FDOT contract T2A57 bid tabulation
SR 15 (US 17 / PARK AVE) FROM DOCTORS INLET TO WELLS RD. Let by Florida DOT on February 25, 2026, Clay, District 2. 5 bids received; low bid $5,326,772 by Preferred Materials Inc..
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 97
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Preferred Materials Inc. | $5,326,772 | Low |
| 2 | Duval Asphalt Products, Inc. | $5,913,228 | +11% |
| 3 | Pigott Asphalt and Sitework LLC | $6,496,855 | +22% |
| 4 | Hubbard Construction Company | $6,680,929 | +25% |
| 5 | Watson Civil Construction, Inc. | $7,225,350 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Preferred Materials Inc. | 2. Duval Asphalt Products, Inc. | 3. Pigott Asphalt and Sitework LLC | 4. Hubbard Construction Company | 5. Watson Civil Construction, Inc. |
|---|---|---|---|---|---|---|---|---|
| 0005 | Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21) | LF | 844 | $59.00 | $68.50 | $124.50 | $63.68 | $85.00 |
| 0010 | Polymer nosing for bridge expansion joint (0458-2) | CF | 24 | $860.00 | $1,000.00 | $1,000.00 | $928.24 | $890.00 |
| 0015 | Mobilization (0101-1) | LS | 1 | $259,843 | $465,000 | $565,000 | $398,150 | $712,108 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $403,440 | $224,000 | $390,000 | $678,613 | $291,000 |
| 0025 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $875.00 | $13,000 | $7,500.00 | $3,079.37 | $8,000.00 |
| 0030 | Traffic control officer (0102-14) | HR | 60 | $100.00 | $120.00 | $150.00 | $105.86 | $130.00 |
| 0035 | Work zone sign (0102-60) | ED | 25,764 | $0.20 | $0.25 | $0.25 | $0.22 | $0.40 |
| 0040 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 27,012 | $0.10 | $0.15 | $0.01 | $0.11 | $0.20 |
| 0045 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 1,470 | $0.05 | $5.00 | $0.10 | $0.05 | $0.10 |
| 0050 | Arrow board / advance warning arrow panel (0102-76) | ED | 516 | $5.00 | $5.50 | $1.00 | $5.40 | $8.00 |
| 0055 | Portable changeable message sign, temporary (0102-99) | ED | 2,397 | $9.00 | $11.50 | $1.00 | $9.71 | $12.00 |
| 0060 | Temporary signalization and maintenance, intersection (0102-104) | ED | 1,500 | $55.76 | $65.00 | $1.00 | $35.04 | $60.00 |
| 0065 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 1,500 | $28.47 | $33.00 | $1.00 | $13.64 | $34.00 |
| 0070 | Type III barricade (0102-115) | ED | 300 | $0.25 | $0.40 | $1.00 | $0.27 | $0.50 |
| 0075 | Sediment barrier (0104-10-3) | LF | 473 | $0.98 | $1.25 | $5.00 | $1.06 | $6.00 |
| 0080 | Inlet protection system (0104-18) | EACH | 68 | $100.00 | $125.00 | $150.00 | $107.94 | $150.00 |
| 0085 | Litter removal (0107-1) | ACRE | 132.47 | $125.00 | $150.00 | $10.00 | $161.90 | $120.00 |
| 0090 | Mowing (0107-2) | ACRE | 72.07 | $145.00 | $170.00 | $50.00 | $242.85 | $130.00 |
| 0095 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $49,716 | $40,000 | $100,000 | $112,190 | $90,000 |
| 0100 | Removal of existing concrete (0110-4-10) | SY | 543 | $35.50 | $40.00 | $75.00 | $44.26 | $35.00 |
| 0105 | Optional base, base group 04 (0285-704) | SY | 4,345 | $28.28 | $37.50 | $50.00 | $46.80 | $35.50 |
| 0110 | Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2) | SY | 30,772 | $2.34 | $3.75 | $3.00 | $3.81 | $7.00 |
| 0115 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 17,516 | $5.61 | $4.50 | $3.00 | $11.15 | $3.70 |
| 0120 | Milling existing asphalt pavement, 4" avg depth (0327-70-7) | SY | 53,649 | $2.92 | $2.50 | $3.00 | $5.33 | $7.75 |
| 0125 | Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53) | TN | 11,120.10 | $151.43 | $165.00 | $190.00 | $148.55 | $192.00 |
| 0130 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 8,768.30 | $157.18 | $172.00 | $190.00 | $180.18 | $217.00 |
| 0135 | Manhole, adjust (0425-5) | EACH | 17 | $1,250.00 | $2,000.00 | $1,600.00 | $2,741.01 | $2,000.00 |
| 0140 | Valve boxes, adjust (0425-6) | EACH | 3 | $1,250.00 | $2,000.00 | $1,200.00 | $2,380.01 | $1,200.00 |
| 0145 | Concrete curb & gutter, type F (0520-1-10) | LF | 523 | $41.50 | $62.00 | $50.00 | $51.74 | $62.00 |
| 0150 | Concrete curb, type D (0520-2-4) | LF | 8 | $41.50 | $110.00 | $100.00 | $51.74 | $120.00 |
| 0155 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 126 | $47.50 | $50.00 | $90.00 | $59.22 | $87.00 |
| 0160 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 345 | $68.50 | $85.00 | $140.00 | $85.40 | $110.00 |
| 0165 | Detectable warnings (0527-2) | SF | 910 | $35.00 | $40.00 | $35.00 | $43.63 | $46.00 |
| 0170 | Performance turf, sod (0570-1-2) | SY | 125 | $72.40 | $58.00 | $20.00 | $73.61 | $25.00 |
| 0175 | Raised pavement marker, type B (0706-1-3) | EACH | 2,381 | $4.00 | $5.25 | $4.50 | $6.56 | $4.20 |
| 0180 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 5.95 | $1,400.00 | $1,500.00 | $1,500.00 | $2,842.30 | $1,500.00 |
| 0185 | Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102) | GM | 0.06 | $1,500.00 | $2,000.00 | $2,000.00 | $2,580.98 | $1,550.00 |
| 0190 | Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123) | LF | 4,461 | $1.00 | $1.75 | $1.00 | $2.19 | $1.08 |
| 0195 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 1,089 | $2.00 | $2.00 | $2.00 | $3.28 | $2.15 |
| 0200 | Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131) | GM | 8.02 | $700.00 | $600.00 | $750.00 | $820.03 | $720.00 |
| 0205 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.12 | $700.00 | $600.00 | $1,000.00 | $921.74 | $715.00 |
| 0210 | Painted pavement markings, standard, white, message or symbol (0710-11160) | EACH | 19 | $60.00 | $90.00 | $75.00 | $87.47 | $62.00 |
| 0215 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 98 | $40.00 | $55.00 | $50.00 | $52.48 | $42.00 |
| 0220 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 3.84 | $1,400.00 | $1,500.00 | $1,500.00 | $2,838.33 | $1,500.00 |
| 0225 | Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224) | LF | 214 | $1.50 | $3.00 | $3.00 | $3.28 | $1.60 |
| 0230 | Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241) | GM | 0.57 | $700.00 | $900.00 | $1,000.00 | $916.27 | $715.00 |
| 0235 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $68,693 | $68,693 | $68,693 | $68,693 | $68,693 |
| 0240 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 31 | $450.00 | $550.00 | $500.00 | $869.31 | $470.00 |
| 0245 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 6 | $1,800.00 | $1,750.00 | $2,000.00 | $2,154.63 | $1,900.00 |
| 0250 | Single column ground sign assembly, remove (0700-1600) | EACH | 32 | $50.00 | $35.00 | $75.00 | $226.03 | $53.00 |
| 0255 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 20 | $200.00 | $195.00 | $250.00 | $359.68 | $215.00 |
| 0260 | Sign panel, furnish & install ground mount, 12-20 SF (0700-3102) | EACH | 1 | $250.00 | $350.00 | $350.00 | $599.98 | $270.00 |
| 0265 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 22 | $25.00 | $17.50 | $25.00 | $226.03 | $100.00 |
| 0270 | Sign panel, remove, 12-20 SF (0700-3602) | EACH | 1 | $50.00 | $22.50 | $100.00 | $226.03 | $200.00 |
| 0275 | Tubular marker, 36" white post (0704-1-3) | EACH | 2 | $150.00 | $255.00 | $150.00 | $374.73 | $164.00 |
| 0280 | Tubular marker, 36" yellow (0704-1-4) | EACH | 40 | $150.00 | $255.00 | $150.00 | $374.73 | $164.00 |
| 0285 | Raised pavement marker, type B (0706-1-3) | EACH | 2,299 | $4.00 | $5.25 | $4.50 | $6.56 | $4.30 |
| 0290 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 278 | $5.00 | $3.00 | $5.00 | $10.93 | $5.25 |
| 0295 | Painted pavement markings, surface (0710-90) | LS | 1 | $32,500 | $46,000 | $40,000 | $104,836 | $30,000 |
| 0300 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.06 | $6,500.00 | $6,500.00 | $7,500.00 | $9,302.62 | $6,600.00 |
| 0305 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 4,281 | $3.50 | $7.00 | $4.00 | $4.92 | $3.60 |
| 0310 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 1,044 | $6.00 | $9.00 | $7.00 | $8.75 | $6.18 |
| 0315 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.12 | $2,500.00 | $3,000.00 | $5,000.00 | $3,903.55 | $2,555.00 |
| 0320 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 19 | $225.00 | $200.00 | $250.00 | $213.21 | $231.00 |
| 0325 | Thermoplastic, standard, arrow (0711-11170) | EACH | 98 | $80.00 | $90.00 | $100.00 | $131.21 | $82.10 |
| 0330 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 214 | $5.00 | $8.00 | $5.00 | $7.65 | $5.15 |
| 0335 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.57 | $3,000.00 | $3,000.00 | $5,000.00 | $3,880.70 | $3,035.00 |
| 0340 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 2,078 | $15.00 | $17.00 | $17.00 | $13.34 | $15.40 |
| 0345 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 12 | $200.00 | $230.00 | $250.00 | $268.97 | $205.20 |
| 0350 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 12 | $100.00 | $160.00 | $100.00 | $164.01 | $102.60 |
| 0355 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 5.62 | $5,000.00 | $5,000.00 | $5,500.00 | $6,668.40 | $5,130.00 |
| 0360 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 7.36 | $2,500.00 | $2,000.00 | $2,800.00 | $1,967.81 | $2,565.00 |
| 0365 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 3.93 | $5,000.00 | $5,000.00 | $5,500.00 | $6,662.81 | $5,125.00 |
| 0370 | Permanent tape, white, solid, 6" for concrete bridges (0713-103101) | GM | 0.71 | $28,000 | $40,000 | $30,000 | $32,709 | $28,700 |
| 0375 | Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181) | GM | 1.42 | $8,500.00 | $17,000 | $10,000 | $23,987 | $8,695.00 |
| 0380 | Permanent tape, yellow, solid, for concrete bridges (0713-103201) | GM | 0.71 | $28,000 | $40,000 | $30,000 | $32,709 | $28,639 |
| 0385 | Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381) | GM | 1.42 | $8,500.00 | $17,000 | $10,000 | $23,987 | $8,700.00 |
| 0390 | Itsfm subsurface documentation- project length (0611-1-1) | MI | 2.49 | $4,259.02 | $5,000.00 | $3,900.00 | $1,804.57 | $4,630.00 |
| 0395 | Itsfm location documentation- intersection (0611-2-1) | EACH | 6 | $3,205.00 | $3,750.00 | $3,200.00 | $1,808.21 | $3,490.00 |
| 0400 | Conduit, furnish & install, open trench (0630-2-11) | LF | 124 | $25.79 | $30.00 | $25.00 | $17.81 | $28.00 |
| 0405 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,565 | $31.39 | $35.00 | $35.00 | $26.52 | $34.00 |
| 0410 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $2,024.00 | $2,500.00 | $3,000.00 | $6,191.18 | $2,200.00 |
| 0415 | Fiber optic cable locator (0633-6) | DA | 250 | $103.58 | $125.00 | $10.00 | $169.52 | $110.00 |
| 0420 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 47 | $623.30 | $750.00 | $1,500.00 | $1,782.89 | $650.00 |
| 0425 | Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70) | EACH | 2 | $4,394.50 | $5,000.00 | $10,000 | $8,690.11 | $4,600.00 |
| 0430 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 19 | $481.00 | $550.00 | $300.00 | $372.18 | $520.00 |
| 0435 | Loop detector, inductive, F&I, type 4, 1CHANNEL, solid state, shelf mounted, time delay (0660-1113) | EACH | 28 | $706.71 | $800.00 | $500.00 | $485.20 | $735.00 |
| 0440 | Loop detector inductive, remove- cabinet to remain (0660-1600) | EACH | 39 | $127.62 | $150.00 | $25.00 | $226.03 | $135.00 |
| 0445 | Loop assembly, F&I, type F (0660-2106) | AS | 64 | $1,715.61 | $2,000.00 | $1,700.00 | $2,307.84 | $1,800.00 |
| 0450 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 10 | $184.10 | $200.00 | $500.00 | $529.97 | $200.00 |
| 0455 | Pedestrian detector, relocate (0665-1-40) | EACH | 8 | $255.25 | $300.00 | $500.00 | $226.03 | $275.00 |
| 0460 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 10 | $198.80 | $230.00 | $100.00 | $56.51 | $210.00 |
| 0465 | Traffic controller, relocate- without cabinet (0671-2-50) | EACH | 1 | $327.00 | $375.00 | $350.00 | $1,130.13 | $350.00 |
| 0470 | Traffic signal controller cabinet, install (0676-1300) | EACH | 1 | $1,080.00 | $1,150.00 | $10,500 | $7,910.91 | $1,175.00 |
| 0475 | Traffic signal controller cabinet, remove (0676-1600) | EACH | 1 | $1,507.00 | $1,700.00 | $1,000.00 | $1,695.20 | $1,640.00 |
| 0480 | Managed field ethernet switch, relocate (0684-1-4) | EACH | 1 | $796.00 | $900.00 | $500.00 | $2,141.30 | $860.00 |
| 0485 | Uninterruptible power supply, install - equipment furnished others (0685-1-30) | EACH | 1 | $938.00 | $1,050.00 | $500.00 | $3,559.91 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.