FDOT contract T4723 bid tabulation
SR 5 (US 1) FROM PALMETTO PARK RD TO SR 850 (NORTHLAKE BLVD). Let by Florida DOT on April 29, 2026, Palm Beach, District 4. 4 bids received; low bid $2,274,905 by Weekley Asphalt Paving, Inc..
- Owner
- Florida DOT
- Letting
- 29 APR 2026
- Pay items
- 80
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Weekley Asphalt Paving, Inc. | $2,274,905 | Low |
| 2 | The Stout Group LLC | $2,493,437 | +10% |
| 3 | West Construction, Inc. | $2,742,569 | +21% |
| 4 | Florida Engineering & Development Corp | $2,771,862 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Weekley Asphalt Paving, Inc. | 2. The Stout Group LLC | 3. West Construction, Inc. | 4. Florida Engineering & Development Corp |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $132,000 | $240,000 | $325,000 | $209,623 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $297,400 | $225,000 | $150,000 | $58,961 |
| 0015 | Pedestrian or bicycle special detour (0102-4-1) | SY | 1 | $63,110 | $23,000 | $70,000 | $19,644 |
| 0020 | Pedestrian escort/flagger (0102-5) | HR | 1,560 | $59.00 | $63.00 | $35.00 | $24.25 |
| 0025 | Traffic control officer (0102-14) | HR | 208 | $90.00 | $105.00 | $45.00 | $68.06 |
| 0030 | Work zone sign (0102-60) | ED | 8,060 | $0.23 | $0.26 | $0.24 | $0.20 |
| 0035 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 31,850 | $0.20 | $0.14 | $0.15 | $0.10 |
| 0040 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 7,980 | $0.20 | $0.12 | $0.15 | $0.08 |
| 0045 | Arrow board / advance warning arrow panel (0102-76) | ED | 560 | $7.00 | $7.00 | $5.60 | $5.09 |
| 0050 | Portable changeable message sign, temporary (0102-99) | ED | 3,887 | $12.00 | $10.00 | $15.00 | $6.78 |
| 0055 | Temporary signalization and maintenance, intersection (0102-104) | ED | 160 | $17.00 | $10.00 | $20.00 | $6.20 |
| 0060 | Existing ITS maintenance (0102-112) | DA | 250 | $139.00 | $10.00 | $210.00 | $132.91 |
| 0065 | Type III barricade (0102-115) | ED | 260 | $1.50 | $0.69 | $0.50 | $0.51 |
| 0070 | Removable tape, white, symbol or arrow (0102-913-29) | EACH | 1 | $697.00 | $700.00 | $350.00 | $591.11 |
| 0075 | Sediment barrier (0104-10-3) | LF | 1,578 | $4.50 | $4.00 | $5.00 | $3.04 |
| 0080 | Inlet protection system (0104-18) | EACH | 10 | $250.00 | $175.00 | $215.00 | $132.30 |
| 0085 | Litter removal (0107-1) | ACRE | 6.02 | $200.00 | $1.00 | $85.00 | $0.50 |
| 0090 | Mowing (0107-2) | ACRE | 1.98 | $200.00 | $1.00 | $85.00 | $1.83 |
| 0095 | Monitor existing structures- inspection and settlement monitoring (0108-1) | LS | 1 | $12,600 | $6,500.00 | $20,000 | $5,851.70 |
| 0100 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $91,000 | $200,000 | $100,000 | $35,045 |
| 0105 | Selective clearing and areas with trees to remain (0110-2-2) | ACRE | 0.01 | $50,000 | $1.00 | $100,000 | $366,978 |
| 0110 | Removal of existing concrete (0110-4-10) | SY | 1,100 | $69.00 | $35.00 | $45.00 | $44.78 |
| 0115 | Tree protection barrier (0110-21) | LF | 33 | $18.00 | $18.00 | $6.00 | $15.69 |
| 0120 | Borrow excavation, truck measure (0120-2-2) | CY | 517 | $70.00 | $65.00 | $75.00 | $85.80 |
| 0125 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $63,200 | $30,000 | $20,000 | $33,613 |
| 0130 | Inlets, curb type P-1, partial (0425-1315) | EACH | 1 | $7,000.00 | $11,000 | $6,720.00 | $4,754.86 |
| 0135 | Inlets, DT bot, type C,<10' (0425-1521) | EACH | 1 | $12,000 | $18,000 | $7,850.00 | $6,281.97 |
| 0140 | Manholes, P-8, partial (0425-2-63) | EACH | 1 | $8,000.00 | $10,000 | $7,000.00 | $3,857.07 |
| 0145 | Manhole, adjust (0425-5) | EACH | 2 | $1,200.00 | $1,500.00 | $1,000.00 | $1,496.92 |
| 0150 | Valve boxes, adjust (0425-6) | EACH | 3 | $850.00 | $950.00 | $1,000.00 | $897.20 |
| 0155 | Pipe culvert,optional material,round, 18"S/CD (0430-175118) | LF | 41 | $550.00 | $300.00 | $200.00 | $178.30 |
| 0160 | Concrete curb & gutter, type F (0520-1-10) | LF | 1,490 | $63.53 | $75.00 | $65.00 | $73.70 |
| 0165 | Concrete curb & gutter, type F with special gutter profile (0520-1-12) | LF | 14 | $70.00 | $75.00 | $70.00 | $82.21 |
| 0170 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 606 | $65.00 | $140.00 | $95.00 | $48.45 |
| 0175 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 119 | $75.00 | $175.00 | $110.00 | $72.59 |
| 0180 | Bus shelter pad, fiber reinforced concrete (0522-4-1) | SY | 1,040 | $157.00 | $300.00 | $160.00 | $204.84 |
| 0185 | Detectable warnings (0527-2) | SF | 1,681 | $48.00 | $45.00 | $35.00 | $28.48 |
| 0190 | Performance turf, sod (0570-1-2) | SY | 419 | $25.00 | $40.00 | $5.60 | $7.54 |
| 0195 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0200 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
| 0205 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $215.00 | $215.00 | $215.00 | $215.00 |
| 0210 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 5 | $695.00 | $900.00 | $650.00 | $589.41 |
| 0215 | Single column ground sign assembly, relocate (0700-1500) | EACH | 17 | $625.00 | $600.00 | $500.00 | $530.05 |
| 0220 | Object marker, type 2 (0705-10-2) | EACH | 1 | $450.00 | $800.00 | $175.00 | $381.63 |
| 0225 | Raised pavement marker, type B (0706-1-3) | EACH | 12 | $5.00 | $12.00 | $6.00 | $4.24 |
| 0230 | Painted pavement markings, surface (0710-90) | LS | 1 | $2,800.00 | $6,000.00 | $10,000 | $1,102.49 |
| 0235 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.06 | $3,000.00 | $3,700.00 | $3,000.00 | $6,839.35 |
| 0240 | Thermoplastic, standard, arrow (0711-11170) | EACH | 2 | $300.00 | $100.00 | $100.00 | $101.77 |
| 0245 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 1 | $290.00 | $350.00 | $55.00 | $220.50 |
| 0250 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 1 | $170.00 | $190.00 | $55.00 | $127.21 |
| 0255 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.06 | $6,000.00 | $6,300.00 | $6,000.00 | $6,730.79 |
| 0260 | Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1) | SF | 434 | $10.00 | $18.00 | $3.25 | $3.39 |
| 0265 | Green-colored pavement markings, bike lane (0714-10) | SF | 1,261 | $15.00 | $15.00 | $9.00 | $8.48 |
| 0270 | Conduit, furnish & install, open trench (0630-2-11) | LF | 6 | $45.00 | $41.00 | $20.00 | $30.57 |
| 0275 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 234 | $45.00 | $41.00 | $50.00 | $30.57 |
| 0280 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 4 | $2,300.00 | $2,100.00 | $1,500.00 | $1,267.47 |
| 0285 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 2,754 | $5.90 | $7.00 | $3.00 | $2.93 |
| 0290 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 302 | $2.00 | $2.00 | $1.25 | $0.36 |
| 0295 | Special lighting system assembly, solar-powered light pole for bus shelter (0715-52-48) | EACH | 13 | $6,000.00 | $15,000 | $20,000 | $14,733 |
| 0300 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 2 | $800.00 | $800.00 | $1,000.00 | $793.40 |
| 0305 | Light pole complete- special design, relocate (0715-540000) | EACH | 2 | $9,000.00 | $6,200.00 | $6,500.00 | $3,092.69 |
| 0310 | Conduit, furnish & install, open trench (0630-2-11) | LF | 87 | $30.00 | $41.00 | $20.00 | $15.14 |
| 0315 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 595 | $45.00 | $41.00 | $50.00 | $32.90 |
| 0320 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 4 | $12,000 | $14,000 | $15,000 | $6,807.79 |
| 0325 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 18 | $1,670.00 | $1,600.00 | $2,000.00 | $1,453.67 |
| 0330 | Aluminum signals pole, (0646-1-11) | EACH | 3 | $2,000.00 | $1,700.00 | $2,750.00 | $1,984.68 |
| 0335 | Aluminum signals pole, remove (0646-1-60) | EACH | 2 | $300.00 | $80.00 | $500.00 | $443.03 |
| 0340 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 2 | $1,400.00 | $1,900.00 | $1,250.00 | $898.14 |
| 0345 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $1,700.00 | $2,600.00 | $2,500.00 | $1,683.63 |
| 0350 | Loop detector, inductive, F&I, type 4, 2CHANNEL, solid state, shelf mounted, time delay (0660-1104) | EACH | 2 | $350.00 | $3,600.00 | $750.00 | $305.85 |
| 0355 | Loop assembly, F&I, type B (0660-2102) | AS | 2 | $3,400.00 | $1,200.00 | $3,500.00 | $1,421.88 |
| 0360 | Loop assembly, F&I, type F (0660-2106) | AS | 2 | $3,400.00 | $1,900.00 | $3,000.00 | $1,656.49 |
| 0365 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 4 | $700.00 | $500.00 | $750.00 | $382.04 |
| 0370 | Traffic controller, modify (0671-2-40) | EACH | 3 | $4,000.00 | $2,700.00 | $6,000.00 | $1,550.84 |
| 0375 | Landscape complete- small plants (0580-1-1) | LS | 1 | $33,000 | $40,000 | $226,000 | $59,302 |
| 0380 | Landscape complete- large plants (0580-1-2) | LS | 1 | $2,400.00 | $6,000.00 | $16,500 | $34,347 |
| 0385 | Architectural, bus shelter, F&I, 50-100 SF (0751-35-12) | EACH | 13 | $22,250 | $18,000 | $30,000 | $72,250 |
| 0390 | Bicycle rack, furnish & install, 2 bicycles (0751-36-11) | EACH | 39 | $1,480.00 | $500.00 | $750.00 | $3,750.00 |
| 0395 | Trash receptacle (0751-37) | EACH | 26 | $890.00 | $1,000.00 | $1,000.00 | $4,900.00 |
| 0400 | Fiber optic cable locator (0633-6) | DA | 250 | $170.00 | $25.00 | $315.00 | $141.77 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of April 29, 2026. Compiled by Mirage Metrics.