22 contracts let by Alabama DOT on February 23, 2024, $89,497,579 in low bids, a median of 3 bidders per contract.
- Owner
- Alabama DOT
- Contracts
- 22
- Low bids, total
- $89,497,579
- Data through
- 28 AUG 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| 20240223004 | ROADWAY IMPROVEMENTS/RECONSTRUCTION ON I-59 FROM A POINT NORTH OF THE SR-117 INTERCHANGE (MP 233.350) TO THE GEORGIA STATE LINE | 0103 | 4 | Wiregrass Construction Company, Inc. | $40,929,480 | $44,416,576 | +9.0% | ALDOT |
| 20240223008 | PLANING, RESURFACING, BRIDGE GUARDRAIL RETROFIT, AND STRIPE ON SR-8 (US-80) FROM THE JUNCTION OF SR-97 IN LOWNDESBORO TO THE PINTLALA CREEK BRIDGE (MP 120.512) | 0605 | 3 | Apac-Alabama, Inc. | $6,256,447 | $6,573,893 | +5.0% | ALDOT |
| 20240223009 | PLANE, RESURFACE (SCRUB SEAL), GUARDRAIL, AND TRAFFIC STRIPE ON SR-38 (US-280) FROM INTERSECTION OF COOSA STREET IN SYLACAUGA TO THE COOSA COUNTY LINE | 0405 | 4 | Gary Ingram Grading & Paving, Inc. | $4,389,456 | $4,958,957 | +13% | ALDOT |
| 20240223003 | PEDESTRIAN BRIDGE AND SIDEWALKS OVER SR-3 (US-31) NEAR WALD PARK IN VESTAVIA HILLS | 0301 | 2 | Bulls Construction Group, LLC | $4,190,150 | $4,664,062 | +11% | ALDOT |
| 20240223023 | MICRO-MILL, RESURFACING (SCRUB SEAL), GUARDRAIL, AND STRIPE ON SR-233 FROM THE JUNCTION OF SR-129 TO THE JUNCTION OF SR-74 (US-278) WEST OF NATURAL BRIDGE | 1001, 1009 | 1 | S. T. Bunn Construction Company, Inc. | $4,177,388 | ALDOT | ||
| 20240223017 | MICRO-MILL, RESURFACE, GUARDRAIL INSTALLATION, AND STRIPE ON SR-75 FROM THE INTERSECTION OF SR-1 (US-431) TO THE JUNCTION OF GARY ROAD | 0104 | 2 | Wiregrass Construction Company, Inc. | $3,180,082 | $3,317,634 | +4.0% | ALDOT |
| 20240223016 | PLANING, RESURFACING, AND TRAFFIC STRIPE ON SR-28 FROM SR-66 TO WEST OF OF SR-5 (SITE 1) AND ON SR-66 FROM SR-28 TO THE DALLAS COUNTY LINE (SITE 2) | 0802 | 1 | Asphalt Contractors, Inc. | $3,166,664 | ALDOT | ||
| 20240223007 | INTERSECTION IMPROVEMENTS ON SR-1 (US-231) AT SR-210 (ROSS CLARK CIRCLE) IN DOTHAN | 0701 | 2 | Apac-Alabama, Inc. | $2,922,202 | $3,612,937 | +24% | ALDOT |
| 20240223028 | SAFETY WIDEN, RESURFACE, BRIDGE GUARDRAIL RETROFIT, & STRIPE ON SR-605 FROM THE INTERSECTION OF FORTNER STREET IN DOTHAN TO THE JUNCTION OF SR-53 (US-231) | 0701, 0704 | 3 | Apac-Alabama, Inc. | $2,858,720 | $3,070,362 | +7.0% | ALDOT |
| 20240223005 | TRAFFIC SIGN REPLACEMENTS ON I-459 FROM THE I-20/I-59 INTERCHANGE (EXIT 0) IN MCCALLA TO THE I-59 INTERCHANGE | 0301 | 2 | Superior Traffic Control, LLC | $2,567,907 | $4,783,993 | +86% | ALDOT |
| 20240223011 | RESURFACE (MICRO-SURFACING SEAL COAT) & SIGNAL UPGRADES ON SR-3 (US-31) FROM OLD HIGHWAY 31 (MP 64.774) TO A POINT SOUTH OF THE BURNT CORN CREEK BRIDGE (MP 69.0 | 0903 | 3 | Mobile Asphalt Company, LLC | $2,352,846 | $2,364,613 | +1.0% | ALDOT |
| 20240223012 | SAFETY WIDENING, RESURFACING (SCRUB SEAL), AND STRIPE SAFETY WIDENING, MICRO-MILLING, RESURFACING (SCRUB SEAL), AND TRAFFIC STRIPE | 0105 | 4 | Whitaker Contracting Corporation | $2,267,953 | $2,322,917 | +2.0% | ALDOT |
| 20240223029 | RESURFACE, GUARDRAIL, STEEL BLOCK OUT REPLACEMENT, & STRIPE ON SR-269 FROM THE WCL OF BIRMINGHAM (MP 1.959) TO THE JUNCTION OF OLD MULGA LOOP ROAD | 0301 | 2 | Whitaker Contracting Corporation | $1,934,943 | $2,323,589 | +20% | ALDOT |
| 20240223015 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON SR-20 FROM INTERSECTION OF THE NATCHEZ TRACE PARKWAY TO THE INTERSECTION OF CR-222 | 0201 | 3 | Grayson Carter & Son Contracting, Inc. | $1,699,220 | $1,719,595 | +1.0% | ALDOT |
| 20240223026 | SAFETY WIDENING, RESURFACING, AND TRAFFIC STRIPE ON SR-27 FROM THE COFFEE COUNTY LINE TO A POINT NEAR MP 22.774 (4- LANE SECTION) SOUTHWEST OF ENTERPRISE | 0702 | 3 | Wiregrass Construction Company, Inc. | $1,372,089 | $1,646,005 | +20% | ALDOT |
| 20240223021 | RESURFACING (SURFACE TREATMENT), GUARDRAIL, AND STRIPE ON SR-25 (US-411) FROM THE JEFFERSON COUNTY LINE TO THE JUNCTION OF CHURCH STREET IN MOODY | 0302 | 2 | Whitaker Contracting Corporation | $1,308,711 | $1,866,746 | +43% | ALDOT |
| 20240223035 | MICRO-MILLING, RESURFACING, AND TRAFFIC STRIPE ON VARIOUS ROUTES AT VARIOUS LOCATIONS IN PRICEVILLE AS INDICATED IN THE PLANS | 0202 | 4 | Rogers Group, Inc. | $1,091,132 | $1,095,552 | 0.0% | ALDOT |
| 20240223018 | RESURFACING (SCRUB SEAL) AND TRAFFIC STRIPE ON SR-83 FROM THE CONECUH COUNTY LINE TO THE JUNCTION OF SR-47 SOUTHEAST OF BEATRICE | 0803 | 3 | Mobile Asphalt Company, LLC | $788,832 | $806,925 | +2.0% | ALDOT |
| 20240223022 | RESURFACING, GUARDRAIL INSTALLATION, AND TRAFFIC STRIPE ON SR-76 FROM THE JUNCTION OF SR-25 IN HARPERVILLE TO THE JUNCTION OF SR-38 (US-280). | 0305 | 3 | Wiregrass Construction Company, Inc. | $732,449 | $735,161 | 0.0% | ALDOT |
| 20240223044 | INTERSECTION IMPROVEMENTS (TURN LANE AND TRAFFIC SIGNALS) ON SR-2 (US-43) AT CR-61 (MIDDLE ROAD) IN FLORENCE | 0202 | 5 | Grayson Carter & Son Contracting, Inc. | $483,977 | $509,328 | +5.0% | ALDOT |
| 20240223032 | RESURFACING AND TRAFFIC STRIPE ON CR-27 (OLD MCGEHEE ROAD) FROM CR-23 (BUTLER MILL ROAD) TO SR-3 (US-31) SOUTHEAST OF HOPE HULL | 0603 | 3 | Apac-Alabama, Inc. | $482,090 | $508,253 | +5.0% | ALDOT |
| 20240223001 | RESURFACING AND TRAFFIC STRIPE ON CR-6 FROM THE WINSTON COUNTY LINE TO THE JUNCTION OF SR-33 | 0202 | 4 | Grayson Carter & Son Contracting, Inc. | $344,842 | $347,958 | +1.0% | ALDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ALDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.