TxDOT contract A00206903 bid tabulation
Construct Pedestrian Infrastructure, Various (SH 60 (Milam St) to FM 1301 (Boling Hwy)). Let by Texas DOT on July 2, 2025, Wharton, Yoakum District. 8 bids received; low bid $2,973,237 by Ti-Zack Concrete, LLC, -17% against the engineer's estimate of $3,601,994.
- Owner
- Texas DOT
- Letting
- 02 JUL 2025
- Pay items
- 82
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ti-Zack Concrete, LLC | $2,973,237 | Low | -17% |
| 2 | 3LW Civil LLC | $3,111,287 | +5.0% | -14% |
| 3 | Talbert Companies LLC | $3,198,881 | +8.0% | -11% |
| 4 | STX Civil | $3,360,994 | +13% | -7.0% |
| 5 | Encino Landscape, Inc. | $3,591,172 | +21% | 0.0% |
| 6 | E-Z Bel Construction, LLC | $3,733,780 | +26% | +4.0% |
| 7 | C. E. Barker, LTD. | $3,943,181 | +33% | +9.0% |
| 8 | Ragle Construction, Inc. | $3,948,350 | +33% | +10% |
Engineer's estimate: $3,601,994.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Ti-Zack Concrete, LLC | 2. 3LW Civil LLC | 3. Talbert Companies LLC | 4. STX Civil | 5. Encino Landscape, Inc. | 6. E-Z Bel Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 47 | $1,000.00 | $400.00 | $1,750.00 | $4,400.00 | $3,500.00 | $1,000.00 | $1,500.00 |
| 2 | Removing concrete (riprap) (104-7006) | SY | 110 | $16.00 | $68.40 | $25.00 | $13.59 | $10.00 | $20.00 | $45.00 |
| 3 | Removing concrete (driveways) (104-7011) | SY | 1,676 | $28.00 | $26.94 | $30.00 | $18.15 | $15.00 | $25.00 | $45.00 |
| 4 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 1,203 | $68.00 | $25.02 | $25.00 | $18.70 | $15.00 | $25.00 | $45.00 |
| 5 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 4,926 | $21.00 | $9.16 | $18.50 | $17.71 | $3.00 | $15.00 | $45.00 |
| 6 | Removing concrete (miscellaneous) (104-7046) | SY | 17 | $75.00 | $44.26 | $35.00 | $29.70 | $10.00 | $30.00 | $59.00 |
| 7 | Remove (2"-6") TRT/untrt base & asphalt pavement (105-7002) | SY | 1,224 | $100.00 | $24.59 | $40.00 | $7.19 | $10.00 | $20.00 | $9.00 |
| 8 | Block sodding (162-7002) | SY | 2,123 | $10.00 | $5.00 | $4.56 | $4.18 | $6.00 | $10.00 | $6.00 |
| 9 | Vegetative watering (168-7001) | TGL | 17.50 | $55.00 | $1.00 | $82.50 | $38.50 | $50.00 | $100.00 | $300.00 |
| 10 | Flexible pavement structure repair(8") (351-7007) | SY | 553 | $74.00 | $95.00 | $162.00 | $79.11 | $125.00 | $200.00 | $135.00 |
| 11 | Drilled shaft (roadway illumination pole) (24 in) (416-7039) | LF | 36 | $340.00 | $193.32 | $330.00 | $212.65 | $504.00 | $250.00 | $1,600.00 |
| 12 | Riprap (concrete)(5 in) (432-7002) | CY | 42 | $850.00 | $824.56 | $675.00 | $726.00 | $750.00 | $1,000.00 | $911.00 |
| 13 | Riprap (concrete)(CL B) (432-7005) | CY | 2.10 | $900.00 | $824.56 | $850.00 | $737.00 | $800.00 | $1,000.00 | $2,500.00 |
| 14 | Rail (handrail)(type A) (450-7058) | LF | 829 | $210.00 | $96.20 | $88.00 | $111.38 | $160.00 | $100.00 | $100.00 |
| 15 | CMP (gal steel 12 in) (460-7001) | LF | 12 | $150.00 | $182.38 | $225.00 | $863.50 | $110.00 | $50.00 | $106.00 |
| 16 | RC pipe (CL III)(18 in) (464-7003) | LF | 28 | $105.00 | $255.00 | $258.00 | $1,375.00 | $130.00 | $100.00 | $103.00 |
| 17 | Inlet (complete)(PSL)(FG)(3FTX3FT-3FTX3FT) (465-7126) | EACH | 2 | $5,660.00 | $8,614.01 | $7,500.00 | $16,335 | $10,000 | $5,000.00 | $16,500 |
| 18 | Adjusting manholes (479-7001) | EACH | 5 | $3,000.00 | $300.96 | $3,000.00 | $3,850.00 | $2,900.00 | $2,500.00 | $1,200.00 |
| 19 | Adjusting manholes & inlets (479-7003) | EACH | 3 | $4,500.00 | $501.60 | $4,500.00 | $4,015.00 | $2,800.00 | $3,000.00 | $2,900.00 |
| 20 | Adjusting inlets (cap) (479-7006) | EACH | 2 | $1,000.00 | $2,000.00 | $1,800.00 | $4,015.00 | $5,000.00 | $1,000.00 | $2,900.00 |
| 21 | Clean existing culverts (480-7001) | EACH | 6 | $3,500.00 | $500.00 | $3,750.00 | $4,950.00 | $3,500.00 | $4,000.00 | $1,500.00 |
| 22 | Removing structure (set) (496-7004) | EACH | 3 | $550.00 | $962.00 | $750.00 | $935.00 | $250.00 | $500.00 | $385.00 |
| 23 | Removing structure (headwall) (496-7006) | EACH | 4 | $2,100.00 | $962.00 | $1,700.00 | $2,475.00 | $750.00 | $2,000.00 | $2,500.00 |
| 24 | Mobilization (500-7001) | LS | 1 | $322,500 | $238,075 | $203,000 | $268,455 | $300,000 | $400,000 | $300,000 |
| 25 | Barricades, signs and traffic handling (502-7001) | MO | 14 | $4,000.00 | $1,616.00 | $2,588.57 | $1,318.89 | $3,500.00 | $6,000.00 | $2,500.00 |
| 26 | TMA (stationary) (505-7001) | DAY | 20 | $500.00 | $0.01 | $2,000.00 | $461.99 | $180.00 | $500.00 | $189.00 |
| 27 | Sandbags for erosion control (506-7035) | EACH | 30 | $14.00 | $0.01 | $3.30 | $11.00 | $1.00 | $1.00 | $9.00 |
| 28 | Temporary sediment control fence (install) (506-7039) | LF | 500 | $13.00 | $0.01 | $4.50 | $4.13 | $5.00 | $3.00 | $2.00 |
| 29 | Temporary sediment control fence (remove) (506-7041) | LF | 500 | $2.00 | $0.01 | $1.37 | $1.38 | $1.00 | $1.00 | $1.00 |
| 30 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 825 | $10.00 | $0.01 | $10.80 | $9.90 | $8.00 | $10.00 | $9.00 |
| 31 | Biodegradable erosion control logs (remove) (506-7046) | LF | 825 | $3.00 | $0.01 | $2.40 | $2.20 | $1.00 | $1.00 | $2.00 |
| 32 | Concrete curb (type II) (529-7002) | LF | 42 | $35.00 | $65.36 | $42.00 | $20.35 | $45.00 | $35.00 | $50.00 |
| 33 | Concrete curb & gutter (type II) (529-7009) | LF | 3,721 | $90.00 | $54.66 | $60.00 | $35.75 | $55.00 | $30.00 | $34.00 |
| 34 | Concrete curb (type F2) (529-7015) | LF | 442 | $225.00 | $176.16 | $139.38 | $297.55 | $180.00 | $300.00 | $250.00 |
| 35 | Concrete curb (type C1) (529-7016) | LF | 391 | $80.00 | $150.99 | $53.11 | $217.05 | $180.00 | $250.00 | $275.00 |
| 36 | Concrete curb (type F1) (529-7017) | LF | 257 | $95.00 | $211.39 | $130.74 | $167.20 | $180.00 | $250.00 | $250.00 |
| 37 | Concrete curb (type F3) (529-7022) | LF | 130 | $200.00 | $264.24 | $168.72 | $318.01 | $180.00 | $250.00 | $325.00 |
| 38 | Driveways (concrete) (530-7006) | SY | 2,471 | $150.00 | $128.68 | $106.49 | $102.30 | $118.00 | $120.00 | $150.00 |
| 39 | Driveways (concrete) (hes) (530-7007) | SY | 320 | $176.00 | $133.53 | $110.66 | $96.80 | $127.00 | $125.00 | $152.00 |
| 40 | Concrete sidewalks (6") (531-7003) | SY | 8,820 | $100.00 | $118.81 | $110.00 | $106.92 | $110.00 | $135.00 | $115.00 |
| 41 | Concrete sidewalk (steps) (531-7004) | SY | 2 | $1,000.00 | $195.39 | $1,750.00 | $209.00 | $2,000.00 | $200.00 | $2,300.00 |
| 42 | Curb ramps (type 1) (531-7015) | SY | 284 | $200.00 | $135.52 | $144.35 | $176.22 | $135.00 | $150.00 | $315.00 |
| 43 | Curb ramps (type 7) (531-7020) | SY | 326 | $200.00 | $135.52 | $195.00 | $214.50 | $240.00 | $150.00 | $315.00 |
| 44 | Curb ramps (type 10) (531-7021) | SY | 236 | $220.00 | $135.52 | $184.46 | $188.10 | $240.00 | $150.00 | $315.00 |
| 45 | Concrete sidewalks (special) (531-7025) | SY | 15 | $150.00 | $976.30 | $1,250.00 | $280.83 | $210.00 | $180.00 | $600.00 |
| 46 | Relocate existing mailbox (560-7012) | EACH | 5 | $300.00 | $181.50 | $780.00 | $181.50 | $100.00 | $500.00 | $165.00 |
| 47 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 1,520 | $10.50 | $17.51 | $16.50 | $11.51 | $15.65 | $20.00 | $25.00 |
| 48 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 115 | $17.00 | $20.81 | $21.00 | $25.30 | $23.23 | $22.00 | $37.00 |
| 49 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 690 | $26.00 | $28.56 | $27.50 | $32.49 | $38.19 | $30.00 | $48.00 |
| 50 | Conduit (PVC) (schedule 80) (2") (bore) (618-7055) | LF | 50 | $10.50 | $26.18 | $21.00 | $17.60 | $24.17 | $30.00 | $47.00 |
| 51 | Electrical conductor (no.8) bare (620-7007) | LF | 2,305 | $1.50 | $2.33 | $2.20 | $2.18 | $2.03 | $3.00 | $3.00 |
| 52 | Electrical conductor (no.8) insulated (620-7008) | LF | 2,500 | $1.50 | $3.09 | $2.75 | $2.42 | $2.63 | $3.20 | $3.00 |
| 53 | Electrical conductor (no.6) bare (620-7009) | LF | 20 | $1.50 | $2.63 | $2.75 | $1.96 | $2.39 | $3.00 | $4.00 |
| 54 | Electrical conductor (no.6) insulated (620-7010) | LF | 35 | $2.00 | $3.11 | $3.10 | $2.79 | $3.20 | $3.20 | $4.00 |
| 55 | Ground box type A (122311)W/apron (624-7002) | EACH | 3 | $1,500.00 | $1,316.99 | $1,650.00 | $1,122.00 | $1,782.32 | $1,500.00 | $1,626.00 |
| 56 | Ground box type D (162922)W/apron (624-7008) | EACH | 8 | $1,460.00 | $1,387.40 | $1,650.00 | $1,314.50 | $1,920.42 | $1,500.00 | $1,896.00 |
| 57 | Elc SRV type A 240/480 060(NS)SS(E)SP(O) (628-7048) | EACH | 1 | $9,000.00 | $8,691.90 | $8,250.00 | $7,051.00 | $11,596 | $10,000 | $14,547 |
| 58 | Elc SRV type D 120/240 060(NS)GS(N)EX(O) (628-7131) | EACH | 1 | $10,000 | $3,130.57 | $8,250.00 | $7,139.00 | $2,173.84 | $3,000.00 | $3,391.00 |
| 59 | Elc SRV type D 120/240 060(NS)SS(E)PS(U) (628-7147) | EACH | 2 | $10,000 | $7,896.38 | $11,000 | $6,853.00 | $12,382 | $10,000 | $12,339 |
| 60 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 4 | $654.00 | $624.80 | $660.00 | $792.00 | $650.00 | $1,000.00 | $720.00 |
| 61 | Install small roadside sign support and assembly type 10BWG(1)SA(P-BM) (644-7002) | EACH | 8 | $1,000.00 | $693.00 | $737.00 | $863.50 | $750.00 | $1,500.00 | $785.00 |
| 62 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 4 | $750.00 | $720.50 | $770.00 | $951.50 | $755.00 | $1,500.00 | $865.00 |
| 63 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 12 | $1,030.00 | $503.80 | $550.00 | $731.50 | $500.00 | $1,000.00 | $665.00 |
| 64 | Remove SM RD SN sup&AM (644-7073) | EACH | 12 | $120.00 | $96.80 | $93.50 | $121.00 | $100.00 | $500.00 | $110.00 |
| 65 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 848 | $15.00 | $29.54 | $23.10 | $23.10 | $35.00 | $40.00 | $2.00 |
| 66 | Prefabricated PM type C (W)(18")(yld tri) (668-7110) | EACH | 10 | $25.00 | $71.50 | $55.00 | $55.00 | $80.00 | $40.00 | $2.00 |
| 67 | Eliminating existing PM & markers (24") (677-7008) | LF | 1,297 | $4.00 | $4.40 | $13.20 | $13.20 | $6.00 | $15.00 | $1.00 |
| 68 | Install highway traffic signal (isolated) (680-7002) | EACH | 1 | $16,000 | $9,667.06 | $8,250.00 | $9,667.06 | $6,061.33 | $10,000 | $15,943 |
| 69 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 16 | $690.00 | $919.83 | $1,540.00 | $919.83 | $843.21 | $1,000.00 | $812.00 |
| 70 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 2,180 | $2.00 | $2.75 | $2.48 | $2.75 | $2.78 | $3.00 | $3.00 |
| 71 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 540 | $5.00 | $7.32 | $7.70 | $7.32 | $8.79 | $7.00 | $11.00 |
| 72 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 2,100 | $1.45 | $2.66 | $2.56 | $2.66 | $2.61 | $3.00 | $3.00 |
| 73 | Install RDSD flash beacon assembly (685-7001) | EACH | 2 | $5,580.00 | $5,311.19 | $8,250.00 | $5,311.19 | $11,428 | $5,500.00 | $10,629 |
| 74 | Pedestrian pole assembly (687-7001) | EACH | 16 | $2,150.00 | $2,599.28 | $3,300.00 | $2,599.28 | $4,863.34 | $3,000.00 | $3,124.00 |
| 75 | Pedestrian detect push button (APS) (688-7001) | EACH | 16 | $760.00 | $935.52 | $880.00 | $935.52 | $1,307.33 | $1,000.00 | $1,415.00 |
| 76 | Pedestrian detector controller unit (688-7003) | EACH | 2 | $3,500.00 | $4,244.31 | $5,940.00 | $4,244.31 | $5,538.31 | $4,500.00 | $7,054.43 |
| 77 | Shrub planting and removal (751-7009) | EACH | 5 | $250.00 | $275.00 | $82.50 | $82.50 | $1,000.00 | $100.00 | $500.00 |
| 78 | Spot tree trimming / brush removal (752-7002) | LF | 370 | $200.00 | $1.10 | $27.50 | $27.50 | $150.00 | $50.00 | $5.00 |
| 79 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 5 | $550.00 | $1,287.00 | $1,650.00 | $1,650.00 | $1,500.00 | $1,500.00 | $1,170.00 |
| 80 | Tree removal (18" - 24" diameter) (752-7007) | EACH | 1 | $1,000.00 | $1,980.00 | $2,750.00 | $2,750.00 | $2,700.00 | $2,500.00 | $1,800.00 |
| 81 | Tree removal (24" - 30" diameter) (752-7008) | EACH | 3 | $2,000.00 | $2,640.00 | $3,850.00 | $3,850.00 | $3,500.00 | $3,000.00 | $2,400.00 |
| 82 | Pedestrain illumination assembly (6099-7001) | EACH | 6 | $14,690 | $7,543.67 | $8,800.00 | $7,543.67 | $11,960 | $8,000.00 | $11,415 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 2, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.