| 0005 | Mobilization (0101-1) | LS | 1 | $414,521 | $814,229 | $638,500 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $406,610 | $367,758 | $380,500 |
| 0015 | Special detour- temporary pavement (0102-2200) | SY | 1 | $82,516 | $172,025 | $160,000 |
| 0020 | Special detour- temporary earthwork/base (0102-2300) | CY | 1 | $54,679 | $67,513 | $63,750 |
| 0025 | Traffic control officer (0102-14) | HR | 76 | $127.82 | $109.06 | $122.50 |
| 0030 | Work zone sign (0102-60) | ED | 10,870 | $0.27 | $0.27 | $0.30 |
| 0035 | Business sign (0102-61) | EACH | 6 | $130.43 | $25.79 | $325.00 |
| 0040 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 960 | $53.48 | $43.32 | $53.00 |
| 0045 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 14,120 | $0.13 | $0.12 | $0.15 |
| 0050 | Temporary separator, F&I remove (0102-75-1) | LF | 645 | $27.39 | $36.10 | $27.00 |
| 0055 | Arrow board / advance warning arrow panel (0102-76) | ED | 660 | $6.52 | $0.46 | $6.45 |
| 0060 | Portable changeable message sign, temporary (0102-99) | ED | 856 | $13.04 | $11.35 | $12.85 |
| 0065 | Sediment barrier (0104-10-3) | LF | 1,128 | $1.96 | $3.60 | $8.80 |
| 0070 | Inlet protection system (0104-18) | EACH | 22 | $228.26 | $170.33 | $320.00 |
| 0075 | Litter removal (0107-1) | ACRE | 13.16 | $71.74 | $82.51 | $65.00 |
| 0080 | Mowing (0107-2) | ACRE | 13.20 | $71.74 | $103.14 | $260.00 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $79,551 | $505,477 | $270,000 |
| 0090 | Removal of existing concrete (0110-4-10) | SY | 1,031 | $52.17 | $71.43 | $125.00 |
| 0095 | Tree root and branch pruning (0110-22) | EACH | 4 | $3,912.96 | $2,905.34 | $2,600.00 |
| 0100 | Tree removal (0110-23) | EACH | 1 | $6,521.61 | $2,408.41 | $3,900.00 |
| 0105 | Regular excavation (0120-1) | CY | 216.30 | $91.30 | $159.46 | $127.00 |
| 0110 | Embankment (0120-6) | CY | 66.10 | $78.26 | $159.46 | $490.00 |
| 0115 | Type B stabilization (0160-4) | SY | 1,712 | $32.61 | $70.32 | $27.50 |
| 0120 | Optional base, base group 10 (0285-710) | SY | 1,712 | $71.83 | $63.35 | $72.50 |
| 0125 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 5,902 | $12.22 | $4.30 | $6.00 |
| 0130 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 8,458 | $11.64 | $11.45 | $8.50 |
| 0135 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 10,559 | $7.90 | $4.40 | $5.90 |
| 0140 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 1,270.30 | $258.02 | $192.00 | $217.00 |
| 0145 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 2,153.70 | $247.04 | $235.40 | $213.00 |
| 0150 | Inlets, curb type P-1, partial (0425-1315) | EACH | 1 | $20,869 | $15,425 | $19,500 |
| 0155 | Inlets, curb, type P-5, partial (0425-1355) | EACH | 1 | $22,173 | $15,662 | $15,750 |
| 0160 | Inlets, curb, type P-6, modify (0425-1369) | EACH | 2 | $15,652 | $10,657 | $20,500 |
| 0165 | Manhole, adjust (0425-5) | EACH | 3 | $3,912.96 | $1,563.08 | $6,000.00 |
| 0170 | Pipe culvert,optional material,round, 15"S/CD (0430-175115) | LF | 38 | $313.04 | $307.25 | $360.00 |
| 0175 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 11 | $489.12 | $342.77 | $850.00 |
| 0180 | Pipe culvert, opt material, round, 42"S/CD (0430-175142) | LF | 150 | $749.98 | $787.22 | $1,355.00 |
| 0185 | Pipe culvert, opt material, round, 48"S/CD (0430-175148) | LF | 591 | $978.24 | $838.00 | $1,200.00 |
| 0190 | Cleaning & sealing existing pipe joint, 18" storm sewer (0430-821-25) | EACH | 3 | $23,478 | $928.27 | $1,160.00 |
| 0195 | Cleaning & sealing existing pipe joint, 30" storm sewer (0430-821-33) | EACH | 1 | $32,608 | $1,340.83 | $1,700.00 |
| 0200 | PVC pipe, 6 inch (0430-964-7) | LF | 12 | $352.17 | $224.68 | $675.00 |
| 0205 | Pipe liner, cured in place, 18" (0431-1118) | LF | 107 | $182.61 | $144.40 | $180.00 |
| 0210 | Pipe liner, cured in place, 42" (0431-1142) | LF | 460 | $456.51 | $360.99 | $450.00 |
| 0215 | Concrete curb & gutter, type F (0520-1-10) | LF | 1,755 | $49.56 | $55.59 | $53.25 |
| 0220 | Valley gutter- concrete (0520-3) | LF | 391 | $50.87 | $64.99 | $148.75 |
| 0225 | Traffic separator concrete- type I, 4' wide (0520-5-11) | LF | 336 | $67.17 | $64.60 | $192.35 |
| 0230 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 611 | $76.63 | $85.85 | $87.55 |
| 0235 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 126 | $85.63 | $128.25 | $261.50 |
| 0240 | Detectable warnings (0527-2) | SF | 282 | $50.22 | $30.32 | $66.50 |
| 0245 | Performance turf, sod (0570-1-2) | SY | 349 | $15.11 | $10.07 | $33.25 |
| 0250 | Raised pavement marker, type B (0706-1-3) | EACH | 1,377 | $5.22 | $5.16 | $5.15 |
| 0255 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 3.36 | $2,934.72 | $1,080.72 | $2,900.00 |
| 0260 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 844 | $2.22 | $2.06 | $2.20 |
| 0265 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 50 | $2.48 | $2.06 | $2.45 |
| 0270 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.32 | $1,010.85 | $618.84 | $1,000.00 |
| 0275 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 12 | $65.22 | $30.94 | $64.40 |
| 0280 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 1.21 | $2,934.72 | $1,082.98 | $2,900.00 |
| 0285 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.01 | $1,010.85 | $687.78 | $1,000.00 |
| 0290 | Two component polyurethane injection (0906-173200) | LB | 1,736 | $19.56 | $15.47 | $19.50 |
| 0295 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 |
| 0300 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 15 | $684.77 | $541.49 | $445.00 |
| 0305 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 4 | $2,217.35 | $1,753.40 | $2,300.00 |
| 0310 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $2,869.51 | $2,269.11 | $3,000.00 |
| 0315 | Single column ground sign assembly, remove (0700-1600) | EACH | 16 | $52.17 | $41.26 | $64.50 |
| 0320 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 8 | $163.04 | $128.93 | $110.00 |
| 0325 | Delineator, flexible tubular (0705-11-1) | EACH | 3 | $326.08 | $103.14 | $155.00 |
| 0330 | Raised pavement marker, type B (0706-1-3) | EACH | 724 | $4.96 | $5.16 | $4.90 |
| 0335 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 9 | $26.09 | $5.16 | $26.00 |
| 0340 | Painted pavement markings, surface (0710-90) | LS | 1 | $19,681 | $14,955 | $19,350 |
| 0345 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 2,142 | $4.57 | $5.16 | $4.50 |
| 0350 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 411 | $6.52 | $6.19 | $6.40 |
| 0355 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 118 | $9.13 | $7.22 | $9.00 |
| 0360 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.08 | $4,565.13 | $2,776.92 | $4,500.00 |
| 0365 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 30 | $6.52 | $6.19 | $6.45 |
| 0370 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.11 | $3,260.80 | $2,985.70 | $3,500.00 |
| 0375 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 884 | $22.17 | $15.47 | $22.00 |
| 0380 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 51 | $423.90 | $618.85 | $417.00 |
| 0385 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 1.14 | $7,173.77 | $6,366.58 | $7,100.00 |
| 0390 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.24 | $9,567.20 | $1,985.15 | $9,500.00 |
| 0395 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 1.52 | $1,793.44 | $2,050.60 | $2,000.00 |
| 0400 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.80 | $7,173.77 | $6,386.77 | $7,000.00 |
| 0405 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 2 | $2,608.64 | $1,005.63 | $2,565.00 |
| 0410 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $1,956.48 | $3,604.78 | $1,925.00 |
| 0415 | Conduit, furnish & install, open trench (0630-2-11) | LF | 72 | $71.74 | $25.79 | $71.00 |
| 0420 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 420 | $71.74 | $128.93 | $71.00 |
| 0425 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $39,130 | $33,542 | $38,500 |
| 0430 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $3,586.88 | $10,056 | $3,530.00 |
| 0435 | Fiber optic cable, relocate, underground (0633-1420) | LF | 50 | $11.74 | $9.28 | $11.55 |
| 0440 | Fiber optic connection, install, splice (0633-2-31) | EACH | 12 | $71.74 | $59.82 | $71.00 |
| 0445 | Fiber optic connection hardware, F&I, splice tray (0633-3-12) | EACH | 1 | $78.26 | $773.56 | $77.00 |
| 0450 | Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13) | EACH | 12 | $91.30 | $97.98 | $90.00 |
| 0455 | Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16) | EACH | 1 | $2,282.56 | $1,727.61 | $2,245.00 |
| 0460 | Fiber optic cable locator (0633-6) | DA | 200 | $260.86 | $67.04 | $257.00 |
| 0465 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 8 | $2,608.64 | $1,005.63 | $2,565.00 |
| 0470 | Electrical service wire, & install (0639-2-1) | LF | 20 | $15.65 | $3.76 | $15.40 |
| 0475 | Electrical service wire, (0639-2-6) | LF | 20 | $0.78 | $1.29 | $1.00 |
| 0480 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 18 | $2,934.72 | $1,232.54 | $2,890.00 |
| 0485 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 18 | $326.08 | $386.78 | $321.00 |
| 0490 | Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11) | EACH | 2 | $14,021 | $9,681.86 | $13,785 |
| 0495 | Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12) | EACH | 8 | $15,000 | $9,978.91 | $14,750 |
| 0500 | Vehicle detection system- remove (0660-4-60) | EACH | 1 | $1,304.32 | $2,851.85 | $1,285.00 |
| 0505 | Traffic controller assembly, F&I, NEMA, 1 preemption (0670-5111) | AS | 1 | $78,259 | $50,442 | $76,935 |
| 0510 | Traffic controller assembly, remove controller with (0670-5600) | AS | 1 | $2,543.43 | $2,836.38 | $2,500.00 |
| 0515 | ITS CCTV camera, F&I, dome PTZ enclosure - pressurized, IP, definition (0682-1113) | EACH | 1 | $10,500 | $8,777.31 | $10,325 |
| 0520 | ITS CCTV camera, remove & disposal (0682-1600) | EACH | 1 | $586.94 | $1,005.63 | $580.00 |
| 0525 | Managed field ethernet switch, furnish & install (0684-1-1) | EACH | 1 | $9,782.41 | $7,565.40 | $9,620.00 |
| 0530 | Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14) | EACH | 1 | $14,348 | $9,649.89 | $14,105 |
| 0535 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 1 | $1,369.54 | $1,005.63 | $1,350.00 |
| 0540 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 1 | $260.86 | $180.50 | $257.00 |
| 0545 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 4 | $10,369 | $3,258.23 | $10,200 |
| 0550 | Internally illuminated sign, remove (0700-5-60) | EACH | 4 | $717.38 | $1,005.63 | $705.00 |