TxDOT contract A00210173 bid tabulation
Bridge Maintenance, US 87 (1.95 mi south of FM 145 to On US 87). Let by Texas DOT on June 3, 2026, Swisher, Lubbock District. 9 bids received; low bid $2,742,796 by Pathfield Investments LLC, -12% against the engineer's estimate of $3,132,948.
- Owner
- Texas DOT
- Letting
- 03 JUN 2026
- Pay items
- 47
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Pathfield Investments LLC | $2,742,796 | Low | -12% |
| 2 | Ragle Construction, Inc. | $2,868,974 | +5.0% | -8.0% |
| 3 | Built Right Construction of Oklahoma, LLC | $2,969,473 | +8.0% | -5.0% |
| 4 | Coppell Construction Co., Inc. | $3,041,557 | +11% | -3.0% |
| 5 | Ti-Zack Concrete, LLC | $3,174,151 | +16% | +1.0% |
| 6 | Gibson & Associates, Inc. | $3,517,903 | +28% | +12% |
| 7 | Premier Contractors LLC | $4,474,203 | +63% | +43% |
| 8 | Hodges and Son Construction Company, Inc. | $4,592,854 | +67% | +47% |
| 9 | Concrete Strategies LLC | $4,908,739 | +79% | +57% |
Engineer's estimate: $3,132,948.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Pathfield Investments LLC | 2. Ragle Construction, Inc. | 3. Built Right Construction of Oklahoma, LLC | 4. Coppell Construction Co., Inc. | 5. Ti-Zack Concrete, LLC | 6. Gibson & Associates, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 30 | $200.00 | $45.00 | $20.00 | $130.00 | $64.90 | $50.00 | |
| 2 | Removing concrete (appr slab) (104-7030) | SY | 333 | $50.20 | $70.00 | $49.50 | $20.00 | $75.00 | $29.50 | $270.00 |
| 3 | Removing concrete (flume) (104-7041) | SY | 10 | $190.00 | $75.00 | $20.00 | $200.00 | $64.90 | $50.00 | |
| 4 | Planing asphalt concrete pavement(2") (354-7051) | SY | 3,552 | $10.80 | $12.00 | $7.00 | $15.00 | $10.00 | $10.62 | $17.33 |
| 5 | Planing asphalt concrete pavement(3") (354-7052) | SY | 1,734 | $14.00 | $8.50 | $34.00 | $24.00 | $12.98 | $46.20 | |
| 6 | Flowable backfill (401-7001) | CY | 125 | $500.00 | $200.00 | $400.00 | $360.00 | $536.90 | $605.00 | |
| 7 | Approach slab (422-7013) | CY | 140.25 | $750.00 | $900.00 | $710.00 | $750.00 | $1,000.00 | $79.06 | $1,450.00 |
| 8 | Penetrating concrete surface treatment (428-7001) | SY | 1,000 | $22.50 | $20.00 | $15.00 | $10.00 | $28.00 | $135.70 | $16.50 |
| 9 | Concrete structure repair(deck rep(part depth)) (429-7003) | SF | 350 | $90.00 | $170.00 | $55.00 | $325.00 | $150.00 | $206.50 | $58.00 |
| 10 | Concrete structure repair(deck rep (full depth)) (429-7005) | SF | 1,250 | $150.00 | $190.00 | $80.00 | $365.00 | $80.00 | $247.80 | $80.00 |
| 11 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 610 | $170.00 | $180.00 | $150.00 | $265.00 | $275.00 | $260.78 | $198.00 |
| 12 | Riprap (concrete)(5 in) (432-7002) | CY | 35 | $920.00 | $600.00 | $600.00 | $900.00 | $1,121.00 | $1,010.00 | |
| 13 | Riprap (concrete)(flume) (432-7012) | CY | 4 | $2,060.00 | $735.00 | $600.00 | $1,200.00 | $1,178.82 | $1,100.00 | |
| 14 | Latex - modified concrete overlay (2 in) (439-7007) | SY | 1,500 | $150.00 | $180.00 | $150.00 | $105.00 | $145.00 | $135.70 | $155.00 |
| 15 | Polyester polymer concrete overlay (439-7025) | CY | 249 | $2,900.00 | $2,950.00 | $3,200.00 | $3,000.00 | $3,776.00 | $3,725.00 | |
| 16 | Miscellaneous non-bridge (nbis) (442-7017) | LB | 9.20 | $160.00 | $400.00 | $150.00 | $50.00 | $225.00 | $1,770.00 | $100.00 |
| 17 | Hydro-demolition (1/2 in) (483-7006) | SY | 1,500 | $95.00 | $40.00 | $125.00 | $75.00 | $105.00 | $136.85 | $145.00 |
| 18 | Micromilling concrete slab (1 in) (483-7022) | SY | 1,500 | $35.00 | $10.00 | $12.00 | $14.00 | $15.00 | $41.24 | $12.10 |
| 19 | Mobilization (500-7001) | LS | 1 | $290,000 | $250,000 | $280,000 | $200,000 | $285,000 | $64,900 | $332,000 |
| 20 | Barricades, signs and traffic handling (502-7001) | MO | 9 | $4,500.00 | $1.00 | $30,000 | $5,400.00 | $16,000 | $7,670.00 | $14,400 |
| 21 | Portable changeable message sign (503-7001) | DAY | 437 | $117.00 | $1.00 | $55.00 | $50.00 | $200.00 | $64.90 | $40.00 |
| 22 | TMA (stationary) (505-7001) | DAY | 227 | $184.50 | $1.00 | $100.00 | $300.00 | $330.00 | $195.88 | $200.00 |
| 23 | TMA (mobile operation) (505-7003) | DAY | 20 | $225.00 | $1.00 | $550.00 | $300.00 | $500.00 | $295.00 | $500.00 |
| 24 | Sandbags for erosion control (506-7035) | EACH | 300 | $10.30 | $20.00 | $12.00 | $12.00 | $23.00 | $8.26 | $22.00 |
| 25 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 160 | $5.38 | $40.00 | $7.50 | $8.00 | $12.00 | $10.62 | $14.00 |
| 26 | Portable concrete traffic barrier (des source)(F-shape)(type 1) (512-7017) | LF | 420 | $121.50 | $50.00 | $200.00 | $50.00 | $37.00 | $88.50 | $62.00 |
| 27 | Portable concrete traffic barrier (move)(F-shape)(type 1) (512-7029) | LF | 1,500 | $27.00 | $35.00 | $15.00 | $30.00 | $30.00 | $41.30 | $34.00 |
| 28 | Portable concrete traffic barrier (stockpile)(F-shape)(type 1) (512-7041) | LF | 420 | $45.00 | $60.00 | $15.00 | $30.00 | $30.00 | $88.50 | $38.50 |
| 29 | Crash cushion attenuator (move & reset) (545-7002) | EACH | 6 | $3,150.00 | $1,700.00 | $1,150.00 | $2,000.00 | $2,500.00 | $11,210 | $1,250.00 |
| 30 | Crash cushion attenuator (remove) (545-7004) | EACH | 2 | $2,475.00 | $4,000.00 | $950.00 | $1,300.00 | $2,000.00 | $6,490.00 | $500.00 |
| 31 | Crash cushion attenuator (install)(S)(N)(TL3) (545-7014) | EACH | 2 | $11,250 | $11,000 | $8,000.00 | $9,000.00 | $10,000 | $11,210 | $10,200 |
| 32 | Work zone pavement marking removing (W)24"(solid) (662-7077) | LF | 70 | $22.50 | $28.00 | $25.00 | $30.00 | $25.00 | $29.50 | $27.50 |
| 33 | Reflectorized pavement marking type II (W) 4" (solid) (666-7171) | LF | 2,390 | $1.20 | $3.00 | $3.00 | $3.60 | $3.00 | $3.54 | $3.30 |
| 34 | Reflectorized pavement marking type II (W) 6" (broken) (666-7172) | LF | 120 | $7.00 | $1.50 | $3.60 | $3.00 | $3.54 | $3.30 | |
| 35 | Reflectorized pavement marking type II (Y) 6" (solid) (666-7213) | LF | 2,390 | $0.35 | $2.00 | $1.50 | $3.60 | $3.00 | $3.54 | $3.30 |
| 36 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 76 | $8.00 | $15.00 | $66.00 | $55.00 | $64.90 | $60.50 | |
| 37 | Reflectorized pavement marker type II-C-C (672-7005) | EACH | 36 | $13.50 | $10.00 | $15.00 | $66.00 | $55.00 | $64.90 | $60.50 |
| 38 | Reflectorized pavement marker type II-C-R (672-7006) | EACH | 36 | $10.00 | $15.00 | $66.00 | $55.00 | $64.90 | $60.50 | |
| 39 | Traffic button type W (672-7007) | EACH | 192 | $3.60 | $4.00 | $10.00 | $66.00 | $55.00 | $64.90 | $60.50 |
| 40 | Traffic button type Y (672-7008) | EACH | 84 | $8.00 | $10.00 | $66.00 | $55.00 | $64.90 | $60.50 | |
| 41 | Temporary traffic signals (681-7001) | EACH | 1 | $36,000 | $8,000.00 | $125,000 | $30,000 | $40,000 | $17,700 | $5,000.00 |
| 42 | Litter removal (734-7002) | CYC | 4 | $1,700.98 | $2,700.00 | $250.00 | $500.00 | $1,000.00 | $2,478.00 | $500.00 |
| 43 | Concrete rail repair (in-kind) (778-7001) | LF | 80 | $360.00 | $700.00 | $150.00 | $300.00 | $620.00 | $470.82 | $165.00 |
| 44 | Bridge joint replacement (armor) (785-7010) | LF | 873 | $275.00 | $310.00 | $230.00 | $225.00 | $232.00 | $160.48 | $569.00 |
| 45 | Carbon fiber reinforced polymer protection (786-7001) | SF | 400 | $135.00 | $140.00 | $75.00 | $75.00 | $125.00 | $112.10 | $77.00 |
| 46 | Replacing elastomeric bearing pads (787-7001) | EACH | 10 | $7,000.00 | $12,000 | $4,000.00 | $10,000 | $11,210 | $4,400.00 | |
| 47 | Abate asbestos (coatings) (5009-7001) | SF | 300 | $90.00 | $45.00 | $35.00 | $30.00 | $34.42 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 3, 2026. Compiled by Mirage Metrics.