ALDOT contract 20250228001 bid tabulation
BRIDGE REPLACEMENT (GRADING, DRAINAGE, PAVEMENT, AND BRIDGE) ON SR-243 OVER CEDAR CREEK SOUTHEAST OF RUSSELLVILLE. Let by Alabama DOT on February 28, 2025, Franklin, 0202. 3 bids received; low bid $2,754,368 by Miller & Miller, Inc..
- Owner
- Alabama DOT
- Letting
- 28 FEB 2025
- Pay items
- 94
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Miller & Miller, Inc. | $2,754,368 | Low |
| 2 | Glasgow Construction Co., Inc. | $3,327,396 | +21% |
| 3 | Key, LLC | $5,561,747 | +102% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller & Miller, Inc. | 2. Glasgow Construction Co., Inc. | 3. Key, LLC |
|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (maximum allowable bid $ 8,000.00 per acre) (approximately 3 acres) (201A002) | LS | 1 | $24,000 | $24,000 | $22,125 |
| 0020 | Removal of old bridge, station 123+36.24 (206A000) | LS | 1 | $93,900 | $212,600 | $777,500 |
| 0030 | Removing pipe (206D000) | LF | 94 | $22.00 | $10.00 | $40.00 |
| 0040 | Removing guardrail (206D001) | LF | 230 | $15.00 | $10.00 | $9.00 |
| 0050 | Removing fence (206D011) | LF | 1,384 | $7.00 | $10.00 | $7.45 |
| 0060 | Removing guardrail end anchor (all type) (206E008) | EACH | 4 | $800.00 | $1,100.00 | $1,190.00 |
| 0070 | Unclassified excavation (210A000) | CY | 4,634 | $26.00 | $40.00 | $60.00 |
| 0080 | Borrow excavation (210D000) | CY | 8,506 | $26.00 | $25.00 | $26.00 |
| 0090 | Roadbed processing (230A000) | RBST | 7 | $700.00 | $1,700.00 | $1,716.00 |
| 0100 | Crushed aggregate base course, type B, plant mixed, 6" compacted thickness (301A012) | SY | 2,445 | $15.00 | $145.70 | $17.00 |
| 0110 | Plant mix bituminous base, mix 2 (327A021) | TON | 141 | $115.00 | $18.10 | $132.00 |
| 0120 | Bituminous treatment A (401A000) | SY | 2,279 | $1.25 | $2.14 | $1.95 |
| 0130 | Tack coat (405A000) | GAL | 1,387 | $3.50 | $5.32 | $4.80 |
| 0140 | Micro-milling existing pavement (approximately 1.10" thru 2.00" thick) (408B001) | SY | 2,019 | $3.50 | $5.42 | $4.90 |
| 0150 | Superpave bituminous concrete wearing surface layer, 1/2" maximum aggregate size mix, esal range C/D (424A360) | TON | 339 | $110.00 | $147.36 | $133.20 |
| 0160 | Superpave bituminous concrete upper binder layer, 3/4" maximum aggregate size mix, esal range C/D (424B650) | TON | 544 | $105.00 | $130.02 | $117.55 |
| 0170 | Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range C/D (424B655) | TON | 100 | $185.00 | $229.36 | $208.00 |
| 0180 | Superpave bituminous concrete upper binder layer, leveling, 1/2" maximum aggregate size mix, esal range C/D (424B657) | TON | 127 | $125.00 | $142.92 | $130.00 |
| 0190 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range C/D (424B658) | TON | 201 | $120.00 | $138.90 | $126.00 |
| 0200 | Superpave bituminous concrete upper binder layer, leveling, 1" maximum aggregate size mix, esal range C/D (424B659) | TON | 911 | $100.00 | $128.52 | $117.00 |
| 0210 | Superpave bituminous concrete lower binder layer, 1" maximum aggregate size mix, esal range C/D (424B681) | TON | 414 | $120.00 | $131.53 | $119.00 |
| 0220 | Scoring bituminous pavement surface (428A001) | MI | 1 | $8,910.00 | $330.00 | $2,850.00 |
| 0230 | Aggregate surfacing (aldot #410 modified) (430B014) | TON | 408 | $44.00 | $47.00 | $50.00 |
| 0240 | Aggregate surfacing (aldot #57 or #67) (430B033) | TON | 43 | $44.00 | $47.00 | $62.00 |
| 0250 | Aggregate surfacing (crushed aggregate base, type B) (430B040) | TON | 100 | $44.00 | $37.60 | $54.00 |
| 0260 | Aggregate surfacing (crushed aggregate base, type A) (430B042) | TON | 33 | $44.00 | $47.70 | $88.00 |
| 0270 | Aggregate surfacing (aldot #2) (430B046) | TON | 369 | $44.00 | $40.00 | $46.00 |
| 0280 | Reinforced cement concrete bridge end slab (450B000) | SY | 207 | $165.00 | $1.50 | $700.00 |
| 0290 | Steel reinforcement (502A000) | LB | 26,900 | $1.25 | $1.50 | $3.25 |
| 0300 | Steel reinforcement for bridge superstructure, station 123+41.00, approximately 38,400 pounds (502B000) | LS | 1 | $62,000 | $57,600 | $67,000 |
| 0310 | Drilled shaft excavation, 4'-0" diameter (506A008) | LF | 117 | $305.00 | $672.80 | $1,415.00 |
| 0320 | Special drilled shaft excavation, 4'-0" diameter (506B003) | LF | 36 | $2,300.00 | $1,800.00 | $3,448.00 |
| 0330 | Drilled shaft construction, 4'-0" diameter, class DS1 concrete (506C042) | LF | 153 | $135.00 | $528.00 | $1,071.00 |
| 0340 | Exploration below drilled shaft (506D000) | LF | 60 | $565.00 | $256.00 | $570.00 |
| 0350 | Crosshole sonic logging, 4'-0" diameter (506G002) | EACH | 6 | $565.00 | $465.00 | $2,750.00 |
| 0360 | Structural steel (508A000) | LB | 2,510 | $5.25 | $3.00 | $10.00 |
| 0370 | Bridge substructure concrete (510A007) | CY | 77 | $950.00 | $1,500.00 | $4,500.00 |
| 0380 | Bridge concrete superstructure, station 123+41.00, approximately 142 cubic yards (510C051) | LS | 1 | $159,500 | $191,700 | $650,000 |
| 0390 | Grooving concrete bridge decks (510E000) | SY | 491 | $11.00 | $90.00 | $17.00 |
| 0400 | Bridge barrier rail, type 36” single slope (510J000) | LF | 276 | $95.00 | $275.00 | $322.00 |
| 0410 | Elastomeric bearing type 2 (mark B5) (511A065) | EACH | 10 | $985.00 | $881.60 | $1,020.00 |
| 0420 | Pretensioned-prestressed concrete girders, type BT-72 modified (specialty item) (513B032) | LF | 686 | $525.00 | $468.00 | $885.00 |
| 0430 | 18" side drain pipe (class 3 R.C.) (535A080) | LF | 84 | $150.00 | $59.00 | $123.00 |
| 0440 | 24" side drain pipe (class 3 R.C.) (535A085) | LF | 76 | $170.00 | $70.00 | $110.00 |
| 0450 | Mobilization (600A000) | LS | 1 | $359,700 | $294,685 | $650,000 |
| 0460 | Right of way markers (602A000) | EACH | 10 | $775.00 | $400.00 | $1,725.00 |
| 0470 | Separation geotextile (608A000) | SY | 389 | $4.00 | $7.00 | $4.00 |
| 0480 | Loose riprap, class 2 (610C001) | TON | 1,711 | $48.00 | $40.00 | $50.00 |
| 0490 | Filter blanket, geotextile (610D003) | SY | 2,208 | $5.00 | $7.00 | $3.25 |
| 0500 | 18" side drain pipe end treatment, class 1 (619A101) | EACH | 6 | $3,100.00 | $1,000.00 | $1,625.00 |
| 0510 | 24" side drain pipe end treatment, class 1 (619A102) | EACH | 2 | $3,600.00 | $1,378.00 | $2,060.00 |
| 0520 | Steel beam guardrail, class A, type 2 (630A001) | LF | 50 | $34.00 | $42.00 | $37.00 |
| 0530 | Guardrail end anchor, type 13 (MASH) (630C079) | EACH | 4 | $3,600.00 | $3,800.00 | $2,380.00 |
| 0540 | Guardrail end anchor, type 20 series (MASH) (630C080) | EACH | 4 | $3,300.00 | $4,500.00 | $4,760.00 |
| 0550 | Industrial fence, 6 feet high plus barbed wire (45 degree arms) (634B000) | LF | 390 | $32.00 | $50.00 | $86.00 |
| 0560 | Gate, 20 feet wide, complete with fittings (with barbed wire) (634D003) | EACH | 1 | $2,925.00 | $2,500.00 | $5,125.00 |
| 0570 | Barbed wire fence, 5 strands, 5 feet high (636A002) | LF | 794 | $12.00 | $20.00 | $29.00 |
| 0580 | Topsoil (650A000) | CY | 1,125 | $36.00 | $40.00 | $18.00 |
| 0590 | Seeding (652A100) | ACRE | 2 | $1,900.00 | $2,035.00 | $3,990.00 |
| 0600 | Mowing (652C000) | ACRE | 8 | $160.00 | $176.55 | $285.00 |
| 0610 | Solid sodding (bermuda) (654A001) | SY | 3,877 | $10.75 | $15.00 | $8.00 |
| 0620 | Solid sodding (myers zoysia) (654A006) | SY | 1,238 | $12.00 | $16.00 | $14.00 |
| 0630 | Mulching (656A010) | ACRE | 2 | $1,800.00 | $1,914.00 | $1,710.00 |
| 0640 | Erosion control product, type C8 (659C007) | SY | 2,284 | $7.00 | $6.50 | $12.00 |
| 0650 | Temporary seeding (665A000) | ACRE | 3 | $1,300.00 | $1,334.00 | $1,710.00 |
| 0660 | Temporary mulching (665B001) | TON | 27 | $1,100.00 | $12.18 | $285.00 |
| 0670 | Temporary pipe (665C010) | LF | 100 | $56.00 | $29.00 | $18.00 |
| 0680 | Polyethylene (665E000) | SY | 500 | $4.00 | $4.00 | $18.00 |
| 0690 | Hay bales (665F000) | EACH | 50 | $11.00 | $12.00 | $12.00 |
| 0700 | Sand bags (665G000) | EACH | 50 | $8.00 | $10.00 | $29.00 |
| 0710 | Temporary riprap, class 2 (665I000) | TON | 552 | $60.00 | $45.00 | $57.00 |
| 0720 | Silt fence (665J002) | LF | 469 | $5.00 | $5.00 | $9.00 |
| 0730 | Temporary coarse aggregate,aldot number 1 (665N000) | TON | 120 | $46.00 | $40.00 | $60.00 |
| 0740 | Temporary coarse aggregate,aldot number 4 (665N001) | TON | 75 | $46.00 | $40.00 | $53.00 |
| 0750 | Silt fence removal (665O001) | LF | 469 | $1.30 | $3.00 | $4.00 |
| 0760 | Wattle (665Q002) | LF | 360 | $9.00 | $20.00 | $15.00 |
| 0770 | Pest control treatment (666A001) | ACRE | 3 | $10.00 | $50.00 | $285.00 |
| 0780 | Geometric controls (680A001) | LS | 1 | $63,500 | $30,000 | $95,000 |
| 0790 | Construction fuel (maximum bid limited to $ 122,000.00) (698A000) | LS | 1 | $0.00 | $1.00 | $1.00 |
| 0800 | Solid temporary traffic stripe (701C001) | MI | 2 | $2,016.00 | $1,375.00 | $1,425.00 |
| 0810 | Solid white, class W, type A traffic stripe (5"wide) (701G146) | LF | 280 | $10.64 | $8.80 | $10.00 |
| 0820 | Solid yellow, class W, type A traffic stripe (5" wide) (701G154) | LF | 280 | $10.64 | $8.80 | $10.00 |
| 0830 | Solid white, class 2, type A traffic stripe (5" wide) (701G253) | LF | 2,564 | $2.24 | $2.20 | $2.30 |
| 0840 | Solid yellow, class 2, type A traffic stripe (5" wide) (701G265) | LF | 2,585 | $2.24 | $2.28 | $2.30 |
| 0850 | Traffic control markings, class 2, type A (703A002) | SF | 32 | $16.80 | $11.40 | $12.00 |
| 0860 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 33 | $11.20 | $11.40 | $12.00 |
| 0870 | Class 10 aluminum flat sign panels (type XI background) (710A163) | SF | 8 | $28.00 | $26.68 | $25.00 |
| 0880 | Class 4, aluminum flat sign panels (type IV background) (710A171) | SF | 64 | $22.40 | $25.52 | $26.00 |
| 0890 | Roadway sign post (#3 U channel, galvanized steel or 2 ", 14 GA square tubular steel) (710B021) | LF | 168 | $17.92 | $22.04 | $22.00 |
| 0900 | Construction signs (740B000) | SF | 692 | $7.00 | $10.00 | $8.00 |
| 0910 | Channelizing drums (740D000) | EACH | 50 | $85.00 | $33.64 | $34.00 |
| 0920 | Cones (36 inches high) (740E000) | EACH | 50 | $29.00 | $25.60 | $26.00 |
| 0930 | Barricades, type III (740F002) | EACH | 8 | $280.00 | $300.00 | $255.00 |
| 0940 | Portable changeable message sign, type 2 (742A001) | EACH | 4 | $5,600.00 | $5,670.00 | $5,400.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of February 28, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.