FDOT contract T4733 bid tabulation
SR 9 (I-95) NB EXIT RAMP TO WB SR 68 (ORANGE AVE). Let by Florida DOT on July 30, 2025, St Lucie, District 4. 4 bids received; low bid $840,956 by C.W. Roberts Contracting, Inc..
- Owner
- Florida DOT
- Letting
- 30 JUL 2025
- Pay items
- 48
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C.W. Roberts Contracting, Inc. | $840,956 | Low |
| 2 | Carr Construction, LLC | $870,928 | +4.0% |
| 3 | Ranger Construction Industries, Inc. | $890,801 | +6.0% |
| 4 | The Stout Group LLC | $1,320,500 | +57% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C.W. Roberts Contracting, Inc. | 2. Carr Construction, LLC | 3. Ranger Construction Industries, Inc. | 4. The Stout Group LLC |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $154,000 | $108,200 | $89,000 | $130,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $55,000 | $84,000 | $237,190 | $400,000 |
| 0015 | Traffic control officer (0102-14) | HR | 30 | $89.25 | $112.00 | $91.50 | $200.00 |
| 0020 | Work zone sign (0102-60) | ED | 621 | $0.60 | $0.60 | $0.60 | $0.37 |
| 0025 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 5,010 | $0.35 | $0.30 | $0.30 | $0.19 |
| 0030 | Portable changeable message sign, temporary (0102-99) | ED | 38 | $36.65 | $28.00 | $30.50 | $22.00 |
| 0035 | Type III barricade (0102-115) | ED | 5 | $2.50 | $0.60 | $0.60 | $1.50 |
| 0040 | Sediment barrier (0104-10-3) | LF | 1,450 | $8.70 | $4.30 | $5.45 | $9.00 |
| 0045 | Inlet protection system (0104-18) | EACH | 3 | $333.00 | $223.00 | $203.80 | $250.00 |
| 0050 | Litter removal (0107-1) | ACRE | 27.46 | $224.00 | $89.00 | $147.10 | $1.00 |
| 0055 | Mowing (0107-2) | ACRE | 25.69 | $454.00 | $178.00 | $285.90 | $1.00 |
| 0060 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $12,000 | $24,465 | $14,900 | $100,000 |
| 0065 | Regular excavation (0120-1) | CY | 112.90 | $81.25 | $65.00 | $34.45 | $65.00 |
| 0070 | Embankment (0120-6) | CY | 671.30 | $28.50 | $68.00 | $35.10 | $95.00 |
| 0075 | Type B stabilization (0160-4) | SY | 860 | $36.25 | $40.25 | $10.20 | $30.00 |
| 0080 | Optional base, base group 01 (0285-701) | SY | 619 | $34.25 | $75.00 | $44.00 | $70.00 |
| 0085 | Milling existing asphalt pavement, 2" avg depth (0327-70-5) | SY | 2,633 | $4.25 | $7.60 | $6.35 | $10.00 |
| 0090 | Milling existing asphalt pavement, 1 1/4" avg depth (0327-70-12) | SY | 1,002 | $4.35 | $15.00 | $5.50 | $8.00 |
| 0095 | Asphalt concrete friction course,traffic C, FC-9.5, PG 76-22 (0337-7-82) | TN | 297 | $225.50 | $303.00 | $202.40 | $400.00 |
| 0100 | Performance turf, sod (0570-1-2) | SY | 2,070 | $10.00 | $5.00 | $7.45 | $10.00 |
| 0105 | Raised pavement marker, type B (0706-1-3) | EACH | 79 | $6.00 | $8.90 | $6.10 | $8.00 |
| 0110 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.30 | $3,000.00 | $2,746.00 | $3,000.00 | $2,500.00 |
| 0115 | Painted pavement markings, standard, yellow, solid, 6" (0710-11201) | GM | 0.30 | $3,000.00 | $2,774.00 | $3,030.00 | $2,500.00 |
| 0120 | High friction surface course (0908-333100) | SY | 2,633 | $40.00 | $44.75 | $39.75 | $35.00 |
| 0125 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $41,314 | $41,314 | $41,314 | $41,314 |
| 0130 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 26 | $726.00 | $670.00 | $701.00 | $600.00 |
| 0135 | Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112) | EACH | 1 | $3,875.00 | $3,575.00 | $2,260.00 | $3,200.00 |
| 0140 | Single column ground sign assembly, remove (0700-1600) | EACH | 16 | $91.00 | $84.00 | $61.00 | $75.00 |
| 0145 | Retroreflective sign strip- furnish and install, 2' (0700-13-12) | EACH | 2 | $151.35 | $140.00 | $182.90 | $125.00 |
| 0150 | Retroreflective sign strip- furnish and install, 5' (0700-13-15) | EACH | 1 | $181.50 | $168.00 | $243.90 | $150.00 |
| 0155 | Delineator, flexible tubular (0705-11-1) | EACH | 33 | $133.25 | $140.00 | $134.20 | $125.00 |
| 0160 | Raised pavement marker, type B (0706-1-3) | EACH | 110 | $6.00 | $8.90 | $6.10 | $8.00 |
| 0165 | Painted pavement markings, surface (0710-90) | LS | 1 | $6,700.00 | $8,379.00 | $6,770.00 | $17,500 |
| 0170 | Thermoplastic, standard, solid, 8" for interchange and urban island (0711-11102) | GM | 0.01 | $22,000 | $13,965 | $23,200 | $10,000 |
| 0175 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 30 | $5.20 | $8.90 | $5.25 | $8.00 |
| 0180 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 26 | $7.75 | $11.25 | $7.80 | $10.00 |
| 0185 | Thermoplastic, standard, arrow (0711-11170) | EACH | 2 | $123.00 | $13.50 | $124.40 | $12.00 |
| 0190 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 30 | $26.00 | $33.50 | $26.50 | $30.00 |
| 0195 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 0.29 | $13,650 | $9,723.00 | $13,800 | $8,500.00 |
| 0200 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 0.30 | $13,400 | $9,592.00 | $13,600 | $8,500.00 |
| 0205 | Conduit, furnish & install, open trench (0630-2-11) | LF | 1,071 | $16.35 | $11.00 | $14.65 | $13.50 |
| 0210 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 9 | $2,500.00 | $1,432.00 | $1,620.00 | $2,074.00 |
| 0215 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 3,981 | $3.00 | $2.60 | $2.55 | $2.60 |
| 0220 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 0' arm length (0715-61400) | EACH | 7 | $12,000 | $13,057 | $12,800 | $10,044 |
| 0225 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 10' arm length (0715-61421) | EACH | 1 | $12,500 | $13,057 | $12,800 | $10,279 |
| 0230 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 7 | $1,785.00 | $937.00 | $1,720.00 | $1,474.00 |
| 0235 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 8 | $1,000.00 | $1,235.00 | $1,310.00 | $801.00 |
| 0240 | Fiber optic cable locator (0633-6) | DA | 133 | $260.00 | $23.00 | $42.05 | $216.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.