ARDOT contract 090672 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO REALIGN HWY. 66 IN SEARCY COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, PORTLAND CEMENT CONCRETE BASE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH SLABS, PORTLAND CEMENT CONCRETE DRIVEWAY, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, MINOR DRAINAGE, EROSION CONTROL, CONCRETE WALKS, HAND RAILING, CONCRETE CURB AND GUTTER, WHEELCHAIR RAMPS, PAVEMENT MARKINGS, UTILITY ITEMS, POLYMER OVERLAY, CONSTRUCT ONE BRIDGE CONSISTING OF CONTINOUS R.C. SLAB UNIT (140') AND CONTINOUS W-BEAM UNIT (140') AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Searcy. 6 bids received; low bid $6,399,110 by Crouse Construction Co..
- Owner
- Arkansas DOT
- Letting
- 05 NOV 2025
- Pay items
- 137
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Crouse Construction Co. | $6,399,110 | Low |
| 2 | L. E. Davis Construction, Inc. | $7,221,786 | +13% |
| 3 | West Plains BR. & Grading, LLC | $7,995,000 | +25% |
| 4 | Graylee Construction & Demolition, LLC | $9,140,857 | +43% |
| 5 | Mobley Contractors, Inc. | $9,927,797 | +55% |
| 6 | Robertson Contractors, Inc. | $10,909,770 | +70% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crouse Construction Co. | 2. L. E. Davis Construction, Inc. | 3. West Plains BR. & Grading, LLC | 4. Graylee Construction & Demolition, LLC | 5. Mobley Contractors, Inc. | 6. Robertson Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 16 | $1,100.00 | $500.00 | $400.00 | $2,131.03 | $1,191.30 | $3,000.00 |
| 0002 | Grubbing (201111) | STA | 16 | $1,100.00 | $500.00 | $400.00 | $1,506.94 | $1,191.30 | $3,000.00 |
| 0003 | Removal and disposal of curb (202001) | LF | 166 | $10.00 | $15.00 | $5.00 | $36.14 | $28.07 | $20.00 |
| 0004 | Removal and disposal of concrete walls (202035) | LF | 50 | $30.00 | $75.00 | $16.00 | $150.00 | $46.60 | $5.50 |
| 0005 | Removal and disposal of concrete driveways (202062) | SY | 184 | $25.00 | $10.00 | $19.00 | $30.00 | $55.03 | $30.00 |
| 0006 | Removal and disposal of walks (202072) | SY | 259 | $30.00 | $10.00 | $6.50 | $18.00 | $39.75 | $35.00 |
| 0007 | Removal and disposal of drop inlets (202093) | EACH | 1 | $1,200.00 | $500.00 | $470.00 | $600.00 | $5,541.63 | $2,000.00 |
| 0008 | Removal and disposal of pipe culverts (202096) | EACH | 8 | $350.00 | $750.00 | $620.00 | $240.00 | $2,041.49 | $1,450.00 |
| 0009 | Removal and disposal of box culverts (202097) | EACH | 1 | $3,700.00 | $500.00 | $3,650.00 | $28,140 | $6,796.38 | $20,000 |
| 0010 | Removal and disposal of headwalls (202099) | EACH | 3 | $400.00 | $500.00 | $625.00 | $1,320.00 | $1,443.92 | $1,150.00 |
| 0011 | Removal and disposal of luminaire pole and foundation (202153) | EACH | 3 | $1,500.00 | $1,000.00 | $750.00 | $2,100.00 | $1,636.44 | $1,500.00 |
| 0012 | Unclassified excavation (210213) | CY | 1,242 | $35.00 | $30.00 | $70.00 | $16.15 | $82.93 | $32.00 |
| 0013 | Compacted embankment (210611) | CY | 11,267 | $18.00 | $25.00 | $28.50 | $26.50 | $39.55 | $34.50 |
| 0014 | Soil stabilization (210702) | TON | 100 | $5.00 | $2.00 | $75.00 | $570.00 | $210.00 | $50.00 |
| 0015 | Aggregate base course (class 7) (303117) | TON | 2,307 | $30.00 | $32.00 | $60.00 | $52.80 | $91.52 | $58.00 |
| 0016 | Portland cement concrete base (6" uniform thickness) (309506) | SY | 65 | $110.00 | $150.00 | $150.00 | $138.00 | $197.78 | $240.00 |
| 0017 | Portland cement concrete base (8" uniform thickness) (309508) | SY | 40 | $130.00 | $175.00 | $210.00 | $174.00 | $300.89 | $360.00 |
| 0018 | Tack coat (401011) | GAL | 1,038 | $3.45 | $2.00 | $4.00 | $5.50 | $4.20 | $4.00 |
| 0019 | Mineral aggregate in achm binder course (1") (406161) | TON | 678 | $146.00 | $150.00 | $143.06 | $175.21 | $150.21 | $143.06 |
| 0020 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 35 | $120.00 | $850.00 | $120.00 | $195.43 | $126.00 | $120.00 |
| 0021 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,370 | $140.00 | $150.00 | $127.93 | $154.04 | $134.33 | $127.93 |
| 0022 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 10 | $120.00 | $850.00 | $120.00 | $144.00 | $126.00 | $120.00 |
| 0023 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 76 | $120.00 | $900.00 | $120.00 | $169.26 | $126.00 | $120.00 |
| 0024 | Cold milling asphalt pavement (412002) | SY | 533 | $20.50 | $25.00 | $23.00 | $26.11 | $19.70 | $18.76 |
| 0025 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 25 | $150.00 | $300.00 | $75.00 | $381.60 | $128.63 | $243.50 |
| 0026 | Achm patching of existing roadway (415011) | TON | 25 | $150.00 | $200.00 | $75.00 | $535.20 | $315.00 | $300.00 |
| 0027 | Approach slabs (504031) | CY | 136 | $800.00 | $800.00 | $680.00 | $1,068.53 | $1,100.15 | $1,150.00 |
| 0028 | Portland cement concrete driveway (505011) | SY | 412.92 | $100.00 | $100.00 | $110.00 | $152.62 | $158.69 | $177.00 |
| 0029 | Furnishing field office (602011) | EACH | 1 | $20,000 | $15,000 | $25,000 | $52,000 | $66,326 | $40,000 |
| 0030 | Maintenance of traffic (603009) | LS | 1 | $50,000 | $60,000 | $223,415 | $110,000 | $206,487 | $250,000 |
| 0031 | Signs (604003) | SF | 233 | $25.00 | $30.00 | $25.00 | $30.00 | $26.25 | $25.00 |
| 0032 | Barricades (604013) | LF | 80 | $25.00 | $40.00 | $25.00 | $30.00 | $26.25 | $25.00 |
| 0033 | Traffic drums (604023) | EACH | 32 | $65.00 | $80.00 | $65.00 | $78.00 | $68.25 | $65.00 |
| 0034 | Construction pavement markings (604041) | LF | 9,430 | $1.50 | $2.00 | $1.50 | $1.80 | $1.58 | $1.50 |
| 0035 | Removal of permanent pavement markings (604061) | LF | 1,420 | $3.00 | $3.50 | $3.00 | $3.60 | $3.15 | $3.00 |
| 0036 | Removal of permanent pavement markings (words) (604062) | EACH | 1 | $200.00 | $300.00 | $200.00 | $240.00 | $210.00 | $200.00 |
| 0037 | Removal of permanent pavement markings (arrows) (604063) | EACH | 1 | $200.00 | $300.00 | $200.00 | $240.00 | $210.00 | $200.00 |
| 0038 | Vertical panels (604083) | EACH | 32 | $75.00 | $100.00 | $75.00 | $90.00 | $78.75 | $75.00 |
| 0039 | Concrete ditch paving (type B) (605012) | SY | 194 | $100.00 | $125.00 | $130.00 | $180.40 | $177.65 | $205.00 |
| 0040 | 59" X 36" reinforced concrete arch pipe culverts (class III) (605763) | LF | 120 | $375.00 | $300.00 | $265.00 | $494.27 | $457.67 | $330.00 |
| 0041 | 18" side drain (606703) | LF | 96 | $60.00 | $80.00 | $80.00 | $94.32 | $145.31 | $115.00 |
| 0042 | Selected pipe bedding (606994) | CY | 555 | $70.00 | $2.00 | $8.00 | $68.59 | $93.26 | $72.95 |
| 0043 | Drop inlets (type C) (609013) | EACH | 8 | $10,000 | $15,000 | $11,500 | $10,995 | $16,476 | $21,200 |
| 0044 | Drop inlets (type MO) (609134) | EACH | 24 | $7,000.00 | $7,500.00 | $7,200.00 | $9,515.00 | $9,048.84 | $9,670.00 |
| 0045 | Drop inlet extensions (4') (609311) | EACH | 15 | $1,500.00 | $3,000.00 | $1,725.00 | $2,334.00 | $1,500.16 | $3,250.00 |
| 0046 | Drop inlet extensions (8') (609312) | EACH | 2 | $2,500.00 | $5,000.00 | $3,050.00 | $4,626.00 | $2,325.79 | $3,920.00 |
| 0047 | 4" pipe underdrains (611008) | LF | 500 | $5.00 | $15.00 | $4.85 | $60.66 | $15.93 | $12.31 |
| 0048 | Underdrain outlet protectors (611013) | EACH | 4 | $400.00 | $500.00 | $350.00 | $1,020.00 | $1,405.98 | $603.75 |
| 0049 | Pavement repair over culverts (asphalt) (615022) | TON | 30 | $425.00 | $300.00 | $225.00 | $390.00 | $315.00 | $335.00 |
| 0050 | Lime (620001) | TON | 2 | $95.00 | $1.00 | $95.00 | $162.00 | $99.75 | $95.00 |
| 0051 | Seeding (620011) | ACRE | 0.93 | $1,700.00 | $3,000.00 | $1,687.29 | $3,225.80 | $1,771.65 | $1,687.29 |
| 0052 | Mulch cover (620022) | ACRE | 8.08 | $1,125.00 | $2,000.00 | $1,124.68 | $1,935.48 | $1,180.91 | $1,124.68 |
| 0053 | Water (620030) | MGAL | 242.60 | $10.00 | $10.00 | $10.00 | $12.00 | $10.50 | $10.00 |
| 0054 | Temporary seeding (621001) | ACRE | 7.15 | $837.00 | $1,250.00 | $836.14 | $960.00 | $877.95 | $836.14 |
| 0055 | Silt fence (621021) | LF | 1,515 | $4.50 | $5.00 | $3.43 | $4.20 | $3.60 | $3.43 |
| 0056 | Sediment basin (621071) | CY | 20 | $4.00 | $5.00 | $10.00 | $18.00 | $50.36 | $5.50 |
| 0057 | Obliteration of sediment basin (621101) | CY | 20 | $4.00 | $5.00 | $10.00 | $12.00 | $50.36 | $11.00 |
| 0058 | Sediment removal and disposal (621111) | CY | 136 | $4.00 | $5.00 | $1.00 | $12.00 | $7.41 | $4.04 |
| 0059 | Rock ditch checks (621151) | CY | 98 | $70.00 | $75.00 | $100.00 | $112.04 | $174.59 | $145.00 |
| 0060 | Filter sock (12") (621168) | LF | 926 | $8.00 | $12.00 | $7.86 | $9.31 | $8.25 | $7.86 |
| 0061 | Wattle (20") (621173) | LF | 59 | $14.00 | $15.00 | $13.29 | $15.50 | $13.95 | $13.29 |
| 0062 | Second seeding application (623001) | ACRE | 0.93 | $377.00 | $1,500.00 | $375.69 | $1,548.00 | $394.47 | $375.69 |
| 0063 | Solid sodding (624001) | SY | 148 | $7.00 | $5.00 | $6.87 | $12.00 | $7.21 | $6.87 |
| 0064 | Concrete walks (633011) | SY | 889 | $100.00 | $115.00 | $100.00 | $118.54 | $109.67 | $160.00 |
| 0065 | Hand railing (633201) | LF | 381 | $85.00 | $100.00 | $125.00 | $154.78 | $95.14 | $135.00 |
| 0066 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 2,926 | $30.00 | $32.00 | $53.00 | $62.40 | $47.25 | $48.00 |
| 0067 | Roadway construction control (635001) | LS | 1 | $20,000 | $50,000 | $50,000 | $51,132 | $51,832 | $80,000 |
| 0068 | Bridge construction control (636001) | LS | 1 | $20,000 | $70,000 | $50,000 | $100,200 | $62,020 | $85,000 |
| 0069 | Wheelchair ramps (type 3) (641020) | SY | 195 | $350.00 | $200.00 | $150.00 | $373.38 | $158.04 | $285.00 |
| 0070 | Wheelchair ramps (type 4) (641021) | SY | 36 | $350.00 | $250.00 | $190.00 | $390.00 | $160.35 | $305.00 |
| 0071 | Galvanized steel conduit (1") (709001) | LF | 55 | $100.00 | $100.00 | $66.50 | $141.82 | $105.00 | $100.00 |
| 0072 | Non-metallic conduit (2") (710004) | LF | 750 | $35.00 | $30.00 | $23.35 | $37.64 | $28.88 | $27.50 |
| 0073 | Thermoplastic pavement marking white (6") (719002) | LF | 1,040 | $1.55 | $2.00 | $1.55 | $1.86 | $1.63 | $1.55 |
| 0074 | Thermoplastic pavement marking white (12") (719005) | LF | 45 | $10.00 | $15.00 | $10.00 | $12.00 | $10.50 | $10.00 |
| 0075 | Thermoplastic pavement marking yellow (6") (719102) | LF | 4,370 | $1.55 | $2.00 | $1.55 | $1.98 | $1.63 | $1.55 |
| 0076 | Thermoplastic pavement marking (words) (719201) | EACH | 3 | $300.00 | $500.00 | $300.00 | $360.00 | $315.00 | $300.00 |
| 0077 | Thermoplastic pavement marking (arrows) (719202) | EACH | 6 | $250.00 | $500.00 | $250.00 | $300.00 | $262.50 | $250.00 |
| 0078 | Raised pavement markers (type II) (721002) | EACH | 59 | $10.00 | $50.00 | $10.00 | $12.00 | $10.50 | $10.00 |
| 0079 | Unclassified excavation for structures-bridge (801001) | CY | 1,375 | $85.00 | $75.00 | $285.00 | $227.35 | $446.23 | $185.00 |
| 0080 | Unclassified excavation for structures-roadway (801101) | CY | 331 | $50.00 | $25.00 | $375.00 | $78.13 | $96.56 | $205.00 |
| 0081 | Class S concrete-roadway (802012) | CY | 78.13 | $800.00 | $1,100.00 | $3,200.00 | $2,150.26 | $2,755.19 | $1,950.00 |
| 0082 | Class S concrete-bridge (802112) | CY | 568.90 | $1,100.00 | $1,350.00 | $1,250.00 | $1,690.74 | $1,889.47 | $2,150.00 |
| 0083 | Class S(AE) concrete-bridge (802122) | CY | 852 | $1,100.00 | $1,350.00 | $1,500.00 | $1,757.07 | $2,076.14 | $2,985.00 |
| 0084 | Architectural finish (802229) | SF | 5,675 | $14.00 | $15.00 | $16.50 | $28.46 | $31.74 | $28.00 |
| 0085 | Staining concrete surfaces (802231) | SF | 7,043 | $12.00 | $15.00 | $15.00 | $17.93 | $5.90 | $4.92 |
| 0086 | Textured coating finish (802951) | SY | 287 | $35.00 | $25.00 | $78.00 | $102.74 | $31.36 | $26.13 |
| 0087 | Class 2 protective surface treatment (803004) | SY | 1,381.30 | $7.00 | $15.00 | $8.00 | $9.30 | $9.12 | $7.60 |
| 0088 | Reinforcing steel-roadway (grade 60) (804003) | LB | 23,573 | $1.75 | $2.00 | $2.50 | $2.89 | $3.11 | $2.30 |
| 0089 | Reinforcing steel-bridge (grade 60) (804013) | LB | 81,770 | $1.75 | $1.80 | $2.00 | $2.03 | $2.05 | $2.35 |
| 0090 | Epoxy coated reinforcing steel (grade 60) (804023) | LB | 264,540 | $2.00 | $2.00 | $1.50 | $1.86 | $1.76 | $2.25 |
| 0091 | Steel piling (HP 12X53) (805022) | LF | 388 | $135.00 | $150.00 | $115.25 | $313.92 | $170.04 | $205.00 |
| 0092 | Preboring (805504) | LF | 120 | $320.00 | $350.00 | $360.00 | $565.50 | $444.38 | $515.00 |
| 0093 | Exploratory holes (805531) | LF | 275 | $120.00 | $125.00 | $38.00 | $133.09 | $116.40 | $145.00 |
| 0094 | Metal bridge railing (type H2) (806021) | LF | 560 | $100.00 | $150.00 | $150.00 | $164.14 | $218.83 | $180.00 |
| 0095 | Transitional approach railing (806217) | EACH | 4 | $9,000.00 | $7,500.00 | $8,000.00 | $12,975 | $9,561.30 | $9,500.00 |
| 0096 | Structural steel in beam spans (A709, GR. 50W) (807017) | LB | 183,720 | $4.20 | $4.50 | $3.85 | $3.76 | $4.04 | $4.80 |
| 0097 | Painting structural steel (807301) | TON | 9.50 | $4,000.00 | $2,000.00 | $4,180.00 | $4,883.37 | $4,800.00 | $1,500.00 |
| 0098 | Elastomeric bearings (808002) | CUIN | 7,079 | $4.50 | $5.00 | $5.50 | $4.25 | $6.09 | $9.65 |
| 0099 | Silicone joint sealant (809015) | LF | 141 | $100.00 | $50.00 | $125.00 | $141.18 | $131.54 | $150.00 |
| 0100 | Bridge name plate (type D) (812004) | EACH | 1 | $500.00 | $1,000.00 | $500.00 | $3,240.00 | $882.44 | $2,800.00 |
| 0101 | Dewater/bypass pumping (815020) | LS | 1 | $20,000 | $3,000.00 | $19,200 | $60,000 | $20,160 | $19,200 |
| 0102 | Filter blanket (816003) | SY | 1,654 | $5.00 | $25.00 | $3.50 | $5.15 | $10.69 | $5.00 |
| 0103 | Dumped riprap (816111) | CY | 362 | $60.00 | $75.00 | $105.00 | $124.97 | $145.53 | $150.00 |
| 0104 | Foundation protection riprap (816131) | TON | 1,419 | $60.00 | $35.00 | $100.00 | $61.97 | $59.62 | $85.00 |
| 0105 | Bridge deck repair for polymer overlays (822011) | SF | 167 | $55.00 | $70.00 | $75.00 | $76.78 | $176.87 | $55.00 |
| 0106 | Polymer overlay (822020) | SY | 372 | $124.00 | $130.00 | $126.85 | $154.52 | $121.80 | $116.00 |
| 0107 | NEMA 4X stainless steel junction box (901213) | EACH | 8 | $4,000.00 | $1,000.00 | $2,616.00 | $3,960.00 | $3,465.00 | $3,300.00 |
| 0108 | 8" steel encasement pipe (903160) | LF | 150 | $85.00 | $150.00 | $145.90 | $126.48 | $153.20 | $145.90 |
| 0109 | 2" PVC SDR-17 water main (903302) | LF | 280 | $28.00 | $30.00 | $79.45 | $22.31 | $83.42 | $79.45 |
| 0110 | Ductile iron pipe water main fittings (904135) | LB | 66 | $30.00 | $25.00 | $125.00 | $126.00 | $131.25 | $125.00 |
| 0111 | 1" polyethylene service tubing (904140) | LF | 290 | $18.00 | $30.00 | $20.23 | $7.20 | $21.24 | $20.23 |
| 0112 | 2" gate valve with box (904147) | EACH | 1 | $850.00 | $1,500.00 | $1,479.13 | $2,916.89 | $1,553.09 | $1,479.13 |
| 0113 | Single water meter setting (inc. meter box and shut off valve) (904170) | EACH | 5 | $1,600.00 | $1,500.00 | $1,555.75 | $1,738.03 | $1,633.54 | $1,555.75 |
| 0114 | 8" PVC SDR-26 sewer main (904208) | LF | 520 | $78.00 | $80.00 | $190.52 | $92.51 | $200.05 | $190.52 |
| 0115 | Manhole, 0' to 6' depth (4' diameter) (904219) | EACH | 7 | $8,500.00 | $6,000.00 | $5,135.00 | $9,894.00 | $5,391.75 | $5,135.00 |
| 0116 | Manhole, extra depth (4' diameter) (904222) | LF | 19 | $350.00 | $300.00 | $220.80 | $540.00 | $231.84 | $220.80 |
| 0117 | Abandon existing manhole (904501) | EACH | 4 | $3,800.00 | $1,500.00 | $1,920.00 | $3,033.60 | $2,016.00 | $1,920.00 |
| 0118 | Fill abandoned sewer mains with flowable fill (abandon-in-place) (904937) | LF | 580 | $20.00 | $5.00 | $19.01 | $36.00 | $19.96 | $19.01 |
| 0119 | Fire hydrant assembly (904957) | EACH | 1 | $2,500.00 | $8,000.00 | $8,784.72 | $10,200 | $9,223.96 | $8,784.72 |
| 0120 | 1" service bore (905035) | LF | 240 | $85.00 | $60.00 | $56.90 | $78.00 | $59.75 | $56.90 |
| 0121 | 4" PVC sewer service line (911094) | LF | 340 | $32.00 | $30.00 | $57.58 | $72.88 | $60.46 | $57.58 |
| 0122 | (__)" blowoff assembly (915872) | EACH | 1 | $1,200.00 | $4,000.00 | $4,908.13 | $4,789.78 | $5,153.54 | $4,908.13 |
| 0123 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 862 | $80.00 | $98.89 | $143.77 | $155.00 | ||
| 0125 | 18" smooth spiral rib polymer precoated metallic coated corrugated steel pipe (605903) | LF | 862 | $65.00 | $85.00 | ||||
| 0126 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 132 | $80.00 | $131.61 | $130.00 | |||
| 0129 | 18" high density polyethylene pipe (605841) | LF | 132 | $50.00 | $70.00 | $99.00 | |||
| 0132 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 408 | $125.00 | $172.48 | $145.00 | |||
| 0135 | 24" high density polyethylene pipe (605842) | LF | 408 | $55.00 | $90.00 | $116.46 | |||
| 0138 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 388 | $150.00 | $175.52 | $195.00 | |||
| 0141 | 30" high density polyethylene pipe (605843) | LF | 388 | $65.00 | $125.00 | $162.22 | |||
| 0144 | 59" X 36" reinforced concrete arch pipe culverts (class III) (605763) | LF | 142 | $375.00 | $300.00 | $362.97 | $420.00 | ||
| 0145 | 57" X 38" smooth lined polymer precoated metallic coated corrugated steel arch pipe (605827) | LF | 142 | $320.00 | $492.00 | ||||
| 0147 | 30" flared end sections for reinforced concrete pipe culverts (605860) | EACH | 2 | $3,000.00 | $3,962.42 | $2,850.00 | |||
| 0148 | 30" flared end sections for corrugated steel pipe culverts (605861) | EACH | 2 | $1,500.00 | $1,750.00 | $2,013.60 | |||
| 0149 | 59" X 36" flared end sections for reinforced concrete arch pipe culverts (605891) | EACH | 1 | $8,000.00 | $8,000.00 | $10,107 | $5,420.00 | ||
| 0150 | 57" X 38" flared end sections for corrugated steel arch pipe culverts (605892) | EACH | 1 | $4,150.00 | $4,948.80 | ||||
| 0151 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $280,000 | $300,000 | $380,000 | $418,665 | $368,837 | $519,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.