FDOT contract T2A57 bid tabulation

SR 15 (US 17 / PARK AVE) FROM DOCTORS INLET TO WELLS RD. Let by Florida DOT on February 25, 2026, Clay, District 2. 5 bids received; low bid $5,326,772 by Preferred Materials Inc..

Owner
Florida DOT
Letting
25 FEB 2026
Pay items
97
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Preferred Materials Inc.$5,326,772Low
2Duval Asphalt Products, Inc.$5,913,228+11%
3Pigott Asphalt and Sitework LLC$6,496,855+22%
4Hubbard Construction Company$6,680,929+25%
5Watson Civil Construction, Inc.$7,225,350+36%
FDOT contract T2A57: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Preferred Materials Inc.2. Duval Asphalt Products, Inc.3. Pigott Asphalt and Sitework LLC4. Hubbard Construction Company5. Watson Civil Construction, Inc.
0005Bridge deck expansion joint, rehabilitation, poured joint backer rod (0458-1-21)LF844$59.00$68.50$124.50$63.68$85.00
0010Polymer nosing for bridge expansion joint (0458-2)CF24$860.00$1,000.00$1,000.00$928.24$890.00
0015Mobilization (0101-1)LS1$259,843$465,000$565,000$398,150$712,108
0020Maintenance of traffic (0102-1)DA1$403,440$224,000$390,000$678,613$291,000
0025Pedestrian or bicycle special detour (0102-4-1)SY1$875.00$13,000$7,500.00$3,079.37$8,000.00
0030Traffic control officer (0102-14)HR60$100.00$120.00$150.00$105.86$130.00
0035Work zone sign (0102-60)ED25,764$0.20$0.25$0.25$0.22$0.40
0040Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED27,012$0.10$0.15$0.01$0.11$0.20
0045Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD1,470$0.05$5.00$0.10$0.05$0.10
0050Arrow board / advance warning arrow panel (0102-76)ED516$5.00$5.50$1.00$5.40$8.00
0055Portable changeable message sign, temporary (0102-99)ED2,397$9.00$11.50$1.00$9.71$12.00
0060Temporary signalization and maintenance, intersection (0102-104)ED1,500$55.76$65.00$1.00$35.04$60.00
0065Temporary traffic detection and maintenance, intersection (0102-107-1)ED1,500$28.47$33.00$1.00$13.64$34.00
0070Type III barricade (0102-115)ED300$0.25$0.40$1.00$0.27$0.50
0075Sediment barrier (0104-10-3)LF473$0.98$1.25$5.00$1.06$6.00
0080Inlet protection system (0104-18)EACH68$100.00$125.00$150.00$107.94$150.00
0085Litter removal (0107-1)ACRE132.47$125.00$150.00$10.00$161.90$120.00
0090Mowing (0107-2)ACRE72.07$145.00$170.00$50.00$242.85$130.00
0095Clearing & grubbing (0110-1-1)ACRE1$49,716$40,000$100,000$112,190$90,000
0100Removal of existing concrete (0110-4-10)SY543$35.50$40.00$75.00$44.26$35.00
0105Optional base, base group 04 (0285-704)SY4,345$28.28$37.50$50.00$46.80$35.50
0110Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY30,772$2.34$3.75$3.00$3.81$7.00
0115Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY17,516$5.61$4.50$3.00$11.15$3.70
0120Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY53,649$2.92$2.50$3.00$5.33$7.75
0125Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN11,120.10$151.43$165.00$190.00$148.55$192.00
0130Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN8,768.30$157.18$172.00$190.00$180.18$217.00
0135Manhole, adjust (0425-5)EACH17$1,250.00$2,000.00$1,600.00$2,741.01$2,000.00
0140Valve boxes, adjust (0425-6)EACH3$1,250.00$2,000.00$1,200.00$2,380.01$1,200.00
0145Concrete curb & gutter, type F (0520-1-10)LF523$41.50$62.00$50.00$51.74$62.00
0150Concrete curb, type D (0520-2-4)LF8$41.50$110.00$100.00$51.74$120.00
0155Concrete sidewalk and driveways, 4" thick (0522-1)SY126$47.50$50.00$90.00$59.22$87.00
0160Concrete sidewalk and driveways, 6" thick (0522-2)SY345$68.50$85.00$140.00$85.40$110.00
0165Detectable warnings (0527-2)SF910$35.00$40.00$35.00$43.63$46.00
0170Performance turf, sod (0570-1-2)SY125$72.40$58.00$20.00$73.61$25.00
0175Raised pavement marker, type B (0706-1-3)EACH2,381$4.00$5.25$4.50$6.56$4.20
0180Painted pavement markings, standard, white, solid, 6" (0710-11101)GM5.95$1,400.00$1,500.00$1,500.00$2,842.30$1,500.00
0185Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.06$1,500.00$2,000.00$2,000.00$2,580.98$1,550.00
0190Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" (0710-11123)LF4,461$1.00$1.75$1.00$2.19$1.08
0195Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125)LF1,089$2.00$2.00$2.00$3.28$2.15
0200Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM8.02$700.00$600.00$750.00$820.03$720.00
0205Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.12$700.00$600.00$1,000.00$921.74$715.00
0210Painted pavement markings, standard, white, message or symbol (0710-11160)EACH19$60.00$90.00$75.00$87.47$62.00
0215Painted pavement markings, standard, white, arrows (0710-11170)EACH98$40.00$55.00$50.00$52.48$42.00
0220Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM3.84$1,400.00$1,500.00$1,500.00$2,838.33$1,500.00
0225Painted pavement markings, standard, yellow, solid for diagonal or chevron, 18" (0710-11224)LF214$1.50$3.00$3.00$3.28$1.60
0230Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.57$700.00$900.00$1,000.00$916.27$715.00
0235Initial contingency amount, DO not bid (0999-25)LS1$68,693$68,693$68,693$68,693$68,693
0240Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH31$450.00$550.00$500.00$869.31$470.00
0245Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH6$1,800.00$1,750.00$2,000.00$2,154.63$1,900.00
0250Single column ground sign assembly, remove (0700-1600)EACH32$50.00$35.00$75.00$226.03$53.00
0255Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH20$200.00$195.00$250.00$359.68$215.00
0260Sign panel, furnish & install ground mount, 12-20 SF (0700-3102)EACH1$250.00$350.00$350.00$599.98$270.00
0265Sign panel, remove, UP to 12 SF (0700-3601)EACH22$25.00$17.50$25.00$226.03$100.00
0270Sign panel, remove, 12-20 SF (0700-3602)EACH1$50.00$22.50$100.00$226.03$200.00
0275Tubular marker, 36" white post (0704-1-3)EACH2$150.00$255.00$150.00$374.73$164.00
0280Tubular marker, 36" yellow (0704-1-4)EACH40$150.00$255.00$150.00$374.73$164.00
0285Raised pavement marker, type B (0706-1-3)EACH2,299$4.00$5.25$4.50$6.56$4.30
0290Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF278$5.00$3.00$5.00$10.93$5.25
0295Painted pavement markings, surface (0710-90)LS1$32,500$46,000$40,000$104,836$30,000
0300Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102)GM0.06$6,500.00$6,500.00$7,500.00$9,302.62$6,600.00
0305Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF4,281$3.50$7.00$4.00$4.92$3.60
0310Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF1,044$6.00$9.00$7.00$8.75$6.18
0315Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.12$2,500.00$3,000.00$5,000.00$3,903.55$2,555.00
0320Thermoplastic, standard, message or symbol (0711-11160)EACH19$225.00$200.00$250.00$213.21$231.00
0325Thermoplastic, standard, arrow (0711-11170)EACH98$80.00$90.00$100.00$131.21$82.10
0330Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF214$5.00$8.00$5.00$7.65$5.15
0335Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.57$3,000.00$3,000.00$5,000.00$3,880.70$3,035.00
0340Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF2,078$15.00$17.00$17.00$13.34$15.40
0345Thermoplastic, preformed, white, message (0711-14160)EACH12$200.00$230.00$250.00$268.97$205.20
0350Thermoplastic, preformed, white, arrow (0711-14170)EACH12$100.00$160.00$100.00$164.01$102.60
0355Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM5.62$5,000.00$5,000.00$5,500.00$6,668.40$5,130.00
0360Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM7.36$2,500.00$2,000.00$2,800.00$1,967.81$2,565.00
0365Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM3.93$5,000.00$5,000.00$5,500.00$6,662.81$5,125.00
0370Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.71$28,000$40,000$30,000$32,709$28,700
0375Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM1.42$8,500.00$17,000$10,000$23,987$8,695.00
0380Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.71$28,000$40,000$30,000$32,709$28,639
0385Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM1.42$8,500.00$17,000$10,000$23,987$8,700.00
0390Itsfm subsurface documentation- project length (0611-1-1)MI2.49$4,259.02$5,000.00$3,900.00$1,804.57$4,630.00
0395Itsfm location documentation- intersection (0611-2-1)EACH6$3,205.00$3,750.00$3,200.00$1,808.21$3,490.00
0400Conduit, furnish & install, open trench (0630-2-11)LF124$25.79$30.00$25.00$17.81$28.00
0405Conduit, furnish & install, directional bore (0630-2-12)LF1,565$31.39$35.00$35.00$26.52$34.00
0410Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$2,024.00$2,500.00$3,000.00$6,191.18$2,200.00
0415Fiber optic cable locator (0633-6)DA250$103.58$125.00$10.00$169.52$110.00
0420Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH47$623.30$750.00$1,500.00$1,782.89$650.00
0425Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70)EACH2$4,394.50$5,000.00$10,000$8,690.11$4,600.00
0430Loop detector inductive, F&I, type 10 (0660-1110)EACH19$481.00$550.00$300.00$372.18$520.00
0435Loop detector, inductive, F&I, type 4, 1CHANNEL, solid state, shelf mounted, time delay (0660-1113)EACH28$706.71$800.00$500.00$485.20$735.00
0440Loop detector inductive, remove- cabinet to remain (0660-1600)EACH39$127.62$150.00$25.00$226.03$135.00
0445Loop assembly, F&I, type F (0660-2106)AS64$1,715.61$2,000.00$1,700.00$2,307.84$1,800.00
0450Pedestrian detector, furnish & install, standard (0665-1-11)EACH10$184.10$200.00$500.00$529.97$200.00
0455Pedestrian detector, relocate (0665-1-40)EACH8$255.25$300.00$500.00$226.03$275.00
0460Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH10$198.80$230.00$100.00$56.51$210.00
0465Traffic controller, relocate- without cabinet (0671-2-50)EACH1$327.00$375.00$350.00$1,130.13$350.00
0470Traffic signal controller cabinet, install (0676-1300)EACH1$1,080.00$1,150.00$10,500$7,910.91$1,175.00
0475Traffic signal controller cabinet, remove (0676-1600)EACH1$1,507.00$1,700.00$1,000.00$1,695.20$1,640.00
0480Managed field ethernet switch, relocate (0684-1-4)EACH1$796.00$900.00$500.00$2,141.30$860.00
0485Uninterruptible power supply, install - equipment furnished others (0685-1-30)EACH1$938.00$1,050.00$500.00$3,559.91$1,000.00
FDOT contract T2A57: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy