ALDOT contract 20260130064 bid tabulation
RESURFACING, SIDEWALK IMPROVEMENTS, AND TRAFFIC STRIPE ON WALNUT STREET FROM SOUTH 8TH STREET TO SOUTH 5TH STREET IN GADSDEN. Let by Alabama DOT on January 30, 2026, Etowah, 0105. 7 bids received; low bid $852,496 by Alabama Grading & Excavation, LLC..
- Owner
- Alabama DOT
- Letting
- 30 JAN 2026
- Pay items
- 65
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Alabama Grading & Excavation, LLC. | $852,496 | Low |
| 2 | McElhenney Construction Co., LLC | $1,196,103 | +40% |
| 3 | Gillespie Construction, LLC | $1,196,584 | +40% |
| 4 | Bulls Construction Group, LLC | $1,252,636 | +47% |
| 5 | Vulcan Materials Asphalt and Construction, | $1,258,014 | +48% |
| 6 | Wiregrass Construction Company, Inc. | $1,285,256 | +51% |
| 7 | CB&A Construction, LLC. | $1,519,353 | +78% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alabama Grading & Excavation, LLC. | 2. McElhenney Construction Co., LLC | 3. Gillespie Construction, LLC | 4. Bulls Construction Group, LLC | 5. Vulcan Materials Asphalt and Construction, | 6. Wiregrass Construction Company, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Removing concrete sidewalk (206C000) | SY | 551 | $20.22 | $28.83 | $15.00 | $20.00 | $54.00 | $18.58 |
| 0020 | Removing concrete pavement (206C001) | SY | 196 | $34.11 | $48.79 | $18.00 | $25.00 | $30.00 | $22.29 |
| 0030 | Removing concrete driveway (206C010) | SY | 371 | $32.15 | $35.24 | $18.00 | $25.00 | $51.00 | $22.29 |
| 0040 | Removing curb and gutter (206D003) | LF | 1,951 | $14.29 | $15.86 | $15.00 | $20.00 | $25.00 | $18.58 |
| 0050 | Removing gutter (206D005) | LF | 521 | $23.93 | $19.03 | $15.00 | $20.00 | $68.00 | $18.58 |
| 0060 | Removing inlets (206E001) | EACH | 3 | $1,050.91 | $1,427.17 | $1,500.00 | $1,500.00 | $1,175.00 | $1,857.66 |
| 0070 | Removing inlets (partial) (206E042) | EACH | 1 | $1,774.98 | $1,427.16 | $1,250.00 | $1,500.00 | $2,345.00 | $1,548.05 |
| 0080 | Borrow excavation (loose truckbed measurement) (210D001) | CY | 50 | $50.69 | $44.01 | $65.00 | $100.00 | $157.00 | $80.50 |
| 0090 | Structure excavation (214A000) | CY | 20 | $110.58 | $16.57 | $75.00 | $100.00 | $122.00 | $92.88 |
| 0100 | Foundation backfill, commercial (214B001) | CY | 9 | $374.33 | $108.07 | $100.00 | $200.00 | $263.00 | $123.84 |
| 0110 | Crushed aggregate base course, type B, plant mixed (301E008) | TON | 482 | $48.43 | $91.45 | $50.00 | $75.00 | $155.00 | $61.92 |
| 0120 | Tack coat (405A000) | GAL | 1,232 | $6.12 | $9.16 | $15.75 | $5.75 | $4.50 | $14.94 |
| 0130 | Planing existing pavement (approximately 0.00" thru 1.0" thick) (408A051) | SY | 1,142 | $7.00 | $13.46 | $10.00 | $13.00 | $10.00 | $11.15 |
| 0140 | Planing existing pavement (approximately 3.10" thru 4.0" thick) (408A054) | SY | 6,965 | $5.00 | $8.90 | $13.00 | $6.50 | $6.00 | $12.18 |
| 0150 | Material remixing device (410H000) | EACH | 1 | $15,089 | $9,162.59 | $5,500.00 | $33,020 | $26,000 | $5,000.00 |
| 0160 | Superpave bituminous concrete wearing surface layer, 3/8" maximum aggregate size mix, esal range A/B (424A336) | TON | 424 | $163.17 | $184.94 | $216.00 | $248.00 | $210.00 | $205.42 |
| 0170 | Superpave bituminous concrete upper binder layer, patching, 3/4" maximum aggregate size mix, esal range A/B (424B639) | TON | 95 | $333.38 | $235.23 | $253.00 | $440.00 | $350.00 | $230.68 |
| 0180 | Superpave bituminous concrete upper binder layer, leveling, 3/4" maximum aggregate size mix, esal range A/B (424B643) | TON | 870 | $138.07 | $172.73 | $198.00 | $210.00 | $175.00 | $206.33 |
| 0190 | Removal of concrete pavement slab (453C000) | SY | 50 | $34.84 | $79.29 | $100.00 | $98.00 | $415.00 | $94.79 |
| 0200 | Concrete pavement replacement slab (plain concrete) (453D001) | CY | 9 | $712.58 | $1,466.01 | $1,000.00 | $1,932.00 | $2,275.00 | $1,884.04 |
| 0210 | Cleaning and sealing concrete pavement, type II, joints (454A002) | LF | 7,475 | $1.50 | $7.33 | $15.00 | $4.25 | $6.00 | $4.12 |
| 0220 | Mobilization (600A000) | LS | 1 | $76,020 | $189,791 | $110,000 | $146,899 | $108,955 | $207,433 |
| 0230 | Concrete sidewalk, 4" thick (618A000) | SY | 340 | $74.52 | $73.30 | $110.00 | $115.00 | $96.50 | $136.23 |
| 0240 | Concrete sidewalk, 6" thick (618A001) | SY | 7 | $523.82 | $244.34 | $150.00 | $250.00 | $268.00 | $185.77 |
| 0250 | Concrete driveway, 6" thick (includes wire mesh) (618B003) | SY | 386 | $84.10 | $158.82 | $130.00 | $125.00 | $110.00 | $161.00 |
| 0260 | Detectable warning surface (618C001) | SF | 190 | $66.50 | $73.30 | $50.00 | $60.00 | $80.50 | $61.92 |
| 0270 | Curb ramp (618D000) | SY | 145 | $346.96 | $262.66 | $390.00 | $400.00 | $296.00 | $482.99 |
| 0280 | Inlets, type S3 (1 wing) (partial) (621C056) | EACH | 1 | $6,500.00 | $4,275.87 | $6,500.00 | $6,500.00 | $7,365.00 | $8,049.87 |
| 0290 | Inlets, type E (modified) (621C076) | EACH | 3 | $13,324 | $17,714 | $12,500 | $10,000 | $14,050 | $15,481 |
| 0300 | Concrete gutter (623A000) | LF | 565 | $68.30 | $73.30 | $45.00 | $75.00 | $67.00 | $55.73 |
| 0310 | Concrete curb, type A (623B002) | LF | 35 | $108.93 | $73.30 | $65.00 | $58.00 | $67.00 | $80.50 |
| 0320 | Combination curb & gutter, type C (623C000) | LF | 2,055 | $31.99 | $42.76 | $50.00 | $50.00 | $43.00 | $61.92 |
| 0330 | Valve box reset (641S500) | EACH | 13 | $150.00 | $741.37 | $100.00 | $500.00 | $130.00 | $123.84 |
| 0340 | Manhole frame and cover reset (645K500) | EACH | 12 | $567.59 | $1,107.74 | $500.00 | $2,000.00 | $1,805.00 | $619.22 |
| 0350 | Gas valve box reset (646J000) | EACH | 1 | $535.44 | $1,015.40 | $150.00 | $1,500.00 | $130.00 | $185.77 |
| 0360 | Topsoil (650A000) | CY | 67 | $106.00 | $53.27 | $40.00 | $100.00 | $156.00 | $49.54 |
| 0370 | Solid sodding (654A000) | SY | 613 | $10.52 | $9.16 | $12.00 | $25.00 | $12.00 | $16.10 |
| 0380 | Sand bags (665G000) | EACH | 50 | $16.57 | $17.10 | $8.00 | $13.00 | $10.50 | $12.38 |
| 0390 | Wattle (665Q002) | LF | 200 | $9.21 | $12.22 | $12.00 | $16.00 | $15.00 | $14.86 |
| 0400 | Construction safety fence (674A000) | LF | 100 | $7.72 | $3.39 | $5.00 | $15.00 | $15.00 | $30.96 |
| 0410 | Geometric controls (680A001) | LS | 1 | $11,413 | $21,648 | $35,000 | $33,731 | $55,000 | $18,577 |
| 0420 | Construction fuel (maximum bid limited to $ 40,000.00) (698A000) | LS | 1 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 0430 | Solid yellow, class 2, type A traffic stripe (701A235) | MI | 1 | $4,400.00 | $5,497.55 | $5,000.00 | $5,715.00 | $6,025.00 | $5,572.99 |
| 0440 | Dotted, class 2, type A traffic stripe (5" wide) (701B207) | LF | 66 | $2.10 | $2.44 | $3.00 | $2.75 | $2.70 | $2.48 |
| 0450 | Solid temporary traffic stripe (701C001) | MI | 3 | $1,520.00 | $1,527.10 | $1,375.00 | $1,590.00 | $1,675.00 | $1,548.05 |
| 0460 | Solid white, class 2, type A traffic stripe (5" wide) (701G253) | LF | 394 | $5.20 | $1.22 | $2.00 | $2.00 | $1.35 | $1.24 |
| 0470 | Traffic control markings, class 2, type A (703A002) | SF | 1,857 | $5.75 | $6.11 | $5.50 | $7.00 | $6.70 | $6.19 |
| 0480 | Traffic control legends, class 2, type A (703B002) | SF | 68 | $7.50 | $7.33 | $7.00 | $7.75 | $8.05 | $7.43 |
| 0490 | Temporary traffic control markings (703D001) | SF | 3,714 | $1.40 | $2.44 | $3.00 | $2.75 | $2.70 | $2.48 |
| 0500 | Specialty traffic control markings (703H000) | SF | 36 | $25.34 | $58.64 | $55.00 | $61.00 | $64.50 | $59.45 |
| 0510 | Pavement markers, class A-H, type 2-C (705A030) | EACH | 10 | $9.00 | $12.22 | $11.00 | $13.00 | $13.50 | $12.38 |
| 0520 | Pavement markers, class A-H, type 2-D (705A037) | EACH | 50 | $9.00 | $12.22 | $11.00 | $13.00 | $13.50 | $12.38 |
| 0530 | Class 9, aluminum flat sign panels (type XI background) (710A153) | SF | 18 | $46.20 | $32.37 | $45.00 | $27.00 | $28.00 | $26.01 |
| 0540 | Roadway sign post (#3 "U" channel galvanized steel) (710B001) | LF | 24 | $37.95 | $22.60 | $40.00 | $26.00 | $27.00 | $24.77 |
| 0550 | Removal of existing roadway signs (710C000) | LS | 1 | $528.26 | $366.50 | $10,000 | $1,500.00 | $100.00 | $92.88 |
| 0560 | Loop wire (730H001) | LF | 360 | $5.40 | $5.50 | $5.00 | $5.75 | $6.00 | $5.57 |
| 0570 | Loop detector lead-in-cable (730I001) | LF | 20 | $8.13 | $7.94 | $8.00 | $8.50 | $8.70 | $8.05 |
| 0580 | Traffic signal junction box type S1 (730K001) | EACH | 1 | $1,200.00 | $1,221.68 | $1,100.00 | $1,270.00 | $1,340.00 | $1,238.44 |
| 0590 | 1", non-metallic, conduit (730L003) | LF | 20 | $14.00 | $14.66 | $14.00 | $16.00 | $16.00 | $14.86 |
| 0600 | Construction signs (740B000) | SF | 448 | $8.40 | $7.94 | $12.00 | $7.50 | $7.70 | $7.12 |
| 0610 | Channelizing drums (740D000) | EACH | 25 | $25.00 | $16.49 | $65.00 | $50.00 | $33.50 | $30.96 |
| 0620 | Cones (36 inches high) (740E000) | EACH | 25 | $32.50 | $43.98 | $50.00 | $50.00 | $39.00 | $23.53 |
| 0630 | Barricades, type III (740F002) | EACH | 4 | $325.00 | $152.71 | $300.00 | $300.00 | $281.00 | $260.07 |
| 0640 | Barricades, type I, (portable, 24 inches wide) (740G000) | EACH | 4 | $192.50 | $91.63 | $150.00 | $100.00 | $100.00 | $92.88 |
| 0650 | Pilot car (740O000) | EACH | 1 | $5,354.40 | $19,547 | $10,000 | $8,890.00 | $7,000.00 | $2,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of January 30, 2026. Compiled by Mirage Metrics.