ARDOT contract 100879 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO IMPROVE THE INTERSECTION AT PARKER ROAD AND HIGHWAY 49 IN CRAIGHEAD COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, REMOVAL AND DISPOSAL ITEMS, EARTHWORK, AGGREGATE BASE COURSE, PORTLAND CEMENT CONCRETE BASE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, PORTLAND CEMENT CONCRETE DRIVEWAY, MAINTENANCE OF TRAFFIC, CONCRETE DITCH PAVING, PAVEMENT REPAIR OVER CULVERTS, GUARDRAIL, EROSION CONTROL, CONCRETE ISLAND, WALKS, HAND RAILING, CURB AND GUTTER, WHEELCHAIR RAMPS, TRAFFIC SIGNAL ITEMS, PAVEMENT MARKINGS AND MISC. ITEMS. Let by Arkansas DOT on June 25, 2025, Craighead. 4 bids received; low bid $5,984,874 by Rogers Group, Inc..
- Owner
- Arkansas DOT
- Letting
- 25 JUN 2025
- Pay items
- 141
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rogers Group, Inc. | $5,984,874 | Low |
| 2 | White River Materials, Inc. | $6,888,767 | +15% |
| 3 | R.L. Persons Construction, Inc. | $6,899,999 | +15% |
| 4 | Richard Baughn Construction, Inc. | $8,870,484 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rogers Group, Inc. | 2. White River Materials, Inc. | 3. R.L. Persons Construction, Inc. | 4. Richard Baughn Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201011) | STA | 5 | $2,600.00 | $995.01 | $2,865.00 | $2,500.00 |
| 0002 | Grubbing (201111) | STA | 5 | $2,600.00 | $2,017.74 | $2,705.00 | $2,500.00 |
| 0003 | Removal and disposal of curb and gutter (202003) | LF | 3,284 | $18.75 | $9.81 | $31.50 | $18.00 |
| 0004 | Removal and disposal of concrete islands (202047) | SY | 57 | $41.75 | $110.30 | $30.85 | $30.00 |
| 0005 | Removal and disposal of concrete driveways (202062) | SY | 1,706 | $21.00 | $25.15 | $32.40 | $15.00 |
| 0006 | Removal and disposal of walks (202072) | SY | 292 | $55.00 | $24.18 | $21.65 | $22.00 |
| 0007 | Removal and disposal of drop inlets (202093) | EACH | 8 | $3,130.00 | $2,232.50 | $1,375.00 | $4,000.00 |
| 0008 | Removal and disposal of pipe culverts (202096) | EACH | 14 | $2,000.00 | $549.53 | $781.50 | $2,800.00 |
| 0009 | Removal and disposal of concrete ditch paving (202125) | SY | 1,390 | $21.00 | $38.45 | $20.50 | $12.00 |
| 0010 | Removal and disposal of signs (202191) | EACH | 27 | $515.00 | $235.27 | $460.00 | $1,800.00 |
| 0011 | Removal and disposal of mailboxes (202200) | EACH | 3 | $155.00 | $190.18 | $210.00 | $25.00 |
| 0012 | Unclassified excavation (210213) | CY | 7,236 | $39.00 | $33.38 | $48.50 | $46.00 |
| 0013 | Compacted embankment (210611) | CY | 8,677 | $46.00 | $36.44 | $44.00 | $46.00 |
| 0014 | Soil stabilization (210702) | TON | 50 | $415.00 | $498.23 | $520.00 | $285.00 |
| 0015 | Aggregate base course (class 7) (303117) | TON | 5,208 | $52.00 | $68.94 | $48.80 | $48.50 |
| 0016 | Portland cement concrete base (5" uniform thickness) (309505) | SY | 56 | $114.00 | $315.59 | $170.00 | $155.00 |
| 0017 | Portland cement concrete base (6" uniform thickness) (309506) | SY | 49 | $98.00 | $346.09 | $202.00 | $187.00 |
| 0018 | Tack coat (401011) | GAL | 6,548 | $1.00 | $4.25 | $6.50 | $5.50 |
| 0019 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 2,185 | $90.00 | $104.06 | $160.00 | $114.92 |
| 0020 | Asphalt binder (PG 64-22) in achm base course (1 1/2") (minimum bid $120.00) (405402) | TON | 58 | $600.00 | $120.00 | $155.00 | $120.00 |
| 0021 | Asphalt binder (PG 70-22) in achm base course (1 1/2") (minimum bid $120.00) (405412) | TON | 27 | $700.00 | $120.00 | $155.00 | $238.00 |
| 0022 | Mineral aggregate in achm binder course (1") (406161) | TON | 1,473 | $95.00 | $107.69 | $165.00 | $117.78 |
| 0023 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 38 | $600.00 | $120.00 | $155.00 | $120.00 |
| 0024 | Asphalt binder (PG 70-22) in achm binder course (1") (minimum bid $120.00) (406412) | TON | 25 | $700.00 | $120.00 | $155.00 | $250.00 |
| 0025 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 6,193 | $100.00 | $124.55 | $175.00 | $125.10 |
| 0026 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 10 | $600.00 | $120.00 | $155.00 | $120.00 |
| 0027 | Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442) | TON | 198 | $700.00 | $120.00 | $155.00 | $240.00 |
| 0028 | Asphalt binder (PG 76-22) in achm surface course (1/2") (minimum bid $120.00) (407452) | TON | 146 | $800.00 | $120.00 | $155.00 | $310.00 |
| 0029 | Cold milling asphalt pavement (412002) | SY | 2,375 | $6.00 | $6.53 | $29.75 | $6.50 |
| 0030 | Portland cement concrete driveway (505011) | SY | 1,467.89 | $150.00 | $176.62 | $165.00 | $194.47 |
| 0031 | Furnishing field office (602011) | EACH | 1 | $100,000 | $66,969 | $40,000 | $90,000 |
| 0032 | Maintenance of traffic (603010) | LS | 1 | $220,000 | $749,640 | $266,731 | $875,000 |
| 0033 | Signs (604003) | SF | 397 | $7.00 | $7.00 | $9.00 | $14.00 |
| 0034 | Traffic drums (604023) | EACH | 229 | $20.00 | $20.00 | $48.00 | $40.00 |
| 0035 | Construction pavement markings (604041) | LF | 26,975 | $0.40 | $0.40 | $0.49 | $0.42 |
| 0036 | Construction pavement markings (words) (604045) | EACH | 6 | $105.00 | $100.00 | $218.00 | $104.00 |
| 0037 | Construction pavement markings (arrows) (604046) | EACH | 11 | $105.00 | $100.00 | $180.00 | $104.00 |
| 0038 | Vertical panels (604083) | EACH | 10 | $33.00 | $25.00 | $41.00 | $34.00 |
| 0039 | Concrete ditch paving (type B) (605012) | SY | 617 | $85.00 | $192.07 | $175.00 | $214.26 |
| 0040 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 8 | $155.00 | $395.51 | $285.00 | $220.00 |
| 0041 | 30" reinforced concrete pipe culverts (class III) (605611) | LF | 20 | $200.00 | $286.84 | $215.00 | $240.00 |
| 0042 | 30" flared end sections for reinforced concrete pipe culverts (605860) | EACH | 1 | $3,000.00 | $3,161.58 | $2,150.00 | $3,400.00 |
| 0043 | 24" side drain (606704) | LF | 76 | $130.00 | $81.30 | $130.00 | $140.00 |
| 0044 | Selected pipe bedding (606994) | CY | 120 | $45.00 | $0.21 | $32.50 | $40.00 |
| 0045 | Drop inlets (type MO) (609134) | EACH | 12 | $10,200 | $12,770 | $5,785.00 | $4,850.00 |
| 0046 | Drop inlets (type ST) (609138) | EACH | 4 | $11,200 | $6,958.90 | $7,335.00 | $5,400.00 |
| 0047 | Junction boxes (type ST) (609236) | EACH | 1 | $13,200 | $6,762.05 | $7,050.00 | $6,500.00 |
| 0048 | Drop inlet extensions (4') (609311) | EACH | 4 | $4,300.00 | $3,350.00 | $1,730.00 | $4,500.00 |
| 0049 | Drop inlet extensions (8') (609312) | EACH | 3 | $2,900.00 | $4,410.00 | $1,960.00 | $8,000.00 |
| 0050 | Pavement repair over culverts (asphalt) (615022) | TON | 53 | $320.00 | $269.03 | $1,235.00 | $375.00 |
| 0051 | Guardrail (type A) (617005) | LF | 300 | $30.00 | $35.00 | $38.40 | $32.00 |
| 0052 | Guardrail terminal (type 2) (617312) | EACH | 4 | $3,000.00 | $3,500.00 | $3,850.00 | $3,400.00 |
| 0053 | Lime (620001) | TON | 6 | $100.00 | $100.00 | $128.00 | $107.50 |
| 0054 | Seeding (620011) | ACRE | 2.87 | $1,500.00 | $1,500.00 | $1,920.00 | $1,612.50 |
| 0055 | Mulch cover (620022) | ACRE | 5.74 | $1,000.00 | $1,000.00 | $1,280.00 | $1,075.00 |
| 0056 | Water (620030) | MGAL | 357.30 | $10.00 | $10.00 | $12.80 | $10.75 |
| 0057 | Temporary seeding (621001) | ACRE | 2.87 | $750.00 | $750.00 | $960.00 | $1,612.50 |
| 0058 | Silt fence (621021) | LF | 5,310 | $3.25 | $3.25 | $4.20 | $3.49 |
| 0059 | Sand bag ditch checks (621031) | BAG | 858 | $10.00 | $10.00 | $12.80 | $10.75 |
| 0060 | Sediment removal and disposal (621111) | CY | 280 | $11.00 | $0.22 | $73.35 | $2.50 |
| 0061 | Rock ditch checks (621151) | CY | 102 | $130.00 | $84.29 | $115.00 | $125.00 |
| 0062 | Filter sock (12") (621168) | LF | 276 | $9.00 | $8.82 | $11.30 | $9.48 |
| 0063 | Second seeding application (623001) | ACRE | 2.87 | $350.00 | $350.00 | $450.00 | $376.25 |
| 0064 | Solid sodding (624001) | SY | 476 | $5.25 | $10.04 | $9.10 | $5.64 |
| 0065 | Concrete island (632011) | SY | 295 | $160.00 | $185.00 | $260.00 | $210.98 |
| 0066 | Concrete walks (633011) | SY | 1,031 | $112.00 | $166.56 | $110.00 | $175.25 |
| 0067 | Hand railing (633201) | LF | 573 | $210.00 | $180.83 | $150.00 | $160.00 |
| 0068 | Concrete curb (type B) (634102) | LF | 500 | $43.00 | $86.33 | $70.15 | $48.00 |
| 0069 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 2,798 | $32.00 | $32.94 | $49.75 | $45.00 |
| 0070 | Roadway construction control (635001) | LS | 1 | $100,000 | $365,403 | $79,500 | $600,000 |
| 0071 | Mailboxes (637001) | EACH | 2 | $50.00 | $50.00 | $65.00 | $175.00 |
| 0072 | Mailbox supports (double) (637018) | EACH | 1 | $185.00 | $140.00 | $250.00 | $240.00 |
| 0073 | Wheelchair ramps (type 1) (641018) | SY | 77 | $430.00 | $269.97 | $150.00 | $290.22 |
| 0074 | Wheelchair ramps (type 2) (641019) | SY | 11 | $475.00 | $786.41 | $305.00 | $845.39 |
| 0075 | Wheelchair ramps (type 3) (641020) | SY | 33 | $475.00 | $794.67 | $435.00 | $854.27 |
| 0076 | Wheelchair ramps (type 4) (641021) | SY | 47 | $430.00 | $744.13 | $330.00 | $799.94 |
| 0077 | System local controller TS2-type 2, E-net (8 phases) (701227) | EACH | 2 | $45,000 | $43,500 | $56,500 | $46,763 |
| 0078 | Ethernet switch, T100 hardened (8-port) (701722) | EACH | 2 | $4,100.00 | $4,000.00 | $5,200.00 | $4,300.00 |
| 0079 | E-net cable (exterior cat 5E) (701751) | LF | 225 | $4.20 | $4.00 | $5.20 | $4.30 |
| 0080 | Local radio (E-net 5.8) with antenna (702304) | EACH | 1 | $4,100.00 | $4,000.00 | $5,200.00 | $4,300.00 |
| 0081 | Local radio with antenna relocation (702309) | EACH | 1 | $1,000.00 | $1,000.00 | $1,300.00 | $1,075.00 |
| 0082 | Battery backup system (702335) | EACH | 1 | $12,200 | $12,000 | $15,600 | $12,900 |
| 0083 | Traffic signal head, LED, (3 section, 1 way) (706039) | EACH | 23 | $1,450.00 | $1,400.00 | $1,820.00 | $1,505.00 |
| 0084 | Traffic signal head, LED, (4 section, 1 way) (706043) | EACH | 4 | $1,650.00 | $1,600.00 | $2,100.00 | $1,720.00 |
| 0085 | Central control unit (707006) | EACH | 1 | $4,600.00 | $4,500.00 | $5,850.00 | $4,837.50 |
| 0086 | Pole mounted assembly (707007) | EACH | 8 | $1,250.00 | $1,200.00 | $1,600.00 | $1,290.00 |
| 0087 | Countdown pedestrian signal head, LED (707015) | EACH | 8 | $1,250.00 | $1,200.00 | $1,600.00 | $1,290.00 |
| 0088 | Traffic signal cable (5C/12 A.W.G.) (708007) | LF | 1,536 | $4.15 | $4.00 | $5.20 | $4.30 |
| 0089 | Traffic signal cable (5C/14 A.W.G.) (708008) | LF | 2,725 | $3.90 | $3.75 | $4.90 | $4.03 |
| 0090 | Traffic signal cable (7C/14 A.W.G.) (708012) | LF | 1,810 | $4.60 | $4.50 | $5.85 | $4.84 |
| 0091 | Traffic signal cable (12C/14 A.W.G.) (708022) | LF | 167 | $5.15 | $5.00 | $6.50 | $5.38 |
| 0092 | Traffic signal cable (20C/14 A.W.G.) (708038) | LF | 756 | $7.20 | $6.95 | $9.00 | $7.47 |
| 0093 | Electrical conductors-in-conduit (1C/8 A.W.G., E.G.C.) (708207) | LF | 828 | $1.55 | $1.50 | $1.95 | $1.61 |
| 0094 | Electrical conductors-in-conduit (1C/12 A.W.G., E.G.C.) (708211) | LF | 378 | $1.55 | $1.50 | $1.95 | $1.61 |
| 0095 | Electrical conductors-in-conduit (2C/6 A.W.G.) (708217) | LF | 130 | $4.10 | $4.00 | $5.20 | $4.30 |
| 0096 | Electrical conductors for luminaires (708451) | LF | 1,067 | $2.30 | $2.25 | $2.95 | $2.42 |
| 0097 | Galvanized steel conduit (2") (709004) | LF | 60 | $31.00 | $30.00 | $39.00 | $32.25 |
| 0098 | Galvanized steel conduit (3") (709005) | LF | 66 | $51.00 | $50.00 | $65.00 | $53.75 |
| 0099 | Non-metallic conduit (2") (710004) | LF | 200 | $21.00 | $20.00 | $26.00 | $21.50 |
| 0100 | Non-metallic conduit (3") (710005) | LF | 732 | $35.60 | $35.00 | $46.00 | $37.63 |
| 0101 | Concrete pull box (type 3) (711005) | EACH | 2 | $2,500.00 | $2,400.00 | $3,120.00 | $2,580.00 |
| 0102 | Concrete pull box (type 1 HD) (711104) | EACH | 1 | $2,050.00 | $2,000.00 | $2,600.00 | $2,150.00 |
| 0103 | Concrete pull box (type 2 HD) (711105) | EACH | 5 | $2,600.00 | $2,500.00 | $3,250.00 | $2,687.50 |
| 0104 | Concrete pull box (type 3 HD) (711106) | EACH | 1 | $2,800.00 | $2,750.00 | $3,575.00 | $2,956.25 |
| 0105 | Span wire assembly (713011) | EACH | 1 | $9,400.00 | $9,000.00 | $11,700 | $9,675.00 |
| 0106 | Traffic signal mast arm and pole with foundation (44') (714044) | EACH | 1 | $48,000 | $46,000 | $59,750 | $49,450 |
| 0107 | Traffic signal mast arm and pole with foundation (60') (714060) | EACH | 1 | $50,000 | $48,000 | $62,500 | $51,600 |
| 0108 | Traffic signal mast arm and pole with foundation (64') (714064) | EACH | 1 | $54,000 | $52,000 | $67,500 | $55,900 |
| 0109 | Traffic signal mast arm and pole with foundation (70') (714070) | EACH | 1 | $58,000 | $56,000 | $72,800 | $60,200 |
| 0110 | LED luminaire assembly (714724) | EACH | 4 | $1,250.00 | $1,200.00 | $1,560.00 | $1,290.00 |
| 0111 | Traffic signal pedestal pole with foundation (715011) | EACH | 3 | $6,200.00 | $6,000.00 | $7,795.00 | $6,450.00 |
| 0112 | Service point assembly (2 circuits) (715102) | EACH | 1 | $5,700.00 | $5,500.00 | $7,145.00 | $5,912.50 |
| 0113 | Removal of traffic signal equipment (715704) | LS | 1 | $16,500 | $16,000 | $20,750 | $17,200 |
| 0114 | Treated wood pole (class 2, 45') (716245) | EACH | 4 | $9,400.00 | $9,000.00 | $11,700 | $9,675.00 |
| 0115 | Reflectorized paint pavement marking white (12") (718005) | LF | 464 | $8.00 | $7.50 | $6.40 | $8.06 |
| 0116 | Reflectorized paint pavement marking yellow (12") (718105) | LF | 247 | $8.00 | $7.50 | $5.80 | $8.06 |
| 0117 | Thermoplastic pavement marking white (6") (719002) | LF | 11,479 | $0.90 | $0.85 | $1.55 | $0.91 |
| 0118 | Thermoplastic pavement marking white (12") (719005) | LF | 1,796 | $5.75 | $5.50 | $10.25 | $5.91 |
| 0119 | Thermoplastic pavement marking yellow (6") (719102) | LF | 11,436 | $0.90 | $0.85 | $1.55 | $0.91 |
| 0120 | Thermoplastic pavement marking yellow (12") (719105) | LF | 85 | $7.40 | $7.00 | $10.25 | $7.53 |
| 0121 | Thermoplastic pavement marking (words) (719201) | EACH | 26 | $300.00 | $285.00 | $450.00 | $306.38 |
| 0122 | Thermoplastic pavement marking (arrows) (719202) | EACH | 28 | $280.00 | $265.00 | $385.00 | $284.88 |
| 0123 | Raised pavement markers (type II) (721002) | EACH | 187 | $5.25 | $5.00 | $13.00 | $5.38 |
| 0124 | 18" street name sign (726012) | EACH | 4 | $1,030.00 | $1,000.00 | $1,300.00 | $1,075.00 |
| 0125 | Video detector (IP) (733008) | EACH | 6 | $6,200.00 | $6,000.00 | $7,795.00 | $6,450.00 |
| 0126 | Hybrid video/radar detector (733009) | EACH | 2 | $12,500 | $12,000 | $15,500 | $12,900 |
| 0127 | Video cable (exterior cat 5E) (733035) | LF | 2,277 | $4.15 | $4.00 | $5.20 | $4.30 |
| 0128 | Video monitor (CLR) (733042) | EACH | 2 | $1,025.00 | $1,000.00 | $1,300.00 | $1,075.00 |
| 0129 | Central control unit (8 channel) (733105) | EACH | 2 | $41,000 | $40,000 | $51,955 | $43,000 |
| 0130 | Unclassified excavation for structures-roadway (801101) | CY | 573 | $125.00 | $60.00 | $92.85 | $600.00 |
| 0131 | Class S concrete-roadway (802012) | CY | 271.17 | $1,500.00 | $1,743.12 | $1,675.00 | $3,500.00 |
| 0132 | Architectural finish (802229) | SF | 3,325 | $27.00 | $26.00 | $7.30 | $50.00 |
| 0133 | Textured coating finish (802951) | SY | 1,094 | $28.00 | $12.64 | $33.25 | $225.00 |
| 0134 | Reinforcing steel-roadway (grade 60) (804003) | LB | 27,157 | $2.15 | $2.95 | $1.30 | $3.00 |
| 0135 | 18" reinforced concrete pipe culverts (class III) (605601) | LF | 576 | $130.00 | $127.00 | $220.00 | |
| 0138 | 18" high density polyethylene pipe (605841) | LF | 576 | $136.02 | |||
| 0140 | 24" reinforced concrete pipe culverts (class III) (605606) | LF | 832 | $135.00 | $174.44 | $145.00 | $260.00 |
| 0142 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 7 | $2,250.00 | $1,450.00 | $3,000.00 | |
| 0143 | 18" flared end sections for corrugated steel pipe culverts (605857) | EACH | 7 | $1,631.58 | |||
| 0144 | 24" flared end sections for reinforced concrete pipe culverts (605858) | EACH | 3 | $1,350.00 | $2,001.88 | $1,715.00 | $0.00 |
| 0146 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $260,000 | $302,396 | $325,000 | $400,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of June 25, 2025. Compiled by Mirage Metrics.