FDOT contract T1940 bid tabulation
SR 25 (US 27) FROM SANTA MARIA WAY TO LAKE ISIS AVE. Let by Florida DOT on August 26, 2026, Highlands, District 1. 4 bids received; low bid $17,290,361 by Ajax Paving Industries of Florida LLC.
- Owner
- Florida DOT
- Letting
- 26 AUG 2026
- Pay items
- 178
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ajax Paving Industries of Florida LLC | $17,290,361 | Low |
| 2 | C.W. Roberts Contracting, Inc. | $18,268,520 | +6.0% |
| 3 | Hubbard Construction Company | $18,557,724 | +7.0% |
| 4 | Ohla USA Inc | $19,068,000 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ajax Paving Industries of Florida LLC | 2. C.W. Roberts Contracting, Inc. | 3. Hubbard Construction Company | 4. Ohla USA Inc |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $135,000 | $266,000 | $465,248 | $572,000 |
| 0010 | Mobilization (0101-1) | LS | 1 | $57,364 | $6,600.00 | $35,000 | $95,300 |
| 0015 | Mobilization (0101-1) | LS | 1 | $57,364 | $6,600.00 | $35,000 | $190,000 |
| 0020 | Mobilization (0101-1) | LS | 1 | $135,000 | $370,000 | $35,000 | $953,800 |
| 0025 | Mobilization (0101-1) | LS | 1 | $57,364 | $6,600.00 | $35,000 | $95,300 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $298,200 | $199,000 | $407,688 | $125,000 |
| 0035 | Maintenance of traffic (0102-1) | DA | 1 | $125,960 | $4,900.00 | $50,000 | $25,000 |
| 0040 | Maintenance of traffic (0102-1) | DA | 1 | $125,600 | $4,900.00 | $50,000 | $40,000 |
| 0045 | Maintenance of traffic (0102-1) | DA | 1 | $345,000 | $271,000 | $50,000 | $182,000 |
| 0050 | Maintenance of traffic (0102-1) | DA | 1 | $128,500 | $4,900.00 | $50,000 | $25,000 |
| 0055 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $18,735 | $16,000 | $9,757.24 | $5,000.00 |
| 0060 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $2,703.06 | $2,700.00 | $3,211.18 | $6,500.00 |
| 0065 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $2,654.40 | $7,500.00 | $5,050.86 | $5,000.00 |
| 0070 | Traffic control officer (0102-14) | HR | 2,650 | $92.05 | $56.00 | $81.69 | $0.01 |
| 0075 | Work zone sign (0102-60) | ED | 190,241 | $0.15 | $0.20 | $0.20 | $0.18 |
| 0080 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 442,495 | $0.05 | $0.10 | $0.10 | $0.09 |
| 0085 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 24,041 | $0.03 | $0.05 | $0.03 | $0.03 |
| 0090 | Arrow board / advance warning arrow panel (0102-76) | ED | 8,185 | $4.00 | $5.60 | $5.45 | $5.00 |
| 0095 | Temporary raised/retroreflective pavement marker, type B (0102-78-2) | EACH | 7,750 | $4.09 | $5.00 | $4.42 | $4.00 |
| 0100 | Portable changeable message sign, temporary (0102-99) | ED | 3,569 | $8.00 | $11.00 | $10.89 | $10.00 |
| 0105 | Temporary signalization and maintenance, intersection (0102-104) | ED | 4,950 | $8.90 | $9.00 | $8.80 | $8.90 |
| 0110 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 4,950 | $8.90 | $10.00 | $9.90 | $8.90 |
| 0115 | Type III barricade (0102-115) | ED | 9,570 | $0.20 | $0.25 | $0.25 | $0.23 |
| 0120 | Portable regulatory, sign (0102-150-1) | ED | 2,250 | $4.00 | $5.60 | $5.45 | $5.00 |
| 0125 | Radar speed display unit (0102-150-2) | ED | 2,250 | $4.00 | $5.60 | $5.45 | $5.00 |
| 0130 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 450 | $0.01 | $67.00 | $4.31 | $35.00 |
| 0135 | Removable tape, white, 24" stop bar (0102-913-23) | LF | 40 | $10.23 | $14.50 | $11.06 | $10.00 |
| 0140 | Removable tape, white, 12" crosswalk (0102-913-24) | LF | 604 | $5.11 | $7.25 | $5.53 | $5.00 |
| 0145 | Sediment barrier (0104-10-3) | LF | 9,478 | $1.40 | $5.00 | $1.80 | $2.14 |
| 0150 | Soil tracking prevention device (0104-15) | EACH | 7 | $1,500.00 | $500.00 | $3,113.99 | $3,500.00 |
| 0155 | Inlet protection system (0104-18) | EACH | 213 | $178.98 | $160.00 | $136.14 | $125.00 |
| 0160 | Litter removal (0107-1) | ACRE | 1,139.67 | $35.00 | $11.00 | $65.35 | $0.01 |
| 0165 | Mowing (0107-2) | ACRE | 1,037.15 | $3.00 | $11.00 | $82.77 | $0.01 |
| 0170 | Monitor existing structures- vibration monitoring (0108-2) | LS | 1 | $5,113.78 | $2,700.00 | $71,592 | $21,519 |
| 0175 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $28,237 | $5,400.00 | $5,239.07 | $90,000 |
| 0180 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $25,810 | $20,000 | $11,400 | $115,000 |
| 0185 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $8,175.84 | $1,425.00 | $3,130.92 | $135,000 |
| 0190 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $29,267 | $18,300 | $11,987 | $85,000 |
| 0195 | Removal of existing concrete (0110-4-10) | SY | 1,233 | $30.48 | $16.15 | $46.65 | $75.00 |
| 0200 | Regular excavation (0120-1) | CY | 806.50 | $40.07 | $45.00 | $29.83 | $75.00 |
| 0210 | Embankment (0120-6) | CY | 217.40 | $111.48 | $32.50 | $35.66 | $35.00 |
| 0215 | Type B stabilization (0160-4) | SY | 1,755 | $28.23 | $33.50 | $30.27 | $20.00 |
| 0220 | Optional base, base group 01 (0285-701) | SY | 474 | $54.44 | $53.00 | $55.11 | $60.56 |
| 0225 | Optional base, base group 11 (0285-711) | SY | 736 | $79.75 | $66.00 | $86.26 | $85.90 |
| 0230 | Optional base, base group 15 (0285-715) | SY | 145 | $147.22 | $105.00 | $120.45 | $165.09 |
| 0235 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 160,816 | $3.07 | $3.70 | $4.57 | $4.25 |
| 0240 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 73,425 | $3.08 | $3.30 | $3.88 | $4.25 |
| 0245 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 567 | $8.51 | $16.75 | $17.44 | $18.00 |
| 0250 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 169,305 | $2.92 | $2.75 | $4.40 | $4.25 |
| 0255 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 73,449 | $3.60 | $3.90 | $5.16 | $5.90 |
| 0260 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 14,721.30 | $133.00 | $136.35 | $122.08 | $136.00 |
| 0265 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 19,642.90 | $132.00 | $145.50 | $146.69 | $141.00 |
| 0270 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 39,074.50 | $159.50 | $162.00 | $157.77 | $155.00 |
| 0275 | Plain cement concrete 11.5" (0350-3-12) | SY | 474 | $254.24 | $237.00 | $245.06 | $216.91 |
| 0280 | Cleaning & sealing joints- concrete pavement (0350-5) | LF | 1,134 | $18.92 | $38.50 | $23.99 | $4.00 |
| 0285 | Grinding concrete pavement (0352-70) | SY | 474 | $19.43 | $21.50 | $18.38 | $5.75 |
| 0290 | Inlets, DT bot, type D, <10' (0425-1541) | EACH | 1 | $9,677.97 | $12,300 | $5,818.38 | $9,750.00 |
| 0295 | Inlets, closed flume (0425-1910) | EACH | 2 | $7,862.61 | $11,750 | $2,528.23 | $4,250.00 |
| 0300 | Manhole, adjust (0425-5) | EACH | 4 | $136.79 | $1,660.00 | $1,709.70 | $1,050.00 |
| 0305 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 4 | $1,522.33 | $722.00 | $371.41 | $750.00 |
| 0310 | Pipe handrail - guiderail, relocate, aluminum (0515-1-42) | LF | 9 | $25.57 | $487.75 | $150.51 | $170.00 |
| 0315 | Concrete curb & gutter, type E (0520-1-7) | LF | 370 | $56.97 | $49.00 | $42.08 | $45.00 |
| 0320 | Concrete curb & gutter, type F (0520-1-10) | LF | 3,035 | $51.92 | $49.00 | $44.91 | $46.00 |
| 0325 | Concrete curb, type D (0520-2-4) | LF | 51 | $62.93 | $30.00 | $59.21 | $44.50 |
| 0330 | Valley gutter- concrete (0520-3) | LF | 41 | $78.29 | $56.00 | $64.67 | $62.50 |
| 0335 | Traffic separator concrete- type I, 6' wide (0520-5-12) | LF | 316 | $105.06 | $105.00 | $155.52 | $172.00 |
| 0340 | Shoulder gutter- concrete (0520-6) | LF | 37 | $86.08 | $61.00 | $67.68 | $39.50 |
| 0345 | Concrete traffic separator, special- variable width (0520-70) | SY | 100 | $170.22 | $157.00 | $168.84 | $140.00 |
| 0350 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 27 | $137.69 | $106.00 | $158.24 | $74.50 |
| 0355 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 886 | $141.59 | $126.00 | $125.48 | $98.50 |
| 0360 | Concrete ditch pavement, 4", reinforced (0524-1-29) | SY | 22 | $296.08 | $179.00 | $250.21 | $128.00 |
| 0365 | Detectable warnings (0527-2) | SF | 577 | $20.46 | $68.00 | $39.58 | $41.00 |
| 0370 | Performance turf, sod (0570-1-2) | SY | 18,168 | $5.15 | $5.25 | $6.49 | $2.70 |
| 0375 | Shoulder drop off soil (0570-13-1) | CY | 5,700.30 | $8.00 | $47.65 | $66.42 | $32.39 |
| 0380 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 22.73 | $1,534.13 | $2,350.00 | $1,658.44 | $1,499.87 |
| 0385 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 1.33 | $1,636.41 | $3,050.00 | $1,765.18 | $1,596.40 |
| 0390 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 7,240 | $1.02 | $1.85 | $1.11 | $1.00 |
| 0395 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 2,969 | $1.53 | $2.00 | $1.66 | $1.50 |
| 0400 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 2,872 | $2.05 | $2.15 | $2.21 | $2.00 |
| 0405 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 30.37 | $715.93 | $663.00 | $773.96 | $699.95 |
| 0410 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 1.97 | $715.93 | $781.00 | $772.04 | $701.78 |
| 0415 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 5 | $86.93 | $54.25 | $93.99 | $85.00 |
| 0420 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 663 | $35.80 | $48.00 | $38.70 | $35.00 |
| 0425 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 16.42 | $1,534.13 | $2,350.00 | $1,658.59 | $1,500.00 |
| 0430 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 1,781 | $1.53 | $1.80 | $1.66 | $1.50 |
| 0435 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.99 | $715.93 | $780.00 | $770.89 | $697.18 |
| 0440 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $35,000 | $35,000 | $35,000 | $35,000 |
| 0445 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $25,000 | $25,000 | $25,000 | $25,000 |
| 0450 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $25,000 | $25,000 | $25,000 | $25,000 |
| 0455 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0460 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $15,000 | $15,000 | $15,000 | $15,000 |
| 0465 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 5.67 | $2,328.76 | $2,400.00 | $2,550.16 | $3,503.93 |
| 0470 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 48 | $615.31 | $614.00 | $608.15 | $625.50 |
| 0475 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 20 | $1,556.61 | $2,455.00 | $2,432.59 | $1,852.25 |
| 0480 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 8 | $1,747.48 | $2,790.00 | $2,764.31 | $1,776.25 |
| 0485 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $372.94 | $698.00 | $691.08 | $380.00 |
| 0490 | Single column ground sign assembly, remove (0700-1600) | EACH | 47 | $131.21 | $11.00 | $11.06 | $133.35 |
| 0495 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 3 | $615.31 | $223.00 | $221.15 | $625.00 |
| 0500 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 4 | $311.64 | $111.00 | $110.57 | $315.00 |
| 0505 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 3 | $125.54 | $11.15 | $11.06 | $130.00 |
| 0510 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 37 | $130.74 | $100.50 | $99.52 | $133.00 |
| 0515 | Tubular marker, 36" white post (0704-1-3) | EACH | 14 | $104.77 | $178.50 | $176.92 | $106.50 |
| 0520 | Tubular marker, 36" yellow (0704-1-4) | EACH | 68 | $104.77 | $178.50 | $176.92 | $106.50 |
| 0525 | Raised pavement marker, type B (0706-1-3) | EACH | 8,562 | $4.09 | $5.15 | $4.42 | $4.00 |
| 0530 | Painted pavement markings, surface (0710-90) | LS | 1 | $65,456 | $97,500 | $70,766 | $64,000 |
| 0535 | Painted pavement markings, surface (0710-90) | LS | 1 | $3,579.64 | $11,385 | $3,870.03 | $3,500.00 |
| 0540 | Painted pavement markings, surface (0710-90) | LS | 1 | $10,739 | $15,800 | $11,610 | $10,500 |
| 0545 | Painted pavement markings, surface (0710-90) | LS | 1 | $1,022.76 | $155,000 | $1,105.72 | $100,000 |
| 0550 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 8,882 | $4.09 | $3.85 | $4.42 | $4.00 |
| 0555 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 3,142 | $5.11 | $5.75 | $5.53 | $5.00 |
| 0560 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 2,880 | $6.14 | $7.70 | $6.63 | $6.00 |
| 0565 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 2.19 | $3,068.27 | $3,000.00 | $3,315.65 | $2,998.63 |
| 0570 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 19 | $204.55 | $107.25 | $221.14 | $200.00 |
| 0575 | Thermoplastic, standard, arrow (0711-11170) | EACH | 715 | $81.82 | $78.30 | $88.46 | $80.00 |
| 0580 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 1,817 | $5.11 | $6.00 | $5.53 | $5.00 |
| 0585 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 1.06 | $3,068.27 | $3,000.00 | $3,288.98 | $3,002.83 |
| 0590 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 4,720 | $2.05 | $18.50 | $2.21 | $2.00 |
| 0595 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 38 | $204.55 | $241.00 | $221.14 | $200.00 |
| 0600 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 38 | $102.28 | $103.00 | $110.57 | $100.00 |
| 0605 | Thermoplastic, preformed, yellow, 2-4 dotted guideline on concrete surfaces (0711-14241) | GM | 0.07 | $20,455 | $15,000 | $20,104 | $21,212 |
| 0610 | Thermoplastic, preformed, 24" white with 4" black contrast crosswalk on concrete pavement, 32" (0711-14526) | LF | 452 | $30.68 | $25.00 | $33.17 | $30.00 |
| 0615 | Thermoplastic, preformed, 24" white with 4" black contrast stop line on concrete 32" (0711-14527) | LF | 131 | $30.68 | $25.00 | $33.17 | $30.00 |
| 0620 | Thermoplastic, preformed, 12" white with 4" black contrast crosswalk on concrete pavement, 20" (0711-14528) | LF | 1,070 | $20.46 | $18.00 | $22.11 | $20.00 |
| 0625 | Thermoplastic, preformed, white with black contrast on concrete pavement, message symbol (0711-14560) | EACH | 1 | $1,534.13 | $545.00 | $1,658.58 | $1,500.00 |
| 0630 | Thermoplastic, preformed, white with black contrast, arrow on concrete surface (0711-14570) | EACH | 38 | $818.20 | $912.00 | $884.58 | $800.00 |
| 0635 | Thermoplastic, preformed, color route shield (0711-14660) | EACH | 10 | $2,863.71 | $2,300.00 | $3,096.03 | $2,800.00 |
| 0640 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 24.80 | $5,113.78 | $5,815.00 | $5,526.83 | $5,000.40 |
| 0645 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 1.68 | $5,625.15 | $7,750.00 | $6,074.24 | $5,493.46 |
| 0650 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 31.01 | $2,045.51 | $1,450.00 | $2,211.23 | $1,999.81 |
| 0655 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.02 | $4,091.02 | $1,530.00 | $2,327.89 | $4,210.53 |
| 0660 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 17.66 | $5,318.33 | $5,420.00 | $5,746.83 | $5,200.29 |
| 0665 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 0.01 | $2,045.51 | $1,230.00 | $2,010.00 | $1,818.18 |
| 0670 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 124 | $28.89 | $6.00 | $31.24 | $28.25 |
| 0675 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.05 | $30,683 | $34,300 | $28,845 | $32,609 |
| 0680 | Permanent tape, white, solid W/contrast, 6" primary line width, for concrete surfaces (0713-103121) | GM | 0.46 | $46,024 | $64,000 | $49,650 | $44,902 |
| 0685 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 1.07 | $10,228 | $9,900.00 | $11,016 | $9,962.76 |
| 0690 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.05 | $30,683 | $34,000 | $28,231 | $31,915 |
| 0695 | Permanent tape, yellow, 6-10 dotted extension, 6" wide, for concrete surfaces (0713-103241) | GM | 0.09 | $10,228 | $15,000 | $11,057 | $10,000 |
| 0700 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 1.07 | $10,228 | $9,900.00 | $11,016 | $9,962.76 |
| 0705 | Conduit, furnish & install, open trench (0630-2-11) | LF | 305 | $18.98 | $24.00 | $23.10 | $40.00 |
| 0710 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 8 | $888.27 | $1,400.00 | $1,349.87 | $1,592.78 |
| 0715 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 1,294 | $2.85 | $2.30 | $2.20 | $4.12 |
| 0720 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 10 | $2,453.31 | $1,600.00 | $1,530.29 | $1,502.06 |
| 0725 | Light pole complete, F&I, standard pole standard foundation, 35' mounting height, 8' arm length (0715-61211) | EACH | 1 | $8,639.21 | $11,800 | $11,468 | $7,544.33 |
| 0730 | Light pole complete, F&I, standard pole standard foundation, 40' mounting height, 15' arm length (0715-61352) | EACH | 3 | $9,356.71 | $12,200 | $11,823 | $7,842.27 |
| 0735 | Light pole complete, F&I, utility conflict pole standard foundation, 40' mounting height, 16' arm length (0715-65366) | EACH | 1 | $1,926.95 | $13,700 | $13,280 | $9,048.45 |
| 0740 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 9 | $2,127.30 | $770.00 | $742.59 | $922.68 |
| 0745 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 0.29 | $3,419.65 | $4,900.00 | $4,734.07 | $3,355.09 |
| 0750 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $2,320.26 | $3,300.00 | $3,188.20 | $2,320.00 |
| 0755 | Conduit, furnish & install, open trench (0630-2-11) | LF | 653 | $18.98 | $24.00 | $23.10 | $19.00 |
| 0760 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 947 | $23.67 | $75.50 | $70.41 | $24.00 |
| 0765 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 2 | $12,904 | $8,200.00 | $7,995.81 | $12,900 |
| 0770 | Signal cable, remove- intersection (0632-7-6) | PI | 2 | $1,929.06 | $1,700.00 | $1,740.42 | $1,925.00 |
| 0775 | Fiber optic cable locator (0633-6) | DA | 450 | $140.09 | $225.00 | $220.03 | $0.01 |
| 0780 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 40 | $888.27 | $1,390.00 | $1,349.87 | $885.00 |
| 0785 | Aluminum signals pole, (0646-1-11) | EACH | 14 | $2,845.07 | $3,800.00 | $3,708.57 | $2,840.00 |
| 0790 | Aluminum signals pole, furnish install pedestrian detector post (0646-1-12) | EACH | 2 | $2,648.39 | $2,300.00 | $2,262.99 | $2,645.00 |
| 0795 | Aluminum signals pole, remove (0646-1-60) | EACH | 10 | $558.37 | $413.00 | $400.45 | $558.00 |
| 0800 | Steel mast arm assembly, and install, single arm 60' (0649-21-10) | EACH | 1 | $89,703 | $103,000 | $100,795 | $89,595 |
| 0805 | Vehicular traffic signal, furnish & install aluminum, 3 section, 1 way (0650-1-14) | AS | 8 | $2,297.62 | $2,270.00 | $2,204.68 | $2,295.00 |
| 0810 | Vehicular traffic signal, remove- poles to remain (0650-1-60) | AS | 6 | $416.03 | $358.00 | $347.64 | $415.00 |
| 0815 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 14 | $1,033.13 | $995.00 | $965.92 | $1,030.00 |
| 0820 | Loop detector inductive, F&I, type 9 (0660-1109) | EACH | 6 | $486.01 | $390.00 | $378.45 | $485.00 |
| 0825 | Loop assembly, F&I, type B (0660-2102) | AS | 108 | $1,045.96 | $2,020.00 | $1,961.55 | $1,045.00 |
| 0830 | Loop assembly, F&I, type F (0660-2106) | AS | 59 | $1,465.08 | $1,895.00 | $1,839.43 | $1,465.00 |
| 0835 | Vehicle detection system- adjust/modify cabinet (0660-4-51) | EACH | 1 | $2,789.57 | $937.00 | $909.81 | $2,785.00 |
| 0840 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 7 | $698.58 | $432.00 | $419.15 | $700.00 |
| 0845 | Pedestrian detector, furnish & install, accessible (0665-1-12) | EACH | 10 | $2,228.18 | $1,805.00 | $1,752.52 | $2,225.00 |
| 0850 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 3 | $160.10 | $94.00 | $91.31 | $160.00 |
| 0855 | Traffic controller assembly, modify only - no components added (0670-5710) | AS | 1 | $3,522.18 | $869.00 | $843.81 | $3,520.00 |
| 0860 | Traffic controller, modify (0671-2-40) | EACH | 1 | $3,311.49 | $467.00 | $454.36 | $3,310.00 |
| 0865 | Traffic signal controller cabinet, adjust/modify (0676-1500) | EACH | 1 | $3,638.11 | $1,830.00 | $1,780.02 | $3,635.00 |
| 0870 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 3 | $1,354.46 | $1,135.00 | $1,102.34 | $1,350.00 |
| 0875 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 2 | $120.95 | $268.00 | $260.74 | $121.00 |
| 0880 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 5 | $6,110.26 | $4,300.00 | $4,189.33 | $6,100.00 |
| 0885 | Internally illuminated sign, remove (0700-5-60) | EACH | 4 | $560.51 | $440.00 | $434.56 | $560.00 |
| 0890 | Enhanced highway sign AC powered, F&I overhead blank out sign <12 SF (0700-141360) | EACH | 2 | $8,443.37 | $8,300.00 | $8,089.32 | $8,435.00 |
| 0895 | Enhanced highway sign AC powered, remove - overhead mount (0700-141903) | EACH | 1 | $8,993.77 | $358.00 | $347.64 | $8,985.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of August 26, 2026. Compiled by Mirage Metrics.