TxDOT contract A00209701 bid tabulation
Bridge Maintenance, SH 19 (At Lake Creek to .). Let by Texas DOT on January 6, 2026, Delta, Paris District. 10 bids received; low bid $2,541,166 by Gibson & Associates, Inc., -35% against the engineer's estimate of $3,883,588.
- Owner
- Texas DOT
- Letting
- 06 JAN 2026
- Pay items
- 49
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gibson & Associates, Inc. | $2,541,166 | Low | -35% |
| 2 | THK Construction LLC | $3,089,143 | +22% | -20% |
| 3 | Garret Shields Infrastructure | $3,123,897 | +23% | -20% |
| 4 | Ragle Construction, Inc. | $3,139,758 | +24% | -19% |
| 5 | Structural Integrity Group LLC | $3,471,207 | +37% | -11% |
| 6 | Highway 19 Construction LLC | $3,516,108 | +38% | -9.0% |
| 7 | Built Right Construction of Oklahoma, LLC | $3,673,691 | +45% | -5.0% |
| 8 | Hodges and Son Construction Company, Inc. | $4,032,711 | +59% | +4.0% |
| 9 | Rise Up Construction LLC | $4,040,051 | +59% | +4.0% |
| 10 | Grey Sky Construction LLC | $4,438,679 | +75% | +14% |
Engineer's estimate: $3,883,588.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Gibson & Associates, Inc. | 2. THK Construction LLC | 3. Garret Shields Infrastructure | 4. Ragle Construction, Inc. | 5. Structural Integrity Group LLC | 6. Highway 19 Construction LLC |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7007) | CY | 32.30 | $370.00 | $50.00 | $50.00 | $150.00 | $340.00 | $50.00 | |
| 2 | Planing asphalt concrete pavement(2") (354-7051) | SY | 98 | $50.00 | $150.00 | $20.00 | $17.00 | $95.00 | $110.00 | |
| 3 | Flowable backfill (401-7001) | CY | 7.40 | $750.00 | $1,250.00 | $1,500.00 | $300.00 | $490.00 | $650.00 | $350.00 |
| 4 | Class B concrete (flume) (420-7010) | CY | 19 | $1,000.00 | $1,820.00 | $850.00 | $800.00 | $690.00 | $825.00 | $1,000.00 |
| 5 | Penetrating concrete surface treatment (428-7001) | SY | 534 | $20.00 | $37.40 | $15.00 | $10.00 | $18.00 | $18.00 | $44.00 |
| 6 | Concrete structure repair(clean & coat WTH epoxy) (429-7001) | SF | 34 | $175.00 | $143.00 | $250.00 | $250.00 | $300.00 | $125.00 | $347.00 |
| 7 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 3,551 | $200.00 | $5.00 | $170.00 | $150.00 | $10.00 | $118.00 | $160.00 |
| 8 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 98 | $250.00 | $154.00 | $150.00 | $200.00 | $300.00 | $380.00 | $350.00 |
| 9 | Concrete structure repair (pan girder hole repair) (429-7010) | EACH | 110 | $335.00 | $150.00 | $250.00 | $300.00 | $160.00 | $75.00 | $100.00 |
| 10 | Riprap (stone protection)(18 in) (432-7043) | CY | 386.90 | $275.00 | $231.00 | $200.00 | $300.00 | $185.00 | $320.00 | $180.00 |
| 11 | Cleaning and sealing existing joints (CL3) (438-7004) | LF | 216 | $15.40 | $34.56 | $50.00 | $18.00 | $32.00 | $75.00 | |
| 12 | Cleaning and sealing existing joints (CL7) (438-7007) | LF | 1,059 | $75.00 | $33.00 | $51.84 | $40.00 | $23.00 | $48.00 | $75.00 |
| 13 | Concrete overlay (2 in) (439-7002) | SY | 2,520 | $94.00 | $45.00 | $50.00 | $185.00 | $95.00 | $120.00 | |
| 14 | Polyester polymer concrete overlay (3/4") (439-7015) | SY | 5,372 | $150.00 | $110.00 | $142.00 | $140.00 | $185.00 | $115.75 | $155.00 |
| 15 | STR steel (miscellaneous bridge) (442-7008) | LB | 4,530 | $12.50 | $7.00 | $30.00 | $8.00 | $16.00 | $32.00 | |
| 16 | Hydro-demolition (2 in) (483-7010) | SY | 2,520 | $115.00 | $88.50 | $75.00 | $105.00 | $110.00 | $80.00 | |
| 17 | Mobilization (500-7001) | LS | 1 | $352,000 | $272,000 | $285,000 | $300,000 | $310,000 | $322,000 | $400,000 |
| 18 | Barricades, signs and traffic handling (502-7001) | MO | 12 | $5,500.00 | $14,250 | $7,000.00 | $5,000.00 | $25,000 | $8,800.00 | $5,000.00 |
| 19 | Portable changeable message sign (503-7001) | DAY | 227 | $150.00 | $66.00 | $100.00 | $100.00 | $65.00 | $50.00 | $100.00 |
| 20 | TMA (stationary) (505-7001) | DAY | 148 | $300.00 | $250.00 | $300.00 | $300.00 | $100.00 | $1.00 | $250.00 |
| 21 | TMA (mobile operation) (505-7003) | DAY | 35 | $400.00 | $100.00 | $300.00 | $300.00 | $500.00 | $1.00 | $1,000.00 |
| 22 | Temporary sediment control fence (install) (506-7039) | LF | 4,990 | $6.00 | $4.26 | $4.32 | $5.00 | $4.50 | $4.00 | $4.00 |
| 23 | Temporary sediment control fence (remove) (506-7041) | LF | 4,990 | $2.00 | $1.27 | $0.70 | $1.00 | $1.50 | $0.65 | $1.00 |
| 24 | One-way traffic control (flagger cont) (510-7001) | HR | 216 | $30.00 | $33.00 | $40.00 | $450.00 | $88.00 | $150.00 | |
| 25 | Portable concrete traffic barrier (furnish and install)(single slope)(type 1) (512-7001) | LF | 2,130 | $35.00 | $10.00 | $90.00 | $80.00 | $58.00 | $61.00 | $97.00 |
| 26 | Portable concrete traffic barrier (move)(single slope)(type 1) (512-7025) | LF | 2,130 | $15.00 | $5.00 | $10.00 | $20.00 | $10.00 | $19.50 | $25.00 |
| 27 | Portable concrete traffic barrier (remove)(single slope)(type 1) (512-7049) | LF | 2,130 | $20.00 | $5.00 | $25.00 | $20.00 | $15.00 | $110.00 | $25.00 |
| 28 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 5 | $2,500.00 | $500.00 | $2,160.00 | $1,000.00 | $1,050.00 | $1,500.00 | $2,500.00 |
| 29 | Crash cushion attenuator (remove) (545-7004) | EACH | 5 | $1,500.00 | $500.00 | $864.00 | $500.00 | $1,050.00 | $1,250.00 | $1,500.00 |
| 30 | Crash cushion attenuator (install)(S)(W)(TL3) (545-7016) | EACH | 5 | $15,000 | $3,000.00 | $9,180.00 | $8,000.00 | $7,100.00 | $10,500 | $5,000.00 |
| 31 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 44 | $20.00 | $30.00 | $10.00 | $15.00 | $20.00 | $10.00 | |
| 32 | RE PV marking type I(black)6"(shadow)(100MIL) (666-7138) | LF | 200 | $2.00 | $5.50 | $5.40 | $3.75 | $5.00 | $2.00 | $5.00 |
| 33 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 200 | $0.50 | $2.20 | $2.16 | $0.50 | $2.00 | $0.50 | $2.00 |
| 34 | Reflectorized pavement marking type II (W) 6" (solid) (666-7175) | LF | 5,100 | $0.50 | $1.10 | $1.08 | $2.00 | $1.00 | $0.50 | $1.00 |
| 35 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 2,080 | $0.50 | $1.10 | $1.08 | $2.00 | $1.00 | $0.50 | $1.00 |
| 36 | Pavement sler 6" (666-7347) | LF | 7,580 | $0.30 | $1.10 | $1.08 | $0.60 | $1.00 | $0.50 | $1.00 |
| 37 | Reflectorized pavement marker type I-A (672-7001) | EACH | 32 | $7.00 | $11.00 | $10.80 | $8.00 | $10.00 | $7.00 | $10.00 |
| 38 | Reflectorized pavement marker type I-C (672-7002) | EACH | 653 | $4.00 | $5.50 | $5.40 | $8.00 | $5.00 | $7.00 | $5.00 |
| 39 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 855 | $5.50 | $5.40 | $8.00 | $5.00 | $7.00 | $5.00 | |
| 40 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 93 | $5.00 | $11.00 | $10.80 | $8.00 | $10.00 | $7.00 | $10.00 |
| 41 | Traffic button type W (672-7007) | EACH | 3,772 | $3.00 | $3.85 | $3.78 | $6.00 | $3.50 | $5.00 | $3.50 |
| 42 | Traffic button type Y (672-7008) | EACH | 847 | $3.00 | $5.50 | $5.40 | $6.00 | $5.00 | $5.00 | $5.00 |
| 43 | Eliminating existing PM & markers (6") (677-7002) | LF | 1,120 | $2.00 | $1.10 | $1.08 | $1.10 | $1.00 | $1.00 | $1.00 |
| 44 | Eliminating existing PM & markers (6") (callout) (677-7033) | LF | 6,460 | $1.10 | $1.08 | $1.10 | $1.00 | $0.75 | $1.00 | |
| 45 | Pavement surface preparation for marking (6") (678-7002) | LF | 7,580 | $0.50 | $0.55 | $0.54 | $1.10 | $0.50 | $0.40 | $0.50 |
| 46 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 6,250 | $1.75 | $0.55 | $0.54 | $0.60 | $0.50 | $3.00 | $0.50 |
| 47 | Driftwood removal (735-7060) | CY | 5,948 | $100.00 | $72.60 | $25.00 | $40.00 | $10.00 | $87.00 | $25.00 |
| 48 | Concrete beam repair (788-7001) | EACH | 7 | $1,200.00 | $10,000 | $4,000.00 | $3,500.00 | $1,250.00 | $1,000.00 | |
| 49 | Concrete beam rep (strand splice) (788-7004) | EACH | 1 | $5,600.00 | $25,000 | $5,000.00 | $5,000.00 | $9,000.00 | $3,300.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of January 6, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way