Removing concrete (pavement), TxDOT 104-6001
Low bidders on TxDOT contracts carried a median of $11.22 per SY for this item, over the 24 months to 19 NOV 2026, across 2 low bids. Half of all 6 bids fell between $10.20 and $12.08.
- Owner
- Texas DOT
- Item
- 104-6001
- Unit
- SY
- Data through
- 19 NOV 2026
TxDOT prints this item as “REMOVING CONC (PAV)”.
TxDOT has bid this work under more than one code: 1046001 on lettings from 10 JAN 2020 to 02 AUG 2024 (1,492 bids); 104-6001 on lettings from 07 JAN 2025 to 07 FEB 2025 (6 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 64 | 64 | $12.20 | 389 | $14.00 |
| 2021 | 82 | 81 | $14.47 | 393 | $14.61 |
| 2022 | 56 | 56 | $17.00 | 253 | $18.70 |
| 2023 | 70 | 70 | $20.75 | 231 | $21.00 |
| 2024 | 60 | 60 | $20.15 | 224 | $20.26 |
| 2025 | 2 | 2 | $11.22 | 6 | $10.89 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Houston District | 71 | $9.00 | 377 | $10.00 |
| Dallas District | 65 | $16.50 | 339 | $15.00 |
| Fort Worth District | 23 | $13.60 | 118 | $13.65 |
| Bryan District | 13 | $15.00 | 61 | $20.00 |
| Yoakum District | 17 | $19.89 | 58 | $20.77 |
| San Antonio District | 12 | $16.25 | 58 | $20.00 |
| El Paso District | 15 | $21.00 | 54 | $25.00 |
| Lufkin District | 11 | $29.00 | 44 | $27.00 |
| Waco District | 10 | $20.79 | 42 | $23.10 |
| Austin District | 11 | $27.00 | 37 | $19.95 |
| Beaumont District | 9 | $12.00 | 34 | $12.00 |
| Laredo District | 10 | $31.31 | 33 | $28.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (SY) | Low bids | Low-bid median |
|---|---|---|
| 4 to 193 | 83 | $43.00 |
| 197 to 1,110 | 83 | $21.00 |
| 1,131 to 10,438 | 83 | $10.61 |
| 10,486 to 619,929 | 84 | $7.32 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Webber, LLC | 88 | 31 (35%) |
| James Construction Group, LLC | 53 | 16 (30%) |
| FNH Construction, LLC | 48 | 16 (33%) |
| Harper Brothers Construction LLC | 38 | 13 (34%) |
| Altus Construction LLC | 25 | 13 (52%) |
| Zachry Construction Corporation | 41 | 9 (22%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 FEB 2025 | A00132721 | Dallas District | 243,507 | $10.00 | $13.90 | $15.00 | 2 | Balfour Beatty Infrastructure, Inc. | TxDOT |
| 07 JAN 2025 | A00064247 | Austin District | 43,721 | $12.45 | $10.89 | $9.50 | 4 | Webber, LLC | TxDOT |
| 02 AUG 2024 | 08243202 | Houston District | 14,644 | $5.97 | $4.70 | $10.50 | 4 | James Construction Group, LLC | TxDOT |
| 01 AUG 2024 | 08243001 | Houston District | 146,944 | $1.19 | $8.10 | $12.00 | 2 | Webber, LLC | TxDOT |
| 10 JUL 2024 | 07243201 | Dallas District | 231,614 | $12.60 | $11.50 | $3.85 | 2 | Austin Bridge & Road Services, LP | TxDOT |
| 10 JUL 2024 | 07243207 | Dallas District | 2,837 | $10.00 | $10.59 | $30.00 | 6 | Harper Brothers Construction LLC | TxDOT |
| 10 JUL 2024 | 07243220 | Houston District | 100 | $32.00 | $45.79 | $25.00 | 4 | Statewide Traffic Signal Company | TxDOT |
| 10 JUL 2024 | 07243229 | San Angelo District | 65 | $136.00 | $74.00 | $30.00 | 8 | Talbert Companies LLC | TxDOT |
| 09 JUL 2024 | 07243001 | Fort Worth District | 123,508 | $10.00 | $8.72 | $12.20 | 2 | Zachry Construction Corporation | TxDOT |
| 09 JUL 2024 | 07243002 | El Paso District | 74,423 | $12.00 | $26.00 | $25.00 | 2 | Sundt Construction, Inc. | TxDOT |
| 09 JUL 2024 | 07243012 | Houston District | 16 | $1,000.00 | $1,000.00 | $35.15 | 1 | MC2 Civil, LLC | TxDOT |
| 09 JUL 2024 | 07243014 | Houston District | 90 | $31.00 | $44.50 | $15.00 | 2 | Statewide Traffic Signal Company | TxDOT |
| 09 JUL 2024 | 07243018 | Bryan District | 89 | $36.00 | $48.00 | $13.00 | 4 | Larry Young Paving, Inc. | TxDOT |
| 06 JUN 2024 | 06243202 | Houston District | 1,142 | $10.00 | $10.00 | $12.09 | 3 | Harper Brothers Construction LLC | TxDOT |
| 06 JUN 2024 | 06243203 | Houston District | 7,658 | $4.65 | $7.33 | $3.10 | 2 | James Construction Group, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.