| 0005 | Mobilization (0101-1) | LS | 1 | $127,242 | $182,000 | $115,475 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $50,000 | $74,000 | $126,000 |
| 0015 | Traffic control officer (0102-14) | HR | 136 | $87.00 | $60.00 | $100.00 |
| 0020 | Work zone sign (0102-60) | ED | 9,296 | $0.40 | $0.40 | $0.45 |
| 0025 | Temporary barrier, F&I, low profile, concrete (0102-71-13) | LF | 312 | $73.00 | $68.00 | $263.00 |
| 0030 | Temporary barrier, relocate, low profile concrete (0102-71-23) | LF | 144 | $29.00 | $27.00 | $225.00 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 11,171 | $0.15 | $0.15 | $0.20 |
| 0040 | Arrow board / advance warning arrow panel (0102-76) | ED | 197 | $17.00 | $16.00 | $20.00 |
| 0045 | Portable changeable message sign, temporary (0102-99) | ED | 1,067 | $29.00 | $27.00 | $28.00 |
| 0050 | Temporary signalization and maintenance, intersection (0102-104) | ED | 180 | $11.60 | $20.00 | $20.00 |
| 0055 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 180 | $11.60 | $18.00 | $20.00 |
| 0060 | Type III barricade (0102-115) | ED | 110 | $0.50 | $0.50 | $0.55 |
| 0065 | Sediment barrier (0104-10-3) | LF | 608 | $5.00 | $3.80 | $3.50 |
| 0070 | Inlet protection system (0104-18) | EACH | 2 | $420.00 | $230.00 | $750.00 |
| 0075 | Litter removal (0107-1) | ACRE | 2.03 | $600.00 | $640.00 | $655.00 |
| 0080 | Mowing (0107-2) | ACRE | 0.56 | $2,150.00 | $2,300.00 | $2,400.00 |
| 0085 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $30,000 | $35,000 | $55,000 |
| 0090 | Removal of existing concrete (0110-4-10) | SY | 72 | $45.00 | $39.00 | $55.00 |
| 0095 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $10,000 | $9,072.00 | $22,500 |
| 0100 | Optional base, base group 13 (0285-713) | SY | 338 | $90.00 | $120.00 | $66.70 |
| 0105 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 4,819 | $3.50 | $7.50 | $4.50 |
| 0110 | Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52) | TN | 75.10 | $186.00 | $390.00 | $180.00 |
| 0115 | Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81) | TN | 425.40 | $185.00 | $240.00 | $180.00 |
| 0120 | Miscellaneous asphalt (0339-1) | TN | 7.10 | $440.00 | $700.00 | $950.00 |
| 0125 | Concrete class IV, culverts (0400-4-1) | CY | 14.80 | $2,500.00 | $3,900.00 | $2,581.00 |
| 0130 | Reinforcing steel- roadway (0415-1-1) | LB | 2,713 | $2.00 | $6.10 | $1.25 |
| 0135 | Inlets, curb, type J-6, <10' (0425-1461) | EACH | 1 | $22,850 | $25,000 | $34,950 |
| 0140 | Inlets, DT bot, type C,jbot, <10' (0425-1523) | EACH | 1 | $16,520 | $19,000 | $29,480 |
| 0145 | Inlets, closed flume (0425-1910) | EACH | 1 | $5,435.00 | $4,300.00 | $16,650 |
| 0150 | Pipe culvert, opt material, round, 36"S/CD (0430-175136) | LF | 470 | $223.00 | $230.00 | $420.00 |
| 0155 | Desilting concrete box culvert (0430-950) | CY | 18.30 | $1,150.00 | $310.00 | $605.00 |
| 0160 | Mitered end section, optional round, 36" CD (0430-982138) | EACH | 2 | $6,500.00 | $7,100.00 | $7,600.00 |
| 0165 | Pipe handrail - guiderail, aluminum (0515-1-2) | LF | 14 | $58.00 | $54.00 | $55.00 |
| 0170 | Concrete curb & gutter, type F (0520-1-10) | LF | 328 | $38.00 | $41.00 | $53.40 |
| 0175 | Concrete traffic separator, special- variable width (0520-70) | SY | 6 | $337.00 | $290.00 | $138.00 |
| 0180 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 243 | $75.00 | $89.00 | $65.00 |
| 0185 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 56 | $118.00 | $180.00 | $95.00 |
| 0190 | Concrete ditch pavement, non reinforced, 4" (0524-1-2) | SY | 3 | $432.00 | $370.00 | $350.00 |
| 0195 | Detectable warnings (0527-2) | SF | 76 | $29.00 | $27.00 | $55.00 |
| 0200 | Guardrail -roadway, general (0536-1-1) | LF | 95 | $29.00 | $27.00 | $27.50 |
| 0205 | Special guardrail post- special steel post for concrete structure mount (0536-7-2) | EACH | 2 | $350.00 | $330.00 | $330.00 |
| 0210 | Guardrail removal (0536-73) | LF | 62 | $2.30 | $2.15 | $22.00 |
| 0215 | Guardrail end treatment- type CRT (0536-85-26) | EACH | 2 | $4,340.00 | $4,100.00 | $4,125.00 |
| 0220 | Performance turf, sod (0570-1-2) | SY | 15 | $7.00 | $20.00 | $55.00 |
| 0225 | Performance turf, sod and shoulder treatment index (0570-1-3) | SY | 476 | $9.00 | $9.55 | $33.97 |
| 0230 | Raised pavement marker, type B (0706-1-3) | EACH | 9 | $5.70 | $5.40 | $5.50 |
| 0235 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.03 | $1,730.00 | $1,500.00 | $1,650.00 |
| 0240 | Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" (0710-11125) | LF | 10 | $11.50 | $11.00 | $11.00 |
| 0245 | Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141) | GM | 0.03 | $1,730.00 | $1,200.00 | $1,650.00 |
| 0250 | Painted pavement markings, standard, white, arrows (0710-11170) | EACH | 3 | $75.00 | $70.00 | $71.50 |
| 0255 | Raised pavement marker, type B (0706-1-3) | EACH | 107 | $5.70 | $5.40 | $5.50 |
| 0260 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 98 | $11.50 | $11.00 | $11.00 |
| 0265 | Painted pavement markings, surface (0710-90) | LS | 1 | $5,517.00 | $5,200.00 | $5,240.00 |
| 0270 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 315 | $6.00 | $6.50 | $6.60 |
| 0275 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 78 | $9.00 | $8.65 | $8.80 |
| 0280 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 141 | $13.00 | $13.00 | $13.20 |
| 0285 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.10 | $4,600.00 | $4,100.00 | $4,400.00 |
| 0290 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.02 | $4,600.00 | $3,600.00 | $4,400.00 |
| 0295 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 188 | $17.00 | $16.00 | $16.50 |
| 0300 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 4 | $170.00 | $160.00 | $165.00 |
| 0305 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 19 | $170.00 | $160.00 | $165.00 |
| 0310 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.49 | $5,200.00 | $4,800.00 | $4,950.00 |
| 0315 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 0.01 | $4,600.00 | $4,300.00 | $4,400.00 |
| 0320 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.17 | $5,200.00 | $4,800.00 | $4,950.00 |
| 0325 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 |
| 0330 | Itsfm location documentation- intersection (0611-2-1) | EACH | 1 | $3,470.00 | $4,300.00 | $3,300.00 |
| 0335 | Conduit, furnish & install, open trench (0630-2-11) | LF | 134 | $23.00 | $18.00 | $22.00 |
| 0340 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 215 | $52.00 | $76.00 | $50.00 |
| 0345 | Conduit, furnish & install, aboveground (0630-2-14) | LF | 36 | $23.00 | $43.00 | $22.00 |
| 0350 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $17,000 | $11,000 | $16,500 |
| 0355 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $1,100.00 | $1,100.00 | $1,100.00 |
| 0360 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 13 | $1,800.00 | $1,700.00 | $1,711.00 |
| 0365 | Electrical power service, F&I, overhead meter purchased by contractor from power company (0639-1112) | AS | 1 | $4,000.00 | $6,000.00 | $3,850.00 |
| 0370 | Electrical service wire, & install (0639-2-1) | LF | 82 | $11.00 | $8.65 | $11.00 |
| 0375 | Electrical service disconnect, F&I, pole mount (0639-3-11) | EACH | 1 | $800.00 | $1,100.00 | $800.00 |
| 0380 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $2,500.00 | $2,700.00 | $2,420.00 |
| 0385 | Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70) | EACH | 2 | $9,200.00 | $7,600.00 | $8,800.00 |
| 0390 | Aluminum signals pole, (0646-1-11) | EACH | 3 | $5,700.00 | $3,800.00 | $5,500.00 |
| 0395 | Aluminum signals pole, remove (0646-1-60) | EACH | 3 | $500.00 | $430.00 | $550.00 |
| 0400 | Steel mast arm assembly, and install, double arm 78'-60' (0649-21-25) | EACH | 1 | $170,000 | $150,000 | $167,200 |
| 0405 | Steel mast arm assembly, and install, double arm 78'-70' (0649-21-26) | EACH | 1 | $180,000 | $160,000 | $176,000 |
| 0410 | Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34) | AS | 6 | $2,300.00 | $2,200.00 | $2,200.00 |
| 0415 | Vehicular traffic signal, furnish & install 4 section, 1 way (0650-1-36) | AS | 2 | $2,800.00 | $2,600.00 | $2,750.00 |
| 0420 | Vehicular traffic signal, furnish & install 5 section straight, 1 way (0650-1-38) | AS | 3 | $3,700.00 | $2,700.00 | $3,520.00 |
| 0425 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 2 | $1,700.00 | $1,500.00 | $1,650.00 |
| 0430 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $2,800.00 | $2,700.00 | $2,750.00 |
| 0435 | Vehicle detection system- furnish & install cabinet equipment (0660-4-11) | EACH | 1 | $38,000 | $43,000 | $36,300 |
| 0440 | Vehicle detection system- furnish & install above ground equipment (0660-4-12) | EACH | 3 | $17,000 | $9,200.00 | $16,500 |
| 0445 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 4 | $800.00 | $540.00 | $825.00 |
| 0450 | Traffic controller assembly, relocate controller with cabinet (0670-5500) | AS | 1 | $13,000 | $11,000 | $13,200 |
| 0455 | ITS CCTV camera, non- pressurized, IP, high definition (0682-1173) | EACH | 1 | $9,000.00 | $7,900.00 | $8,800.00 |
| 0460 | Uninterruptible power supply, furnish and install, online/double conversion with cabinet (0685-1-14) | EACH | 1 | $15,000 | $14,000 | $14,300 |
| 0465 | Sign panel, furnish & install overhead mount, UP to 12 SF (0700-3201) | EACH | 2 | $1,200.00 | $1,100.00 | $1,210.00 |
| 0470 | Internally illuminated sign, furnish & install overhead mount, UP to 12 SF (0700-5-21) | EACH | 2 | $6,000.00 | $4,300.00 | $5,775.00 |
| 0475 | Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22) | EACH | 2 | $6,700.00 | $5,400.00 | $6,380.00 |