TxDOT contract A00206966 bid tabulation
Construct Pedestrian Infrastructure, SH 5 (Newport Drive to Umphress Street). Let by Texas DOT on August 5, 2026, Grayson, Paris District. 10 bids received; low bid $993,246 by Xit Paving and Construction Inc., -16% against the engineer's estimate of $1,185,228.
- Owner
- Texas DOT
- Letting
- 05 AUG 2026
- Pay items
- 61
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Xit Paving and Construction Inc. | $993,246 | Low | -16% |
| 2 | Garret Shields Infrastructure | $1,028,214 | +4.0% | -13% |
| 3 | Scout 5 Construction LLC | $1,029,927 | +4.0% | -13% |
| 4 | Pace Construction Services LLC | $1,098,896 | +11% | -7.0% |
| 5 | Highway 19 Construction LLC | $1,132,589 | +14% | -4.0% |
| 6 | Texas Steel Industrial Placing, LLC | $1,165,169 | +17% | -2.0% |
| 7 | GHB Equipment Company, L.L.C. | $1,177,990 | +19% | -1.0% |
| 8 | Ratliff Hardscape, LTD. | $1,184,344 | +19% | 0.0% |
| 9 | Ti-Zack Concrete, LLC | $1,275,174 | +28% | +8.0% |
| 10 | Tight Line Construction, LLC | $1,665,425 | +68% | +41% |
Engineer's estimate: $1,185,228.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Xit Paving and Construction Inc. | 2. Garret Shields Infrastructure | 3. Scout 5 Construction LLC | 4. Pace Construction Services LLC | 5. Highway 19 Construction LLC | 6. Texas Steel Industrial Placing, LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 34 | $1,575.00 | $1,335.00 | $1,200.00 | $1,152.00 | $1,500.00 | $5,000.00 | $750.00 |
| 2 | Preparation row (tree remove) (0"-12" diameter) (100-7003) | EACH | 11 | $200.00 | $825.00 | $1,000.00 | $800.00 | $1,000.00 | $500.00 | $500.00 |
| 3 | Tree protection (install) (100-7014) | LF | 589 | $20.00 | $6.50 | $10.00 | $3.50 | $12.00 | $50.00 | $5.00 |
| 4 | Tree protection (remove) (100-7016) | LF | 589 | $20.00 | $3.00 | $5.00 | $1.50 | $10.00 | $10.00 | $2.00 |
| 5 | Removing concrete (driveways) (104-7011) | SY | 149 | $22.50 | $30.00 | $40.00 | $75.00 | $35.00 | $25.00 | $30.00 |
| 6 | Removing concrete (sidewalk, ramp or shared use path) (104-7013) | SY | 150 | $17.50 | $29.00 | $30.00 | $75.00 | $35.00 | $25.00 | $30.00 |
| 7 | Removing concrete (curb & gutter) (104-7017) | LF | 60 | $15.00 | $10.00 | $20.00 | $40.00 | $55.00 | $10.00 | $20.00 |
| 8 | Removing concrete (wingwall) (104-7028) | CY | 8 | $420.00 | $150.00 | $500.00 | $1,000.00 | $2,200.00 | $125.00 | $550.00 |
| 9 | Remove (16"-20") TRT/untrt base & asphalt pavement (105-7016) | SY | 505 | $75.00 | $52.00 | $40.00 | $15.00 | $50.00 | $15.00 | $30.00 |
| 10 | Remove (0"-8") TRT/untrt base & asphalt pavement (105-7048) | SY | 598 | $6.50 | $23.00 | $30.00 | $37.05 | $23.00 | $15.00 | $18.00 |
| 11 | Excavation (roadway) (110-7001) | CY | 255 | $12.00 | $25.00 | $40.00 | $25.00 | $25.00 | $25.00 | $35.00 |
| 12 | Embankment (final)(OC)(type B) (132-7003) | CY | 1,568 | $25.00 | $35.00 | $30.00 | $25.00 | $30.00 | $30.00 | $35.00 |
| 13 | Broadcast seed (permanent_rural_clay) (164-7002) | SY | 6,738 | $0.50 | $0.35 | $0.10 | $0.39 | $0.50 | $1.00 | $0.49 |
| 14 | Broadcast seed (temporary_warm_cool) (164-7007) | SY | 6,738 | $0.15 | $0.35 | $0.10 | $0.34 | $0.50 | $1.00 | $0.21 |
| 15 | Vegetative watering (168-7001) | TGL | 65 | $5.00 | $115.00 | $25.00 | $26.00 | $93.00 | $100.00 | $50.00 |
| 16 | Cut & restoring pavement (400-7006) | SY | 32 | $150.00 | $150.00 | $120.00 | $169.00 | $91.00 | $350.00 | $200.00 |
| 17 | Flowable backfill (401-7001) | CY | 343.90 | $290.00 | $250.00 | $250.00 | $218.08 | $200.00 | $250.00 | $250.00 |
| 18 | Class C concrete (miscellaneous) (420-7067) | CY | 1.75 | $1,500.00 | $1,900.00 | $1,000.00 | $4,550.00 | $7.00 | $5,000.00 | $1,100.00 |
| 19 | Riprap (concrete)(5 in) (432-7002) | CY | 2 | $875.00 | $800.00 | $600.00 | $871.65 | $260.00 | $1,000.00 | $1,000.00 |
| 20 | Riprap (stone common)(dry)(12 in) (432-7031) | CY | 72 | $200.00 | $220.00 | $200.00 | $152.50 | $300.00 | $180.00 | $200.00 |
| 21 | STR steel (miscellaneous non-bridge) (442-7007) | LB | 2,750 | $3.50 | $6.50 | $10.00 | $6.01 | $7.00 | $17.00 | $25.00 |
| 22 | Rail (type PR11) (450-7044) | LF | 38 | $170.00 | $266.00 | $200.00 | $214.06 | $260.00 | $250.00 | $247.17 |
| 23 | Rail (handrail)(type F) (450-7063) | LF | 30 | $135.00 | $300.00 | $250.00 | $244.92 | $260.00 | $180.00 | $327.45 |
| 24 | Concrete box culvert (3 FT X 2 FT)(extend) (462-7056) | LF | 4.25 | $650.00 | $1,400.00 | $500.00 | $857.45 | $1,800.00 | $1,000.00 | $1,500.00 |
| 25 | RC pipe (CL III)(24 in) (464-7005) | LF | 112 | $100.00 | $150.00 | $120.00 | $94.90 | $145.00 | $110.00 | $100.00 |
| 26 | Inlet (comp)(type sidewalk bridge) (465-7336) | EACH | 9 | $18,000 | $12,300 | $5,000.00 | $2,449.70 | $5,000.00 | $1,000.00 | $12,500 |
| 27 | Inlet (complete)(type sidewalk bridge)(mod) (465-7374) | EACH | 1 | $17,000 | $12,700 | $10,000 | $2,585.00 | $6,000.00 | $5,000.00 | $17,500 |
| 28 | Wingwall (PW - 1) (HW=4 FT) (466-7174) | EACH | 1 | $15,000 | $12,830 | $8,000.00 | $10,826 | $10,000 | $12,000 | $12,500 |
| 29 | Set (type II) (24 in) (RCP) (4: 1) (C) (467-7326) | EACH | 2 | $1,500.00 | $3,951.00 | $2,500.00 | $2,617.50 | $4,500.00 | $1,100.00 | $1,800.00 |
| 30 | Removing structure (set) (496-7004) | EACH | 2 | $650.00 | $760.00 | $500.00 | $1,000.00 | $1,200.00 | $500.00 | $500.00 |
| 31 | Removing structure (pipe) (496-7007) | LF | 90 | $20.00 | $27.00 | $20.00 | $50.00 | $84.00 | $50.00 | $30.00 |
| 32 | Remove STR (bollard) (496-7028) | EACH | 4 | $450.00 | $100.00 | $100.00 | $100.00 | $540.00 | $1,000.00 | $400.00 |
| 33 | Mobilization (500-7001) | LS | 1 | $108,038 | $39,000 | $100,000 | $100,000 | $50,000 | $100,000 | $116,609 |
| 34 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $11,000 | $2,600.00 | $5,000.00 | $1,794.88 | $6,000.00 | $5,000.00 | $2,000.00 |
| 35 | Portable changeable message sign (503-7002) | EACH | 3 | $11,000 | $4,125.00 | $1,000.00 | $46,667 | $1,500.00 | $5,000.00 | $30,000 |
| 36 | TMA (stationary) (505-7001) | DAY | 120 | $250.00 | $115.00 | $300.00 | $0.01 | $300.00 | $250.00 | $200.00 |
| 37 | Rock filter dams (install) (type 2) (506-7002) | LF | 56 | $50.00 | $63.00 | $20.00 | $71.50 | $75.00 | $43.00 | $63.70 |
| 38 | Rock filter dams (remove) (506-7011) | LF | 56 | $15.00 | $5.00 | $5.00 | $16.50 | $25.00 | $10.00 | $39.70 |
| 39 | Temporary sediment control fence (install) (506-7039) | LF | 310 | $4.50 | $4.00 | $5.00 | $500.00 | $6.00 | $4.00 | $3.15 |
| 40 | Temporary sediment control fence (remove) (506-7041) | LF | 310 | $1.75 | $1.00 | $1.00 | $1.50 | $3.00 | $1.00 | $0.72 |
| 41 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 240 | $5.50 | $7.00 | $5.00 | $50.00 | $7.00 | $5.00 | $4.18 |
| 42 | Biodegradable erosion control logs (remove) (506-7046) | LF | 240 | $1.20 | $1.00 | $1.00 | $1.50 | $2.00 | $1.00 | $0.72 |
| 43 | Concrete curb (mono) (type I) (529-7006) | LF | 200 | $34.00 | $5.00 | $40.00 | $11.27 | $30.00 | $35.00 | $30.00 |
| 44 | Concrete curb & gutter (type II) (529-7009) | LF | 2,183 | $34.00 | $34.00 | $35.00 | $17.00 | $40.00 | $35.00 | $40.00 |
| 45 | Concrete curb (ribbon) (529-7028) | LF | 48 | $28.00 | $38.00 | $40.00 | $29.39 | $125.00 | $100.00 | $75.00 |
| 46 | Intrsct, drvways, & turnout (concrete) (530-7021) | SY | 511 | $150.00 | $143.00 | $125.00 | $62.88 | $100.00 | $110.00 | $120.00 |
| 47 | Intrsct, drvways, & turnout (ACP) (530-7022) | SY | 205 | $80.00 | $113.00 | $120.00 | $66.30 | $250.00 | $85.00 | $40.00 |
| 48 | Concrete sidewalks (5") (531-7002) | SY | 2,451 | $75.00 | $75.00 | $90.00 | $20.21 | $100.00 | $85.00 | $75.00 |
| 49 | Curb ramps (type 1) (531-7015) | SY | 7 | $250.00 | $200.00 | $300.00 | $169.00 | $350.00 | $100.00 | $140.00 |
| 50 | Curb ramps (type 6) (531-7019) | SY | 28 | $250.00 | $130.00 | $300.00 | $42.70 | $350.00 | $100.00 | $140.00 |
| 51 | Curb ramps (type 7) (531-7020) | SY | 33 | $250.00 | $212.00 | $300.00 | $91.59 | $350.00 | $100.00 | $140.00 |
| 52 | Curb ramps (type 21) (531-7023) | SY | 12 | $250.00 | $187.00 | $300.00 | $140.83 | $350.00 | $100.00 | $140.00 |
| 53 | Concrete median (536-7002) | SY | 47 | $105.00 | $80.00 | $120.00 | $105.10 | $80.00 | $250.00 | $350.00 |
| 54 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $675.00 | $767.00 | $800.00 | $395.11 | $900.00 | $850.00 | $669.00 |
| 55 | Relocate SM RD SN sup&AM type 10BWG (644-7065) | EACH | 6 | $440.00 | $767.00 | $500.00 | $320.50 | $900.00 | $250.00 | $669.00 |
| 56 | Remove SM RD SN sup&AM (644-7073) | EACH | 1 | $350.00 | $113.00 | $500.00 | $100.00 | $500.00 | $100.00 | $99.00 |
| 57 | Reflectorized pavement marking type I (W)24"(solid)(090MIL) (666-7035) | LF | 242 | $15.00 | $14.00 | $17.00 | $18.20 | $18.00 | $20.00 | $10.00 |
| 58 | Pavement sler 24" (666-7352) | LF | 242 | $3.00 | $1.50 | $2.50 | $2.47 | $3.00 | $5.00 | $3.00 |
| 59 | Eliminating existing PM & markers (4") (677-7001) | LF | 115 | $2.00 | $1.00 | $2.50 | $2.60 | $3.00 | $10.00 | $5.00 |
| 60 | Relocate RDSD flash beacon assembly (685-7002) | EACH | 1 | $5,000.00 | $10,000 | $5,000.00 | $10,000 | $18,000 | $5,000.00 | $5,000.00 |
| 61 | Removable bollard (5005-7001) | EACH | 4 | $1,500.00 | $1,700.00 | $1,000.00 | $20,000 | $1,200.00 | $100.00 | $1,989.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of August 5, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way