FDOT contract T4723 bid tabulation

SR 5 (US 1) FROM PALMETTO PARK RD TO SR 850 (NORTHLAKE BLVD). Let by Florida DOT on April 29, 2026, Palm Beach, District 4. 4 bids received; low bid $2,274,905 by Weekley Asphalt Paving, Inc..

Owner
Florida DOT
Letting
29 APR 2026
Pay items
80
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Weekley Asphalt Paving, Inc.$2,274,905Low
2The Stout Group LLC$2,493,437+10%
3West Construction, Inc.$2,742,569+21%
4Florida Engineering & Development Corp$2,771,862+22%
FDOT contract T4723: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Weekley Asphalt Paving, Inc.2. The Stout Group LLC3. West Construction, Inc.4. Florida Engineering & Development Corp
0005Mobilization (0101-1)LS1$132,000$240,000$325,000$209,623
0010Maintenance of traffic (0102-1)DA1$297,400$225,000$150,000$58,961
0015Pedestrian or bicycle special detour (0102-4-1)SY1$63,110$23,000$70,000$19,644
0020Pedestrian escort/flagger (0102-5)HR1,560$59.00$63.00$35.00$24.25
0025Traffic control officer (0102-14)HR208$90.00$105.00$45.00$68.06
0030Work zone sign (0102-60)ED8,060$0.23$0.26$0.24$0.20
0035Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED31,850$0.20$0.14$0.15$0.10
0040Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD7,980$0.20$0.12$0.15$0.08
0045Arrow board / advance warning arrow panel (0102-76)ED560$7.00$7.00$5.60$5.09
0050Portable changeable message sign, temporary (0102-99)ED3,887$12.00$10.00$15.00$6.78
0055Temporary signalization and maintenance, intersection (0102-104)ED160$17.00$10.00$20.00$6.20
0060Existing ITS maintenance (0102-112)DA250$139.00$10.00$210.00$132.91
0065Type III barricade (0102-115)ED260$1.50$0.69$0.50$0.51
0070Removable tape, white, symbol or arrow (0102-913-29)EACH1$697.00$700.00$350.00$591.11
0075Sediment barrier (0104-10-3)LF1,578$4.50$4.00$5.00$3.04
0080Inlet protection system (0104-18)EACH10$250.00$175.00$215.00$132.30
0085Litter removal (0107-1)ACRE6.02$200.00$1.00$85.00$0.50
0090Mowing (0107-2)ACRE1.98$200.00$1.00$85.00$1.83
0095Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$12,600$6,500.00$20,000$5,851.70
0100Clearing & grubbing (0110-1-1)ACRE1$91,000$200,000$100,000$35,045
0105Selective clearing and areas with trees to remain (0110-2-2)ACRE0.01$50,000$1.00$100,000$366,978
0110Removal of existing concrete (0110-4-10)SY1,100$69.00$35.00$45.00$44.78
0115Tree protection barrier (0110-21)LF33$18.00$18.00$6.00$15.69
0120Borrow excavation, truck measure (0120-2-2)CY517$70.00$65.00$75.00$85.80
0125Regular excavation (3-R projects only) (0120-71)LS1$63,200$30,000$20,000$33,613
0130Inlets, curb type P-1, partial (0425-1315)EACH1$7,000.00$11,000$6,720.00$4,754.86
0135Inlets, DT bot, type C,<10' (0425-1521)EACH1$12,000$18,000$7,850.00$6,281.97
0140Manholes, P-8, partial (0425-2-63)EACH1$8,000.00$10,000$7,000.00$3,857.07
0145Manhole, adjust (0425-5)EACH2$1,200.00$1,500.00$1,000.00$1,496.92
0150Valve boxes, adjust (0425-6)EACH3$850.00$950.00$1,000.00$897.20
0155Pipe culvert,optional material,round, 18"S/CD (0430-175118)LF41$550.00$300.00$200.00$178.30
0160Concrete curb & gutter, type F (0520-1-10)LF1,490$63.53$75.00$65.00$73.70
0165Concrete curb & gutter, type F with special gutter profile (0520-1-12)LF14$70.00$75.00$70.00$82.21
0170Concrete sidewalk and driveways, 4" thick (0522-1)SY606$65.00$140.00$95.00$48.45
0175Concrete sidewalk and driveways, 6" thick (0522-2)SY119$75.00$175.00$110.00$72.59
0180Bus shelter pad, fiber reinforced concrete (0522-4-1)SY1,040$157.00$300.00$160.00$204.84
0185Detectable warnings (0527-2)SF1,681$48.00$45.00$35.00$28.48
0190Performance turf, sod (0570-1-2)SY419$25.00$40.00$5.60$7.54
0195Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00
0200Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000
0205Local agency initial amount (DO not bid) (0999-26)LS1$215.00$215.00$215.00$215.00
0210Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH5$695.00$900.00$650.00$589.41
0215Single column ground sign assembly, relocate (0700-1500)EACH17$625.00$600.00$500.00$530.05
0220Object marker, type 2 (0705-10-2)EACH1$450.00$800.00$175.00$381.63
0225Raised pavement marker, type B (0706-1-3)EACH12$5.00$12.00$6.00$4.24
0230Painted pavement markings, surface (0710-90)LS1$2,800.00$6,000.00$10,000$1,102.49
0235Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.06$3,000.00$3,700.00$3,000.00$6,839.35
0240Thermoplastic, standard, arrow (0711-11170)EACH2$300.00$100.00$100.00$101.77
0245Thermoplastic, preformed, white, message (0711-14160)EACH1$290.00$350.00$55.00$220.50
0250Thermoplastic, preformed, white, arrow (0711-14170)EACH1$170.00$190.00$55.00$127.21
0255Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.06$6,000.00$6,300.00$6,000.00$6,730.79
0260Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF434$10.00$18.00$3.25$3.39
0265Green-colored pavement markings, bike lane (0714-10)SF1,261$15.00$15.00$9.00$8.48
0270Conduit, furnish & install, open trench (0630-2-11)LF6$45.00$41.00$20.00$30.57
0275Conduit, furnish & install, directional bore (0630-2-12)LF234$45.00$41.00$50.00$30.57
0280Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH4$2,300.00$2,100.00$1,500.00$1,267.47
0285Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF2,754$5.90$7.00$3.00$2.93
0290Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF302$2.00$2.00$1.25$0.36
0295Special lighting system assembly, solar-powered light pole for bus shelter (0715-52-48)EACH13$6,000.00$15,000$20,000$14,733
0300Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH2$800.00$800.00$1,000.00$793.40
0305Light pole complete- special design, relocate (0715-540000)EACH2$9,000.00$6,200.00$6,500.00$3,092.69
0310Conduit, furnish & install, open trench (0630-2-11)LF87$30.00$41.00$20.00$15.14
0315Conduit, furnish & install, directional bore (0630-2-12)LF595$45.00$41.00$50.00$32.90
0320Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI4$12,000$14,000$15,000$6,807.79
0325Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH18$1,670.00$1,600.00$2,000.00$1,453.67
0330Aluminum signals pole, (0646-1-11)EACH3$2,000.00$1,700.00$2,750.00$1,984.68
0335Aluminum signals pole, remove (0646-1-60)EACH2$300.00$80.00$500.00$443.03
0340Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS2$1,400.00$1,900.00$1,250.00$898.14
0345Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS1$1,700.00$2,600.00$2,500.00$1,683.63
0350Loop detector, inductive, F&I, type 4, 2CHANNEL, solid state, shelf mounted, time delay (0660-1104)EACH2$350.00$3,600.00$750.00$305.85
0355Loop assembly, F&I, type B (0660-2102)AS2$3,400.00$1,200.00$3,500.00$1,421.88
0360Loop assembly, F&I, type F (0660-2106)AS2$3,400.00$1,900.00$3,000.00$1,656.49
0365Pedestrian detector, furnish & install, standard (0665-1-11)EACH4$700.00$500.00$750.00$382.04
0370Traffic controller, modify (0671-2-40)EACH3$4,000.00$2,700.00$6,000.00$1,550.84
0375Landscape complete- small plants (0580-1-1)LS1$33,000$40,000$226,000$59,302
0380Landscape complete- large plants (0580-1-2)LS1$2,400.00$6,000.00$16,500$34,347
0385Architectural, bus shelter, F&I, 50-100 SF (0751-35-12)EACH13$22,250$18,000$30,000$72,250
0390Bicycle rack, furnish & install, 2 bicycles (0751-36-11)EACH39$1,480.00$500.00$750.00$3,750.00
0395Trash receptacle (0751-37)EACH26$890.00$1,000.00$1,000.00$4,900.00
0400Fiber optic cable locator (0633-6)DA250$170.00$25.00$315.00$141.77
FDOT contract T4723: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of April 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy