WSDOT contract XE3764 bid tabulation
Us 12 Locust Ln Vicinity Emergency Washout Repair. Let by Washington State DOT on August 26, 2026, Yakima, SCR region. 7 bids received; low bid $329,923 by Interwest Construction, Inc., -26% against the engineer's estimate of $443,852.
- Owner
- Washington State DOT
- Letting
- 26 AUG 2026
- Pay items
- 28
- Data through
- 07 OCT 2026
6 of the 7 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Interwest Construction, Inc. | $329,923 | Low | -26% |
| 2 | Steele Trucking Inc. | $359,540 | +9.0% | -19% |
| 3 | M.J. Hughes Construction, Inc. | $413,623 | +25% | -7.0% |
| 5 | Scarsella Bros., Inc. | $448,625 | +36% | +1.0% |
| 6 | Titan Earthwork LLC | $543,933 | +65% | +23% |
| 7 | Granite Construction Company | $580,672 | +76% | +31% |
Engineer's estimate: $443,852.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Interwest Construction, Inc. | 2. Steele Trucking Inc. | 3. M.J. Hughes Construction, Inc. | 4. Scarsella Bros., Inc. | 5. Titan Earthwork LLC | 6. Granite Construction Company |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mobilization | LS | 1 | $40,500 | $26,300 | $76,000 | $55,000 | $40,000 | $54,000 | $58,000 |
| 2 | Clearing and grubbing | LS | 1 | $2,500.00 | $10,000 | $10,000 | $10,000 | $3,000.00 | $8,000.00 | $13,000 |
| 3 | Removing guardrail | LF | 800 | $20.00 | $8.00 | $8.00 | $7.00 | $7.00 | $10.50 | $7.00 |
| 4 | Removing guardrail anchor | EACH | 1 | $500.00 | $400.00 | $350.00 | $250.00 | $350.00 | $650.00 | $350.00 |
| 5 | Removing wire fence | LF | 766 | $10.00 | $6.50 | $5.50 | $1.00 | $5.50 | $9.00 | $5.00 |
| 6 | Streambed boulder type four | EACH | 200 | $200.00 | $300.00 | $350.00 | $300.00 | $575.00 | $700.00 | $510.00 |
| 7 | Rock for erosion and scour protection class C | CY | 900 | $150.00 | $82.00 | $55.00 | $95.00 | $111.70 | $125.00 | $200.00 |
| 8 | Quarry spalls | CY | 300 | $100.00 | $61.00 | $65.00 | $80.00 | $82.25 | $105.00 | $151.00 |
| 9 | Crushed surfacing base course | TON | 120 | $50.00 | $49.00 | $45.00 | $80.00 | $50.00 | $55.00 | $109.00 |
| 10 | Erosion/water pollution control | EST | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 11 | Beam guardrail type 31 | LF | 875 | $50.00 | $46.00 | $40.00 | $43.00 | $39.00 | $51.00 | $39.00 |
| 12 | Beam guardrail anchor type 11 | EACH | 1 | $2,500.00 | $2,700.00 | $2,500.00 | $1,500.00 | $2,300.00 | $3,400.00 | $2,300.00 |
| 13 | Temporary barrier | LF | 1,000 | $50.00 | $30.00 | $28.00 | $60.00 | $26.00 | $32.00 | $26.00 |
| 14 | Temporary impact attenuator | EACH | 1 | $5,000.00 | $5,300.00 | $4,500.00 | $4,900.00 | $4,500.00 | $5,400.00 | $4,500.00 |
| 15 | Flexible guide post | EACH | 10 | $100.00 | $76.00 | $65.00 | $50.00 | $65.00 | $140.00 | $65.00 |
| 16 | Permanent signing | LS | 1 | $2,000.00 | $4,000.00 | $2,500.00 | $2,800.00 | $2,000.00 | $2,600.00 | $4,000.00 |
| 17 | Portable changeable message sign | HR | 1,000 | $5.00 | $2.00 | $5.00 | $3.50 | $3.50 | $5.50 | $4.00 |
| 18 | Project temporary traffic control | LS | 1 | $30,000 | $14,000 | $15,000 | $28,000 | $51,350 | $48,000 | $60,000 |
| 19 | Work zone safety contingency | EST | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 20 | Construction signs class A | SF | 161 | $40.00 | $32.00 | $25.00 | $30.00 | $30.00 | $42.00 | $35.00 |
| 21 | WSP reimbursement | CALC | 1 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 |
| 22 | Project partnering | CALC | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 23 | Roadway surveying | LS | 1 | $5,000.00 | $5,600.00 | $5,000.00 | $5,500.00 | $6,000.00 | $12,000 | $4,800.00 |
| 24 | Roadside cleanup | EST | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 25 | Reimbursement for third party damage | EST | 1 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 26 | Minor change | CALC | 1 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 |
| 27 | Aggregate compliance price adjustment | CALC | 1 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 | -$1.00 |
| 28 | Spill prevention, control, and countermeasures plan | LS | 1 | $2,000.00 | $1,100.00 | $3,000.00 | $750.00 | $1,000.00 | $700.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WSDOT's tabulation for this contract. WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
Every contract let that day: WSDOT letting of August 26, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.