FDOT contract T1893 bid tabulation

SR 72 (CLARK RD) FROM HONROE AVE TO W OF GANTT RD. Let by Florida DOT on February 26, 2025, Sarasota, District 1. 3 bids received; low bid $4,641,884 by Ajax Paving Industries of Florida LLC.

Owner
Florida DOT
Letting
26 FEB 2025
Pay items
110
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ajax Paving Industries of Florida LLC$4,641,884Low
2Preferred Materials Inc.$4,973,058+7.0%
3Superior Asphalt, Inc.$5,265,397+13%
FDOT contract T1893: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ajax Paving Industries of Florida LLC2. Preferred Materials Inc.3. Superior Asphalt, Inc.
0005Mobilization (0101-1)LS1$414,521$814,229$638,500
0010Maintenance of traffic (0102-1)DA1$406,610$367,758$380,500
0015Special detour- temporary pavement (0102-2200)SY1$82,516$172,025$160,000
0020Special detour- temporary earthwork/base (0102-2300)CY1$54,679$67,513$63,750
0025Traffic control officer (0102-14)HR76$127.82$109.06$122.50
0030Work zone sign (0102-60)ED10,870$0.27$0.27$0.30
0035Business sign (0102-61)EACH6$130.43$25.79$325.00
0040Temporary barrier, F&I, low profile, concrete (0102-71-13)LF960$53.48$43.32$53.00
0045Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED14,120$0.13$0.12$0.15
0050Temporary separator, F&I remove (0102-75-1)LF645$27.39$36.10$27.00
0055Arrow board / advance warning arrow panel (0102-76)ED660$6.52$0.46$6.45
0060Portable changeable message sign, temporary (0102-99)ED856$13.04$11.35$12.85
0065Sediment barrier (0104-10-3)LF1,128$1.96$3.60$8.80
0070Inlet protection system (0104-18)EACH22$228.26$170.33$320.00
0075Litter removal (0107-1)ACRE13.16$71.74$82.51$65.00
0080Mowing (0107-2)ACRE13.20$71.74$103.14$260.00
0085Clearing & grubbing (0110-1-1)ACRE1$79,551$505,477$270,000
0090Removal of existing concrete (0110-4-10)SY1,031$52.17$71.43$125.00
0095Tree root and branch pruning (0110-22)EACH4$3,912.96$2,905.34$2,600.00
0100Tree removal (0110-23)EACH1$6,521.61$2,408.41$3,900.00
0105Regular excavation (0120-1)CY216.30$91.30$159.46$127.00
0110Embankment (0120-6)CY66.10$78.26$159.46$490.00
0115Type B stabilization (0160-4)SY1,712$32.61$70.32$27.50
0120Optional base, base group 10 (0285-710)SY1,712$71.83$63.35$72.50
0125Milling existing asphalt pavement, 3" avg depth (0327-70-4)SY5,902$12.22$4.30$6.00
0130Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY8,458$11.64$11.45$8.50
0135Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8)SY10,559$7.90$4.40$5.90
0140Superpave asphaltic conc, traffic C (0334-1-13)TN1,270.30$258.02$192.00$217.00
0145Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN2,153.70$247.04$235.40$213.00
0150Inlets, curb type P-1, partial (0425-1315)EACH1$20,869$15,425$19,500
0155Inlets, curb, type P-5, partial (0425-1355)EACH1$22,173$15,662$15,750
0160Inlets, curb, type P-6, modify (0425-1369)EACH2$15,652$10,657$20,500
0165Manhole, adjust (0425-5)EACH3$3,912.96$1,563.08$6,000.00
0170Pipe culvert,optional material,round, 15"S/CD (0430-175115)LF38$313.04$307.25$360.00
0175Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF11$489.12$342.77$850.00
0180Pipe culvert, opt material, round, 42"S/CD (0430-175142)LF150$749.98$787.22$1,355.00
0185Pipe culvert, opt material, round, 48"S/CD (0430-175148)LF591$978.24$838.00$1,200.00
0190Cleaning & sealing existing pipe joint, 18" storm sewer (0430-821-25)EACH3$23,478$928.27$1,160.00
0195Cleaning & sealing existing pipe joint, 30" storm sewer (0430-821-33)EACH1$32,608$1,340.83$1,700.00
0200PVC pipe, 6 inch (0430-964-7)LF12$352.17$224.68$675.00
0205Pipe liner, cured in place, 18" (0431-1118)LF107$182.61$144.40$180.00
0210Pipe liner, cured in place, 42" (0431-1142)LF460$456.51$360.99$450.00
0215Concrete curb & gutter, type F (0520-1-10)LF1,755$49.56$55.59$53.25
0220Valley gutter- concrete (0520-3)LF391$50.87$64.99$148.75
0225Traffic separator concrete- type I, 4' wide (0520-5-11)LF336$67.17$64.60$192.35
0230Concrete sidewalk and driveways, 4" thick (0522-1)SY611$76.63$85.85$87.55
0235Concrete sidewalk and driveways, 6" thick (0522-2)SY126$85.63$128.25$261.50
0240Detectable warnings (0527-2)SF282$50.22$30.32$66.50
0245Performance turf, sod (0570-1-2)SY349$15.11$10.07$33.25
0250Raised pavement marker, type B (0706-1-3)EACH1,377$5.22$5.16$5.15
0255Painted pavement markings, standard, white, solid, 6" (0710-11101)GM3.36$2,934.72$1,080.72$2,900.00
0260Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF844$2.22$2.06$2.20
0265Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF50$2.48$2.06$2.45
0270Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.32$1,010.85$618.84$1,000.00
0275Painted pavement markings, standard, white, arrows (0710-11170)EACH12$65.22$30.94$64.40
0280Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM1.21$2,934.72$1,082.98$2,900.00
0285Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.01$1,010.85$687.78$1,000.00
0290Two component polyurethane injection (0906-173200)LB1,736$19.56$15.47$19.50
0295Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000
0300Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH15$684.77$541.49$445.00
0305Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH4$2,217.35$1,753.40$2,300.00
0310Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH1$2,869.51$2,269.11$3,000.00
0315Single column ground sign assembly, remove (0700-1600)EACH16$52.17$41.26$64.50
0320Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH8$163.04$128.93$110.00
0325Delineator, flexible tubular (0705-11-1)EACH3$326.08$103.14$155.00
0330Raised pavement marker, type B (0706-1-3)EACH724$4.96$5.16$4.90
0335Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF9$26.09$5.16$26.00
0340Painted pavement markings, surface (0710-90)LS1$19,681$14,955$19,350
0345Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF2,142$4.57$5.16$4.50
0350Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF411$6.52$6.19$6.40
0355Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF118$9.13$7.22$9.00
0360Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.08$4,565.13$2,776.92$4,500.00
0365Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF30$6.52$6.19$6.45
0370Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.11$3,260.80$2,985.70$3,500.00
0375Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF884$22.17$15.47$22.00
0380Thermoplastic, preformed, white, arrow (0711-14170)EACH51$423.90$618.85$417.00
0385Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM1.14$7,173.77$6,366.58$7,100.00
0390Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.24$9,567.20$1,985.15$9,500.00
0395Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM1.52$1,793.44$2,050.60$2,000.00
0400Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.80$7,173.77$6,386.77$7,000.00
0405Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH2$2,608.64$1,005.63$2,565.00
0410Itsfm location documentation- intersection (0611-2-1)EACH1$1,956.48$3,604.78$1,925.00
0415Conduit, furnish & install, open trench (0630-2-11)LF72$71.74$25.79$71.00
0420Conduit, furnish & install, directional bore (0630-2-12)LF420$71.74$128.93$71.00
0425Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$39,130$33,542$38,500
0430Signal cable, remove- intersection (0632-7-6)PI1$3,586.88$10,056$3,530.00
0435Fiber optic cable, relocate, underground (0633-1420)LF50$11.74$9.28$11.55
0440Fiber optic connection, install, splice (0633-2-31)EACH12$71.74$59.82$71.00
0445Fiber optic connection hardware, F&I, splice tray (0633-3-12)EACH1$78.26$773.56$77.00
0450Fiber optic connection hardware, F&I, preterminated connector assembly (0633-3-13)EACH12$91.30$97.98$90.00
0455Fiber optic connection hardware, F&I, patch panel- terminated (0633-3-16)EACH1$2,282.56$1,727.61$2,245.00
0460Fiber optic cable locator (0633-6)DA200$260.86$67.04$257.00
0465Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$2,608.64$1,005.63$2,565.00
0470Electrical service wire, & install (0639-2-1)LF20$15.65$3.76$15.40
0475Electrical service wire, (0639-2-6)LF20$0.78$1.29$1.00
0480Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14)AS18$2,934.72$1,232.54$2,890.00
0485Vehicular traffic signal, remove- poles to remain (0650-1-60)AS18$326.08$386.78$321.00
0490Vehicle detection system- microwave, furnish & install cabinet equipment (0660-3-11)EACH2$14,021$9,681.86$13,785
0495Vehicle detection system- microwave, furnish & install, above ground equipment (0660-3-12)EACH8$15,000$9,978.91$14,750
0500Vehicle detection system- remove (0660-4-60)EACH1$1,304.32$2,851.85$1,285.00
0505Traffic controller assembly, F&I, NEMA, 1 preemption (0670-5111)AS1$78,259$50,442$76,935
0510Traffic controller assembly, remove controller with (0670-5600)AS1$2,543.43$2,836.38$2,500.00
0515ITS CCTV camera, F&I, dome PTZ enclosure - pressurized, IP, definition (0682-1113)EACH1$10,500$8,777.31$10,325
0520ITS CCTV camera, remove & disposal (0682-1600)EACH1$586.94$1,005.63$580.00
0525Managed field ethernet switch, furnish & install (0684-1-1)EACH1$9,782.41$7,565.40$9,620.00
0530Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14)EACH1$14,348$9,649.89$14,105
0535Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201)EACH1$1,369.54$1,005.63$1,350.00
0540Sign panel, remove, UP to 12 SF (0700-3601)EACH1$260.86$180.50$257.00
0545Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH4$10,369$3,258.23$10,200
0550Internally illuminated sign, remove (0700-5-60)EACH4$717.38$1,005.63$705.00
FDOT contract T1893: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy