Set (type I)(S= 5 FT)(HW= 3 FT)(4:1) (C), TxDOT 467-6172
Low bidders on TxDOT contracts carried a median of $7,975.00 per EACH for this item, from 09 JAN 2020 to 05 JUN 2024, across 64 low bids. Half of all 276 bids fell between $6,696.50 and $11,200.
- Owner
- Texas DOT
- Item
- 467-6172
- Unit
- EACH
- Data through
- 19 NOV 2026
TxDOT prints this item as “SET (TY I)(S= 5 FT)(HW= 3 FT)(4:1) (C)”.
TxDOT has bid this work under another code: 4676172 on lettings from 09 JAN 2020 to 05 JUN 2024 (276 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 14 | 14 | $5,737.51 | 70 | $6,784.50 |
| 2021 | 16 | 16 | $7,665.00 | 79 | $8,415.00 |
| 2022 | 9 | 9 | $7,750.00 | 30 | $8,550.00 |
| 2023 | 16 | 16 | $9,010.26 | 60 | $10,442 |
| 2024 | 9 | 9 | $9,537.26 | 37 | $10,000 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Yoakum District | 12 | $8,200.00 | 41 | $8,422.69 |
| Corpus Christi District | 7 | $6,100.00 | 39 | $7,000.00 |
| Abilene District | 8 | $8,084.50 | 37 | $8,415.00 |
| Amarillo District | 8 | $10,211 | 29 | $10,875 |
| Houston District | 5 | $5,788.04 | 29 | $9,440.90 |
| Odessa District | 5 | $5,600.70 | 27 | $6,000.00 |
| San Antonio District | 4 | $8,933.12 | 19 | $7,420.00 |
| Wichita Falls District | 3 | $8,600.00 | 10 | $8,450.00 |
| Lubbock District | 3 | $8,900.00 | 9 | $8,900.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 16 | $7,550.00 |
| 2 to 3 | 16 | $8,835.00 |
| 3 to 6 | 16 | $7,408.00 |
| 6 to 20 | 16 | $8,000.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Hunter Industries, LTD. | 16 | 4 (25%) |
| James Construction Group, LLC | 10 | 4 (40%) |
| RK Hall, LLC | 13 | 3 (23%) |
| A. L. Helmcamp, Inc. | 11 | 3 (27%) |
| J. Lee Milligan, Inc. | 8 | 3 (38%) |
| Kiewit Infrastructure South Co. | 8 | 3 (38%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 05 JUN 2024 | 06243016 | Beaumont District | 4 | $13,000 | $12,000 | $9,600.00 | 3 | Texas Materials Group, Inc. | TxDOT |
| 03 MAY 2024 | 05243201 | Yoakum District | 4 | $9,537.26 | $10,000 | $12,000 | 3 | Pulice Construction, Inc. | TxDOT |
| 05 APR 2024 | 04243210 | Houston District | 1 | $5,300.00 | $9,950.30 | $10,000 | 11 | R Construction Civil, LLC | TxDOT |
| 04 APR 2024 | 04243041 | Lubbock District | 4 | $11,000 | $9,747.50 | $7,200.00 | 4 | A. L. Helmcamp, Inc. | TxDOT |
| 06 MAR 2024 | 03243204 | Yoakum District | 2 | $8,200.00 | $7,269.87 | $10,000 | 2 | Hunter Industries, LTD. | TxDOT |
| 01 FEB 2024 | 02243002 | Lubbock District | 3 | $5,500.00 | $5,420.00 | $10,000 | 2 | Duininck, Inc. | TxDOT |
| 01 FEB 2024 | 02243044 | Amarillo District | 1 | $15,909 | $15,909 | $13,840 | 1 | Webber, LLC | TxDOT |
| 05 JAN 2024 | 01243201 | Yoakum District | 10 | $12,166 | $12,166 | $10,000 | 7 | Hunter Industries, LTD. | TxDOT |
| 04 JAN 2024 | 01243002 | Yoakum District | 2 | $5,507.84 | $5,753.92 | $9,200.00 | 4 | Hunter Industries, LTD. | TxDOT |
| 06 DEC 2023 | 12233201 | Yoakum District | 4 | $7,647.00 | $10,572 | $11,000 | 3 | Williams Brothers Construction Co., Inc. | TxDOT |
| 05 DEC 2023 | 12233010 | Corpus Christi District | 3 | $11,200 | $10,640 | $20,000 | 4 | Anderson Columbia Co., Inc. | TxDOT |
| 05 DEC 2023 | 12233013 | Abilene District | 2 | $15,000 | $15,500 | $14,000 | 5 | A. L. Helmcamp, Inc. | TxDOT |
| 06 SEP 2023 | 09233014 | Abilene District | 2 | $5,000.00 | $11,000 | $6,000.00 | 2 | Bontke Brothers Construction Company | TxDOT |
| 03 AUG 2023 | 08233204 | Yoakum District | 1 | $7,400.00 | $7,400.00 | $14,000 | 1 | Hunter Industries, LTD. | TxDOT |
| 02 AUG 2023 | 08233002 | San Antonio District | 2 | $18,900 | $15,544 | $7,500.00 | 2 | Jordan Foster Construction, LLC | TxDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the TxDOT explorer.
How these prices were read
TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are TxDOT's own: this item is compared with TxDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the TxDOT letting of 19 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way