FDOT contract T4751 bid tabulation
SR 704 (OKEECHOBEE BLVD) FROM E OF SR 809 (MILITARY TR) TO.. Let by Florida DOT on February 25, 2026, Palm Beach, District 4. 4 bids received; low bid $2,346,009 by Ohla USA Inc.
- Owner
- Florida DOT
- Letting
- 25 FEB 2026
- Pay items
- 103
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ohla USA Inc | $2,346,009 | Low |
| 2 | Weekley Asphalt Paving, Inc. | $2,356,839 | 0.0% |
| 3 | The Stout Group LLC | $2,383,298 | +2.0% |
| 4 | J.W. Cheatham, LLC | $2,642,302 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ohla USA Inc | 2. Weekley Asphalt Paving, Inc. | 3. The Stout Group LLC | 4. J.W. Cheatham, LLC |
|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $91,500 | $68,900 | $75,000 | $45,745 |
| 0010 | Mobilization (0101-1) | LS | 1 | $46,000 | $34,500 | $75,000 | $163,935 |
| 0015 | Mobilization (0101-1) | LS | 1 | $91,500 | $34,500 | $75,000 | $176,100 |
| 0020 | Maintenance of traffic (0102-1) | DA | 1 | $91,500 | $133,100 | $115,000 | $49,750 |
| 0025 | Maintenance of traffic (0102-1) | DA | 1 | $45,000 | $66,500 | $115,000 | $47,550 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $91,500 | $66,500 | $115,000 | $47,050 |
| 0035 | Pedestrian escort/flagger (0102-5) | HR | 1,512 | $45.14 | $50.00 | $1.00 | $35.00 |
| 0040 | Traffic control officer (0102-14) | HR | 288 | $91.30 | $90.00 | $1.00 | $100.00 |
| 0045 | Work zone sign (0102-60) | ED | 12,757 | $0.21 | $0.22 | $0.18 | $0.25 |
| 0050 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 24,426 | $0.11 | $0.09 | $0.10 | $0.11 |
| 0055 | Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8) | FD | 7,739 | $0.07 | $0.05 | $0.06 | $0.06 |
| 0060 | Arrow board / advance warning arrow panel (0102-76) | ED | 391 | $5.70 | $5.00 | $5.00 | $5.50 |
| 0065 | Portable changeable message sign, temporary (0102-99) | ED | 910 | $10.14 | $10.00 | $8.90 | $13.00 |
| 0070 | Temporary signalization and maintenance, intersection (0102-104) | ED | 406 | $6.42 | $25.00 | $25.00 | $27.00 |
| 0075 | Temporary traffic detection and maintenance, intersection (0102-107-1) | ED | 406 | $6.42 | $25.00 | $25.00 | $27.00 |
| 0080 | Type III barricade (0102-115) | ED | 1,808 | $0.28 | $0.35 | $0.25 | $0.40 |
| 0085 | Sediment barrier (0104-10-3) | LF | 3,175 | $8.03 | $2.85 | $7.00 | $3.00 |
| 0090 | Inlet protection system (0104-18) | EACH | 33 | $252.25 | $150.00 | $250.00 | $100.00 |
| 0095 | Litter removal (0107-1) | ACRE | 26.63 | $483.48 | $50.00 | $0.01 | $200.00 |
| 0100 | Mowing (0107-2) | ACRE | 21.79 | $350.00 | $50.00 | $0.01 | $500.00 |
| 0105 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $95,000 | $26,000 | $15,000 | $43,750 |
| 0110 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $95,000 | $38,500 | $15,000 | $10,000 |
| 0115 | Removal of existing concrete (0110-4-10) | SY | 297 | $26.28 | $109.50 | $30.00 | $30.00 |
| 0120 | Borrow excavation, truck measure (0120-2-2) | CY | 3.40 | $1,280.76 | $350.00 | $150.00 | $500.00 |
| 0125 | Regular excavation (3-R projects only) (0120-71) | LS | 1 | $3,949.57 | $3,500.00 | $10,000 | $30,000 |
| 0130 | Optional base, base group 13 (0285-713) | SY | 61 | $213.97 | $350.92 | $100.00 | $500.00 |
| 0135 | Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6) | SY | 43,564 | $3.50 | $3.50 | $7.00 | $5.20 |
| 0140 | Superpave asphaltic conc, traffic C (0334-1-13) | TN | 5.10 | $900.00 | $595.00 | $500.00 | $500.00 |
| 0145 | Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83) | TN | 3,599.10 | $155.00 | $210.00 | $190.00 | $237.00 |
| 0150 | Manhole, adjust (0425-5) | EACH | 15 | $1,444.78 | $1,200.00 | $1,000.00 | $1,100.00 |
| 0155 | Valve boxes, adjust (0425-6) | EACH | 13 | $959.43 | $850.00 | $850.00 | $1,000.00 |
| 0160 | Concrete curb & gutter, type F (0520-1-10) | LF | 260 | $94.58 | $125.20 | $50.00 | $50.00 |
| 0165 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 10 | $783.31 | $300.00 | $150.00 | $100.00 |
| 0170 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 233 | $214.07 | $380.00 | $150.00 | $100.00 |
| 0175 | Detectable warnings (0527-2) | SF | 65 | $44.39 | $58.00 | $50.00 | $50.00 |
| 0180 | Performance turf, sod (0570-1-2) | SY | 45 | $104.80 | $18.00 | $50.00 | $20.00 |
| 0185 | Painted pavement markings, standard, white, solid, 6" (0710-11101) | GM | 0.06 | $4,347.26 | $4,000.00 | $7,500.00 | $7,260.00 |
| 0190 | Partnering, DO not bid (0999-16) | LS | 1 | $6,000.00 | $6,000.00 | $6,000.00 | $6,000.00 |
| 0195 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $8,565.00 | $8,565.00 | $8,565.00 | $8,565.00 |
| 0200 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $20,805 | $20,805 | $20,805 | $20,805 |
| 0205 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $20,630 | $20,630 | $20,630 | $20,630 |
| 0210 | Local agency initial amount (DO not bid) (0999-26) | LS | 1 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0215 | Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111) | EACH | 14 | $545.20 | $545.20 | $600.00 | $600.00 |
| 0220 | Single column ground sign assembly, relocate (0700-1500) | EACH | 1 | $345.89 | $345.89 | $500.00 | $380.00 |
| 0225 | Single column ground sign assembly, remove (0700-1600) | EACH | 13 | $54.58 | $54.58 | $35.00 | $61.00 |
| 0230 | Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101) | EACH | 8 | $149.27 | $149.27 | $160.00 | $164.00 |
| 0235 | Sign panel, remove, UP to 12 SF (0700-3601) | EACH | 5 | $27.29 | $27.29 | $35.00 | $31.00 |
| 0240 | Object marker, type 1 (0705-10-1) | EACH | 1 | $142.96 | $142.96 | $350.00 | $308.00 |
| 0245 | Raised pavement marker, type B (0706-1-3) | EACH | 812 | $4.16 | $3.70 | $6.00 | $6.35 |
| 0250 | Painted pavement markings, durable paint, yellow, island nose (0710-12290) | SF | 25 | $7.86 | $7.00 | $8.00 | $4.40 |
| 0255 | Painted pavement markings, surface (0710-90) | LS | 1 | $9,553.62 | $8,507.00 | $11,000 | $29,000 |
| 0260 | Painted pavement markings, surface (0710-90) | LS | 1 | $8,138.60 | $7,247.00 | $9,250.00 | $18,500 |
| 0265 | Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123) | LF | 1,910 | $3.45 | $3.07 | $3.00 | $3.60 |
| 0270 | Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124) | LF | 86 | $5.18 | $4.61 | $4.50 | $4.95 |
| 0275 | Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125) | LF | 568 | $6.90 | $6.14 | $5.00 | $6.60 |
| 0280 | Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141) | GM | 0.77 | $2,517.01 | $2,250.00 | $1,650.00 | $5,650.00 |
| 0285 | Thermoplastic, standard, message or symbol (0711-11160) | EACH | 2 | $113.43 | $101.00 | $450.00 | $275.00 |
| 0290 | Thermoplastic, standard, arrow (0711-11170) | EACH | 84 | $62.89 | $56.00 | $100.00 | $138.00 |
| 0295 | Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224) | LF | 12 | $5.18 | $4.61 | $4.50 | $4.95 |
| 0300 | Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241) | GM | 0.04 | $2,297.05 | $2,250.00 | $1,650.00 | $6,770.00 |
| 0305 | Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125) | LF | 1,572 | $16.88 | $15.03 | $20.00 | $6.60 |
| 0310 | Thermoplastic, preformed, white, message (0711-14160) | EACH | 4 | $218.99 | $195.00 | $300.00 | $275.00 |
| 0315 | Thermoplastic, preformed, white, arrow (0711-14170) | EACH | 4 | $92.09 | $82.00 | $150.00 | $193.00 |
| 0320 | Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101) | GM | 2.69 | $5,436.77 | $4,852.00 | $5,600.00 | $7,260.00 |
| 0325 | Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102) | GM | 0.03 | $7,265.00 | $6,469.00 | $8,000.00 | $10,164 |
| 0330 | Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131) | GM | 2.37 | $1,361.09 | $1,213.00 | $1,750.00 | $3,300.00 |
| 0335 | Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201) | GM | 1.24 | $4,998.41 | $4,458.00 | $5,600.00 | $7,260.00 |
| 0340 | Green-colored pavement markings, bike lane (0714-10) | SF | 543 | $15.41 | $13.72 | $11.00 | $16.50 |
| 0345 | Conduit, furnish & install, open trench (0630-2-11) | LF | 621 | $16.13 | $20.00 | $18.00 | $19.50 |
| 0350 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 14 | $1,519.00 | $1,500.00 | $1,500.00 | $1,620.00 |
| 0355 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 2 | $6,301.77 | $5,363.40 | $6,500.00 | $7,020.00 |
| 0360 | Electrical service wire, & install (0639-2-1) | LF | 60 | $38.30 | $8.50 | $8.50 | $9.20 |
| 0365 | Prestressed concrete pole, type P-II pedestal (0641-2-11) | EACH | 2 | $3,230.88 | $2,100.00 | $2,100.00 | $2,270.00 |
| 0370 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 2,043 | $3.54 | $2.10 | $2.10 | $2.30 |
| 0375 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 1,086 | $0.42 | $1.00 | $1.00 | $1.10 |
| 0380 | Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51) | EACH | 5 | $427.72 | $425.00 | $425.00 | $460.00 |
| 0385 | Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211) | EACH | 34 | $1,455.98 | $1,400.90 | $1,505.00 | $1,625.00 |
| 0390 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 8' arm length (0715-61411) | EACH | 1 | $11,233 | $7,385.50 | $7,147.70 | $7,720.00 |
| 0395 | Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 15' arm length (0715-61452) | EACH | 4 | $11,331 | $7,478.80 | $7,504.00 | $8,100.00 |
| 0400 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 4 | $748.52 | $810.00 | $810.00 | $875.00 |
| 0405 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 38 | $1,154.30 | $618.00 | $674.10 | $730.00 |
| 0410 | Conduit, furnish & install, open trench (0630-2-11) | LF | 33 | $16.13 | $28.00 | $28.00 | $30.00 |
| 0415 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 1,220 | $40.36 | $28.00 | $28.00 | $30.00 |
| 0420 | Signal cable- new or reconstructed intersection, furnish & install (0632-7-1) | PI | 1 | $7,167.02 | $9,500.00 | $9,500.00 | $10,260 |
| 0425 | Signal cable, remove- intersection (0632-7-6) | PI | 1 | $855.45 | $1,200.00 | $1,200.00 | $1,300.00 |
| 0430 | Fiber optic cable locator (0633-6) | DA | 203 | $140.01 | $240.00 | $240.00 | $260.00 |
| 0435 | Pull & splice box, F&I, 24" X 36" cover size (0635-2-12) | EACH | 1 | $2,792.11 | $3,600.00 | $3,600.00 | $3,890.00 |
| 0440 | Pull & splice box, F&I, 17" X 30" cover size (0635-2-14) | EACH | 17 | $1,679.39 | $1,750.00 | $1,750.00 | $1,890.00 |
| 0445 | Pull & splice box, install (0635-2-30) | EACH | 1 | $885.41 | $600.00 | $600.00 | $650.00 |
| 0450 | Electrical power service, F&I, underground, meter by contractor (0639-1122) | AS | 1 | $4,953.49 | $3,200.00 | $3,200.00 | $3,456.00 |
| 0455 | Electrical service wire, & install (0639-2-1) | LF | 149 | $10.63 | $8.50 | $8.50 | $9.00 |
| 0460 | Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60) | EACH | 1 | $3,230.69 | $250.00 | $250.00 | $270.00 |
| 0465 | Prestressed concrete pole, type P-II service pole (0641-2-12) | EACH | 1 | $3,305.59 | $2,400.00 | $2,400.00 | $2,600.00 |
| 0470 | Aluminum signals pole, (0646-1-11) | EACH | 7 | $2,342.68 | $1,900.00 | $1,900.00 | $2,052.00 |
| 0475 | Aluminum signals pole, remove (0646-1-60) | EACH | 2 | $641.59 | $250.00 | $250.00 | $270.00 |
| 0480 | Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109) | EACH | 23 | $802.25 | $750.00 | $600.00 | $650.00 |
| 0485 | Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11) | AS | 6 | $1,079.40 | $850.00 | $850.00 | $920.00 |
| 0490 | Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12) | AS | 1 | $1,977.88 | $1,150.00 | $1,150.00 | $1,250.00 |
| 0495 | Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60) | AS | 2 | $213.87 | $250.00 | $250.00 | $270.00 |
| 0500 | Loop detector inductive, F&I, type 10 (0660-1110) | EACH | 16 | $580.79 | $400.00 | $400.00 | $432.00 |
| 0505 | Loop assembly, F&I, type F (0660-2106) | AS | 46 | $1,878.28 | $2,150.00 | $1,850.00 | $2,000.00 |
| 0510 | Pedestrian detector, furnish & install, standard (0665-1-11) | EACH | 8 | $450.59 | $270.00 | $270.00 | $292.00 |
| 0515 | Pedestrian detector, remove- pole/pedestal to remain (0665-1-60) | EACH | 4 | $106.93 | $50.00 | $50.00 | $54.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.