.00 | |
| 148 | VDS cabling (6017-7012) | LF | 1,880 | $1.75 | $3.80 | $3.37 | $3.26 | |
| 149 | CCTV field equipment (digital) (6018-7002) | EACH | 3 | $2,000.00 | $3,725.00 | $3,318.90 | $3,207.00 | |
| 150 | ITS com CBL (ethernet) (6018-7004) | LF | 275 | $2.75 | $7.90 | $7.04 | $6.80 | |
| 151 | Fiber optic CBL (single-mode)(12 fiber) (6027-7001) | LF | 1,270 | $6.85 | $1.75 | $7.95 | $7.08 | $6.84 |
| 152 | Fiber optic CBL (SNGL-mode)(72 fiber) (6027-7014) | LF | 52,810 | $2.55 | $2.50 | $3.05 | $2.71 | $2.62 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of May 1, 2025. Compiled by Mirage Metrics.