Low bidders on VDOT contracts carried a median of $3,129.22 per EACH for this item, over the 24 months to 28 OCT 2026, across 2 low bids. Half of all 5 bids fell between $1,894.40 and $3,400.00.

Owner
Virginia DOT
Item
510SX20-0046
Unit
EACH
Data through
28 OCT 2026

VDOT prints this item as “NS ADJUST EXIST. JUNCTION BOX”.

VDOT has bid this work under more than one code: 24535 on lettings from 26 FEB 2002 to 24 FEB 2021 (184 bids); 510SX20-0046 on lettings from 22 JUL 2026 to 22 JUL 2026 (5 bids). They are combined here into one trend.

$3,129.22Low bidder's median, per EACH
$2,858.43Median of all bids, per EACH
2Contracts in the window

By year of letting

NS adjust exist. junction box, VDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
200222$599.506$629.00
200312$700.005$700.00
200434$1,050.008$945.00
200523$1,200.009$1,300.00
200635$825.0012$1,012.50
200756$471.0017$500.00
200856$728.9415$750.00
200933$819.209$500.00
201145$1,350.0016$568.49
201233$612.349$750.00
201343$616.178$925.00
201453$501.9210$597.10
201522$625.006$1,100.00
201645$500.0011$623.28
201722$720.005$654.28
201944$1,076.8811$728.40
202066$882.5016$1,035.00
202122$775.146$1,275.14
202622$3,129.225$2,858.43

Bid prices as published, not adjusted for inflation.

By district

DistrictLow bidsLow-bid medianAll bidsMedian, all bids
Northern Virginia24$725.0062$825.49
Hampton Roads12$581.5033$634.00
Richmond7$1,050.2820$1,900.00
Bristol6$1,087.5018$1,200.00
Salem7$616.1717$1,500.00
Fredericksburg5$951.0315$951.03
Lynchburg5$500.0013$300.00
NS adjust exist. junction box, VDOT: unit prices by district, all lettings

Districts with at least three low bids, over all lettings.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 117$1,200.00
1 to 217$825.00
2 to 517$700.00
5 to 10017$529.00
NS adjust exist. junction box, VDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
B & B Signal Co., L.L.C.117 (64%)
Branch Highways, Inc.73 (43%)
Elite Contracting Group, Inc.53 (60%)
Fort Myer Construction Corporation72 (29%)
Branscome Inc.62 (33%)
A & M Concrete Corp.52 (40%)
NS adjust exist. junction box, VDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractDistrictQuantityLow bidder's priceMedianBidsLow bidderSource
22 JUL 2026C0000128966N01Fredericksburg4$2,858.43$1,894.403Richardson-Wayland-Ferreira, LLCVDOT
22 JUL 2026C0000119114C01Northern Virginia3$3,400.00$3,406.382A & M Concrete Corp.VDOT
24 FEB 2021C0000107036M01Richmond1$1,050.28$1,050.283M & F Concrete, Inc.VDOT
24 FEB 2021C0000107055M01Salem2$500.00$2,500.003Jones Road & Bridge, Inc.VDOT
16 DEC 2020C0000117400N01Hampton Roads15$529.00$996.003Bryant-Ritter Electric CorporationVDOT
21 OCT 2020C0000116560N01Fredericksburg6$750.00$990.083B & B Signal Co., L.L.C.VDOT
27 MAY 2020C0000109311C01BRichmond3$1,000.00$2,500.003Jireh Construction Company, Inc.VDOT
22 APR 2020C0000115494M01Lynchburg3$800.00$650.002Ramirez Contracting, L.L.C.VDOT
22 APR 2020C0000116082N01Northern Virginia3$965.00$1,298.003B & B Signal Co., L.L.C.VDOT
22 JAN 2020C000111370C01BSalem2$1,900.00$2,450.002Allegheny Construction Company, Inc.VDOT
25 SEP 2019C0000109538M01Lynchburg1$1,550.00$1,135.002Crossroads Bridge IncVDOT
24 JUL 2019C0000100921C01Hampton Roads2$1,159.75$1,159.753Branscome Inc.VDOT
24 JUL 2019C0000114462N01Fredericksburg5$994.01$611.003Richardson-Wayland Electrical Co. LLCVDOT
26 JUN 2019C0000114674N01Northern Virginia4$400.00$728.403B & B Signal Co., L.L.C.VDOT
15 NOV 2017C0000110896N01Northern Virginia6$1,110.00$1,655.002B & B Signal Co., L.L.C.VDOT
Latest VDOT contracts carrying NS adjust exist. junction box

Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.

How these prices were read

VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy