FDOT contract T2A44 bid tabulation
SR 45 (US 27) FROM SR 500 (US 27) TO ALACHUA CO LINE. Let by Florida DOT on October 29, 2025, Levy, District 2. 5 bids received; low bid $5,635,431 by Anderson Columbia Co., Inc..
- Owner
- Florida DOT
- Letting
- 29 OCT 2025
- Pay items
- 95
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Anderson Columbia Co., Inc. | $5,635,431 | Low |
| 2 | Whitehurst, V. E. & Sons, Inc. | $5,903,343 | +5.0% |
| 3 | Preferred Materials Inc. | $5,937,565 | +5.0% |
| 4 | Watson Construction Company, LLC | $6,159,665 | +9.0% |
| 5 | C.W. Roberts Contracting, Inc. | $6,956,795 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Anderson Columbia Co., Inc. | 2. Whitehurst, V. E. & Sons, Inc. | 3. Preferred Materials Inc. | 4. Watson Construction Company, LLC | 5. C.W. Roberts Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $639,781 | $369,045 | $188,052 | $304,599 | $695,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $347,740 | $381,985 | $253,971 | $289,000 | $470,000 |
| 0015 | Work zone sign (0102-60) | ED | 14,104 | $0.32 | $0.30 | $0.28 | $0.25 | $0.30 |
| 0020 | Business sign (0102-61) | EACH | 1 | $57.14 | $53.75 | $50.00 | $200.00 | $55.00 |
| 0025 | Temporary barrier, F&I, anchored (0102-71-15) | LF | 875 | $34.28 | $32.25 | $30.00 | $47.00 | $35.50 |
| 0030 | Temporary barrier, relocate, anchored (0102-71-25) | LF | 1,725 | $17.14 | $16.13 | $15.00 | $21.00 | $17.75 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 64,479 | $0.11 | $0.11 | $0.10 | $0.11 | $0.10 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 159 | $5.71 | $5.38 | $5.00 | $5.75 | $5.93 |
| 0045 | Temporary raised/retroreflective pavement marker, type D (0102-78-1) | EACH | 813 | $6.00 | $5.64 | $5.25 | $6.50 | $5.00 |
| 0050 | Temporary crash cushion, redirective option (0102-89-1) | LO | 8 | $1,028.61 | $967.50 | $900.00 | $1,093.00 | $3,000.00 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 1,272 | $11.43 | $10.75 | $10.00 | $11.50 | $11.00 |
| 0060 | Temporary signalization and maintenance, intersection (0102-104) | ED | 480 | $28.57 | $20.00 | $25.73 | $25.00 | $28.00 |
| 0065 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 480 | $28.57 | $0.80 | $17.26 | $12.00 | $28.00 |
| 0070 | Type III barricade (0102-115) | ED | 639 | $0.40 | $0.38 | $0.35 | $0.33 | $0.40 |
| 0075 | Temporary raised rumble per day, includes all sets and relocations (0102-909) | DA | 160 | $34.28 | $32.25 | $30.00 | $35.00 | $33.50 |
| 0080 | Sediment barrier (0104-10-3) | LF | 10,028 | $3.32 | $1.13 | $1.05 | $1.75 | $1.75 |
| 0085 | Inlet protection system (0104-18) | EACH | 9 | $246.31 | $80.63 | $100.00 | $150.00 | $180.00 |
| 0090 | Litter removal (0107-1) | ACRE | 502.30 | $171.43 | $107.50 | $40.00 | $50.00 | $105.00 |
| 0095 | Mowing (0107-2) | ACRE | 432.07 | $171.43 | $188.13 | $140.00 | $50.00 | $115.00 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $42,214 | $43,000 | $57,791 | $45,000 | $198,500 |
| 0105 | Removal of existing concrete (0110-4-10) | SY | 463 | $27.97 | $70.63 | $38.00 | $60.00 | $25.00 |
| 0110 | Mailbox, F&I single (0110-7-1) | EACH | 4 | $296.87 | $200.00 | $325.00 | $250.00 | $575.00 |
| 0115 | Regular excavation (0120-1) | CY | 114.40 | $44.00 | $15.00 | $27.58 | $100.00 | $95.00 |
| 0120 | Embankment (0120-6) | CY | 776.30 | $21.28 | $20.00 | $37.23 | $45.00 | $95.00 |
| 0125 | Optional base, base group 01 (0285-701) | SY | 4,419 | $8.87 | $19.75 | $20.52 | $25.00 | $30.00 |
| 0130 | Milling existing asphalt pavement, 1" avg depth (0327-70-1) | SY | 1,160 | $2.99 | $1.59 | $8.14 | $3.00 | $9.50 |
| 0135 | Milling existing asphalt pavement, 3" avg depth (0327-70-4) | SY | 3,753 | $3.65 | $2.41 | $5.87 | $5.00 | $10.50 |
| 0140 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 105,916 | $1.58 | $1.97 | $1.93 | $3.75 | $3.00 |
| 0145 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 1,326 | $3.96 | $1.76 | $7.87 | $5.00 | $9.50 |
| 0150 | Milling existing asphalt pavement, 2 1/2" avg depth (0327-70-8) | SY | 1,586 | $3.37 | $2.19 | $7.10 | $6.00 | $9.50 |
| 0155 | Milling existing asphalt pavement, 1/2" avg depth (0327-70-16) | SY | 35,379 | $1.09 | $1.38 | $1.27 | $2.50 | $3.00 |
| 0160 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 9,108.20 | $132.05 | $144.70 | $175.00 | $170.00 | $143.00 |
| 0165 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 12,280.30 | $134.57 | $144.70 | $178.00 | $168.00 | $166.00 |
| 0170 | Miscellaneous asphalt (0339-1) | TN | 85.20 | $240.89 | $200.00 | $952.58 | $325.00 | $360.00 |
| 0175 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $9,873.54 | $20,508 | $6,750.00 | $13,140 | $8,000.00 |
| 0180 | Inlets, gutter, type S, <10' (0425-1701) | EACH | 6 | $10,299 | $19,320 | $6,950.00 | $13,900 | $9,000.00 |
| 0185 | Manhole, adjust (0425-5) | EACH | 2 | $1,424.94 | $2,260.46 | $1,750.00 | $2,000.00 | $800.00 |
| 0190 | Valve boxes, adjust (0425-6) | EACH | 2 | $1,424.94 | $1,645.56 | $900.00 | $1,500.00 | $400.00 |
| 0195 | Manhole cover- replace (0425-7) | EACH | 4 | $1,424.94 | $831.51 | $1,800.00 | $1,200.00 | $475.00 |
| 0200 | Pipe culvert, optional material, round, 18"SD (0430-174118) | LF | 47 | $272.93 | $359.48 | $175.00 | $110.00 | $188.00 |
| 0205 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 503 | $114.04 | $357.22 | $120.00 | $110.00 | $140.00 |
| 0210 | Straight concrete endwalls, single, 0 degrees, round (0430-518100) | EACH | 1 | $6,456.23 | $8,678.48 | $3,500.00 | $5,779.00 | $4,400.00 |
| 0215 | Straight concrete endwalls, single, 0 degrees, elliptical (0430-518102) | EACH | 1 | $6,456.23 | $8,678.48 | $3,500.00 | $5,779.00 | $7,200.00 |
| 0220 | U-endwall, with baffles & index 261/430-011,1:4 slope,18"pipe (0430-613125) | EACH | 1 | $9,225.55 | $13,800 | $6,500.00 | $11,500 | $6,900.00 |
| 0225 | Mitered end section, optional round, 18" SD (0430-984125) | EACH | 5 | $2,074.65 | $2,372.96 | $2,750.00 | $2,100.00 | $3,900.00 |
| 0230 | Shoulder gutter- concrete (0520-6) | LF | 1,651 | $33.03 | $106.02 | $40.00 | $45.00 | $55.00 |
| 0235 | Concrete slope pavement,non reinforced, 4" (0524-2-2) | SY | 358 | $105.55 | $209.33 | $195.00 | $180.00 | $130.00 |
| 0240 | Detectable warnings (0527-2) | SF | 318 | $41.56 | $62.51 | $35.00 | $38.00 | $45.00 |
| 0245 | Riprap, rubble, F&I, ditch lining (0530-3-4) | TN | 6.40 | $495.86 | $505.50 | $250.00 | $290.00 | $600.00 |
| 0250 | Bedding stone (0530-74) | TN | 8.40 | $402.83 | $413.42 | $250.00 | $290.00 | $460.00 |
| 0255 | Guardrail -roadway, general (0536-1-1) | LF | 2,056 | $28.57 | $26.88 | $20.02 | $21.50 | $28.00 |
| 0260 | Special guardrail post- post for shallow mount (0536-7-3) | EACH | 3 | $85.71 | $80.63 | $108.88 | $375.00 | $83.00 |
| 0265 | Guardrail removal (0536-73) | LF | 1,952 | $2.29 | $2.15 | $2.24 | $3.00 | $2.25 |
| 0270 | Guardrail end treatment- parallel approach terminal (0536-85-24) | EACH | 8 | $3,200.10 | $3,010.00 | $2,987.93 | $3,150.00 | $3,100.00 |
| 0275 | Performance turf, sod (0570-1-2) | SY | 27,745 | $6.80 | $2.58 | $2.91 | $4.50 | $10.00 |
| 0280 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 1,466 | $13.31 | $5.40 | $10.93 | $8.00 | $22.50 |
| 0285 | Raised pavement marker, type B (0706-1-3) | EACH | 1,627 | $6.00 | $5.65 | $5.25 | $6.50 | $5.00 |
| 0290 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 14.44 | $2,257.23 | $2,418.75 | $2,250.00 | $1,800.00 | $2,350.00 |
| 0295 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 1,716 | $3.43 | $3.23 | $3.00 | $2.00 | $1.11 |
| 0300 | Painted pavement markings, standard, white, solid for diagonal or chevron, 18" (0710-11124) | LF | 249 | $4.57 | $4.30 | $4.00 | $2.50 | $1.65 |
| 0305 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 406 | $5.14 | $4.84 | $4.50 | $3.00 | $2.25 |
| 0310 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 6.22 | $1,714.35 | $1,827.50 | $1,700.00 | $775.00 | $1,180.00 |
| 0315 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 20 | $85.71 | $80.63 | $75.00 | $75.00 | $173.00 |
| 0320 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 6.51 | $2,228.63 | $2,418.75 | $2,250.00 | $1,800.00 | $2,350.00 |
| 0325 | Painted pavement markings, standard, yellow, skip, 6" (0710-11231) | GM | 4.56 | $1,714.35 | $1,827.50 | $1,700.00 | $775.00 | $1,180.00 |
| 0330 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $68,751 | $68,751 | $68,751 | $68,751 | $68,751 |
| 0335 | Ground-in rumble strips, 8" sinusoidal (0546-72-3) | GM | 18.17 | $1,800.06 | $2,220.00 | $1,099.88 | $1,876.87 | $1,750.00 |
| 0340 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 26 | $565.73 | $532.13 | $495.00 | $500.00 | $550.00 |
| 0345 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 1 | $2,514.36 | $2,365.00 | $2,200.00 | $700.00 | $2,400.00 |
| 0350 | Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113) | EACH | 1 | $2,971.53 | $2,795.00 | $2,600.00 | $2,000.00 | $2,900.00 |
| 0355 | Single column ground sign assembly, relocate (0700-1500) | EACH | 4 | $142.86 | $135.00 | $125.00 | $175.00 | $140.00 |
| 0360 | Single column ground sign assembly, remove (0700-1600) | EACH | 15 | $28.57 | $26.90 | $25.00 | $30.00 | $28.00 |
| 0365 | Multi-column ground sign assembly, remove (0700-2600) | EACH | 1 | $1,097.56 | $1,032.35 | $960.33 | $50.00 | $1,075.00 |
| 0370 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 3 | $200.01 | $188.15 | $175.00 | $220.00 | $195.00 |
| 0375 | Sign panel, relocate, UP to 12 SF (0700-3501) | EACH | 3 | $74.28 | $70.00 | $65.00 | $150.00 | $72.75 |
| 0380 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 1 | $97.15 | $91.40 | $85.00 | $100.00 | $95.00 |
| 0385 | Object marker, type 1 (0705-10-1) | EACH | 15 | $262.86 | $247.25 | $230.00 | $250.00 | $255.00 |
| 0390 | Raised pavement marker, type B (0706-1-3) | EACH | 1,627 | $6.29 | $5.91 | $5.50 | $5.25 | $5.00 |
| 0395 | Painted pavement markings, surface (0710-90) | LS | 1 | $80,003 | $86,000 | $80,000 | $54,000 | $69,000 |
| 0400 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.05 | $12,286 | $11,556 | $10,750 | $7,000.00 | $9,950.00 |
| 0405 | Thermoplastic, standard, solid, 12" for interchange markings (0711-11103) | GM | 0.16 | $19,715 | $18,544 | $17,250 | $18,484 | $11,750 |
| 0410 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 869 | $6.00 | $5.65 | $5.25 | $3.50 | $3.91 |
| 0415 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 248 | $8.57 | $8.06 | $7.50 | $7.00 | $6.15 |
| 0420 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 169 | $10.86 | $10.21 | $9.50 | $8.00 | $8.90 |
| 0425 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 10 | $200.01 | $188.15 | $175.00 | $175.00 | $195.00 |
| 0430 | Thermoplastic, standard, arrow (0711-11170) | EACH | 10 | $131.44 | $123.65 | $115.00 | $90.00 | $165.00 |
| 0435 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.01 | $6,571.64 | $6,181.25 | $5,750.00 | $2,800.00 | $4,425.00 |
| 0440 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 235 | $21.03 | $19.80 | $18.40 | $16.00 | $16.75 |
| 0445 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 14.44 | $7,228.80 | $6,800.00 | $6,325.00 | $4,500.00 | $7,300.00 |
| 0450 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.46 | $2,102.92 | $1,978.00 | $1,840.00 | $2,800.00 | $4,375.00 |
| 0455 | Thermoplastic, standard-other surfaces white, skip, 12"- approach to toll plaza or 3-9 lane drop (0711-16133) | GM | 0.15 | $4,000.13 | $3,762.50 | $3,500.00 | $10,500 | $8,500.00 |
| 0460 | Thermoplastic, standard other surfaces, white, 6", 6-10 dotted managed lane marking (0711-16171) | GM | 0.14 | $6,571.64 | $6,181.25 | $5,750.00 | $2,800.00 | $4,125.00 |
| 0465 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 6.51 | $7,228.80 | $6,800.00 | $6,325.00 | $4,500.00 | $7,375.00 |
| 0470 | Thermoplastic, standard-other surfaces, yellow, skip, 6" (0711-16231) | GM | 4.55 | $2,102.92 | $1,978.00 | $1,840.00 | $2,800.00 | $4,425.00 |
| 0475 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 900 | $8.57 | $8.06 | $7.50 | $20.00 | $4.45 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of October 29, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way