Traffic barrier service MB-10A, VDOT 512SD20-0002
Low bidders on VDOT contracts carried a median of $125.00 per LF for this item, over the 24 months to 28 OCT 2026, across 1 low bids. Half of all 2 bids fell between $293.75 and $631.25.
- Owner
- Virginia DOT
- Item
- 512SD20-0002
- Unit
- LF
- Data through
- 28 OCT 2026
VDOT prints this item as “TRAFFIC BARRIER SERVICE MB-10A”.
VDOT has bid this work under more than one code: 13495 on lettings from 25 JUN 2002 to 27 OCT 2021 (214 bids); 512SD20-0002 on lettings from 04 FEB 2026 to 04 FEB 2026 (2 bids). They are combined here into one trend.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2002 | 3 | 3 | $28.00 | 8 | $27.75 |
| 2003 | 8 | 8 | $15.00 | 20 | $16.50 |
| 2004 | 6 | 6 | $12.00 | 14 | $20.00 |
| 2005 | 4 | 4 | $9.50 | 10 | $19.00 |
| 2006 | 1 | 1 | $30.00 | 3 | $30.00 |
| 2007 | 2 | 2 | $25.00 | 5 | $50.00 |
| 2008 | 6 | 6 | $22.00 | 17 | $35.00 |
| 2009 | 1 | 1 | $9.00 | 2 | $22.00 |
| 2010 | 1 | 1 | $15.00 | 3 | $10.50 |
| 2011 | 2 | 2 | $34.12 | 6 | $52.00 |
| 2012 | 4 | 4 | $36.62 | 12 | $39.62 |
| 2013 | 6 | 6 | $35.00 | 17 | $47.00 |
| 2014 | 4 | 4 | $62.03 | 8 | $62.03 |
| 2015 | 6 | 6 | $39.00 | 16 | $42.50 |
| 2016 | 8 | 7 | $46.00 | 22 | $53.62 |
| 2017 | 1 | 1 | $45.00 | 3 | $45.00 |
| 2018 | 6 | 6 | $49.50 | 18 | $60.00 |
| 2019 | 4 | 4 | $55.00 | 12 | $60.00 |
| 2020 | 1 | 1 | $85.00 | 3 | $85.00 |
| 2021 | 5 | 5 | $120.05 | 15 | $85.00 |
| 2026 | 1 | 1 | $125.00 | 2 | $462.50 |
Bid prices as published, not adjusted for inflation.
By district
| District | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Salem | 37 | $20.00 | 100 | $30.00 |
| Bristol | 12 | $39.00 | 36 | $40.00 |
| Northern Virginia | 10 | $53.75 | 28 | $57.50 |
| Richmond | 5 | $60.00 | 12 | $62.03 |
| Culpeper | 4 | $62.50 | 12 | $94.50 |
| Fredericksburg | 4 | $55.00 | 10 | $57.00 |
| Lynchburg | 3 | $30.00 | 9 | $45.00 |
Districts with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 120 | 19 | $45.00 |
| 120 to 260 | 20 | $41.62 |
| 268 to 546 | 20 | $32.50 |
| 560 to 3,500 | 20 | $22.75 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Lanford Brothers Company, Incorporated | 21 | 18 (86%) |
| Elk Knob, Inc. | 15 | 7 (47%) |
| Patrick Construction, Inc. | 8 | 6 (75%) |
| Crossroads Bridge Inc | 10 | 4 (40%) |
| Burleigh Construction Co., Inc. | 9 | 4 (44%) |
| Martins Construction Corp. | 6 | 3 (50%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | District | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 04 FEB 2026 | C0000127189N01 | Hampton Roads | 25 | $125.00 | $462.50 | 2 | M. D. Miller Co., Inc. | VDOT |
| 27 OCT 2021 | C0000112877B10 | Salem | 100 | $90.00 | $90.00 | 3 | A. R. Coffey and Sons, Inc. | VDOT |
| 22 SEP 2021 | C0000118341D38 | Salem | 24 | $128.56 | $100.00 | 3 | Kanawha Stone Company, Inc. | VDOT |
| 28 JUL 2021 | C0000110001B54 | Culpeper | 55 | $120.05 | $100.00 | 3 | Clearwater Construction, Inc. | VDOT |
| 24 MAR 2021 | C0000116749N01 | Lynchburg | 1,460 | $30.00 | $45.00 | 3 | Burleigh Construction Co., Inc. | VDOT |
| 20 JAN 2021 | C0000111691B23 | Northern Virginia | 320 | $162.00 | $40.00 | 3 | Joseph B. Fay Co. | VDOT |
| 21 OCT 2020 | C0000101043B60 | Lynchburg | 120 | $85.00 | $85.00 | 3 | Stonewall Bridge, Inc. | VDOT |
| 24 JUL 2019 | C000081548B35B | Bristol | 100 | $50.00 | $55.00 | 3 | Patrick Construction, Inc. | VDOT |
| 22 MAY 2019 | C000093087B60 | Richmond | 1,362 | $35.00 | $60.00 | 3 | Corman Kokosing Construction Company | VDOT |
| 27 FEB 2019 | C0000000673B03 | Salem | 288 | $85.00 | $54.00 | 3 | Brayman Construction Corporation | VDOT |
| 23 JAN 2019 | C0000111320B47 | Northern Virginia | 300 | $60.00 | $86.00 | 3 | Martins Construction Corp. | VDOT |
| 14 NOV 2018 | C0000104773B54 | Bristol | 432 | $42.00 | $50.00 | 3 | Patrick Construction, Inc. | VDOT |
| 22 AUG 2018 | C0000077296B01 | Salem | 112 | $22.37 | $43.00 | 3 | DLB Enterprises LLC | VDOT |
| 20 JUN 2018 | C0000140430B06 | Culpeper | 216 | $50.00 | $98.00 | 3 | Fairfield-Echols, LLC | VDOT |
| 25 APR 2018 | C0000104837B07 | Bristol | 200 | $49.00 | $49.00 | 3 | Orders Construction Company, Inc. | VDOT |
Filter this item by your own quantity, district and period, or check your price against it, in the VDOT explorer.
How these prices were read
VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are VDOT's own: this item is compared with VDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the VDOT letting of 28 OCT 2026 and was rebuilt on 26 NOV 2026.