FDOT contract T4751 bid tabulation

SR 704 (OKEECHOBEE BLVD) FROM E OF SR 809 (MILITARY TR) TO.. Let by Florida DOT on February 25, 2026, Palm Beach, District 4. 4 bids received; low bid $2,346,009 by Ohla USA Inc.

Owner
Florida DOT
Letting
25 FEB 2026
Pay items
103
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ohla USA Inc$2,346,009Low
2Weekley Asphalt Paving, Inc.$2,356,8390.0%
3The Stout Group LLC$2,383,298+2.0%
4J.W. Cheatham, LLC$2,642,302+13%
FDOT contract T4751: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ohla USA Inc2. Weekley Asphalt Paving, Inc.3. The Stout Group LLC4. J.W. Cheatham, LLC
0005Mobilization (0101-1)LS1$91,500$68,900$75,000$45,745
0010Mobilization (0101-1)LS1$46,000$34,500$75,000$163,935
0015Mobilization (0101-1)LS1$91,500$34,500$75,000$176,100
0020Maintenance of traffic (0102-1)DA1$91,500$133,100$115,000$49,750
0025Maintenance of traffic (0102-1)DA1$45,000$66,500$115,000$47,550
0030Maintenance of traffic (0102-1)DA1$91,500$66,500$115,000$47,050
0035Pedestrian escort/flagger (0102-5)HR1,512$45.14$50.00$1.00$35.00
0040Traffic control officer (0102-14)HR288$91.30$90.00$1.00$100.00
0045Work zone sign (0102-60)ED12,757$0.21$0.22$0.18$0.25
0050Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED24,426$0.11$0.09$0.10$0.11
0055Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD7,739$0.07$0.05$0.06$0.06
0060Arrow board / advance warning arrow panel (0102-76)ED391$5.70$5.00$5.00$5.50
0065Portable changeable message sign, temporary (0102-99)ED910$10.14$10.00$8.90$13.00
0070Temporary signalization and maintenance, intersection (0102-104)ED406$6.42$25.00$25.00$27.00
0075Temporary traffic detection and maintenance, intersection (0102-107-1)ED406$6.42$25.00$25.00$27.00
0080Type III barricade (0102-115)ED1,808$0.28$0.35$0.25$0.40
0085Sediment barrier (0104-10-3)LF3,175$8.03$2.85$7.00$3.00
0090Inlet protection system (0104-18)EACH33$252.25$150.00$250.00$100.00
0095Litter removal (0107-1)ACRE26.63$483.48$50.00$0.01$200.00
0100Mowing (0107-2)ACRE21.79$350.00$50.00$0.01$500.00
0105Clearing & grubbing (0110-1-1)ACRE1$95,000$26,000$15,000$43,750
0110Clearing & grubbing (0110-1-1)ACRE1$95,000$38,500$15,000$10,000
0115Removal of existing concrete (0110-4-10)SY297$26.28$109.50$30.00$30.00
0120Borrow excavation, truck measure (0120-2-2)CY3.40$1,280.76$350.00$150.00$500.00
0125Regular excavation (3-R projects only) (0120-71)LS1$3,949.57$3,500.00$10,000$30,000
0130Optional base, base group 13 (0285-713)SY61$213.97$350.92$100.00$500.00
0135Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY43,564$3.50$3.50$7.00$5.20
0140Superpave asphaltic conc, traffic C (0334-1-13)TN5.10$900.00$595.00$500.00$500.00
0145Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN3,599.10$155.00$210.00$190.00$237.00
0150Manhole, adjust (0425-5)EACH15$1,444.78$1,200.00$1,000.00$1,100.00
0155Valve boxes, adjust (0425-6)EACH13$959.43$850.00$850.00$1,000.00
0160Concrete curb & gutter, type F (0520-1-10)LF260$94.58$125.20$50.00$50.00
0165Concrete sidewalk and driveways, 4" thick (0522-1)SY10$783.31$300.00$150.00$100.00
0170Concrete sidewalk and driveways, 6" thick (0522-2)SY233$214.07$380.00$150.00$100.00
0175Detectable warnings (0527-2)SF65$44.39$58.00$50.00$50.00
0180Performance turf, sod (0570-1-2)SY45$104.80$18.00$50.00$20.00
0185Painted pavement markings, standard, white, solid, 6" (0710-11101)GM0.06$4,347.26$4,000.00$7,500.00$7,260.00
0190Partnering, DO not bid (0999-16)LS1$6,000.00$6,000.00$6,000.00$6,000.00
0195Initial contingency amount, DO not bid (0999-25)LS1$8,565.00$8,565.00$8,565.00$8,565.00
0200Initial contingency amount, DO not bid (0999-25)LS1$20,805$20,805$20,805$20,805
0205Initial contingency amount, DO not bid (0999-25)LS1$20,630$20,630$20,630$20,630
0210Local agency initial amount (DO not bid) (0999-26)LS1$600.00$600.00$600.00$600.00
0215Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH14$545.20$545.20$600.00$600.00
0220Single column ground sign assembly, relocate (0700-1500)EACH1$345.89$345.89$500.00$380.00
0225Single column ground sign assembly, remove (0700-1600)EACH13$54.58$54.58$35.00$61.00
0230Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH8$149.27$149.27$160.00$164.00
0235Sign panel, remove, UP to 12 SF (0700-3601)EACH5$27.29$27.29$35.00$31.00
0240Object marker, type 1 (0705-10-1)EACH1$142.96$142.96$350.00$308.00
0245Raised pavement marker, type B (0706-1-3)EACH812$4.16$3.70$6.00$6.35
0250Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF25$7.86$7.00$8.00$4.40
0255Painted pavement markings, surface (0710-90)LS1$9,553.62$8,507.00$11,000$29,000
0260Painted pavement markings, surface (0710-90)LS1$8,138.60$7,247.00$9,250.00$18,500
0265Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF1,910$3.45$3.07$3.00$3.60
0270Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF86$5.18$4.61$4.50$4.95
0275Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF568$6.90$6.14$5.00$6.60
0280Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.77$2,517.01$2,250.00$1,650.00$5,650.00
0285Thermoplastic, standard, message or symbol (0711-11160)EACH2$113.43$101.00$450.00$275.00
0290Thermoplastic, standard, arrow (0711-11170)EACH84$62.89$56.00$100.00$138.00
0295Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF12$5.18$4.61$4.50$4.95
0300Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.04$2,297.05$2,250.00$1,650.00$6,770.00
0305Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF1,572$16.88$15.03$20.00$6.60
0310Thermoplastic, preformed, white, message (0711-14160)EACH4$218.99$195.00$300.00$275.00
0315Thermoplastic, preformed, white, arrow (0711-14170)EACH4$92.09$82.00$150.00$193.00
0320Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM2.69$5,436.77$4,852.00$5,600.00$7,260.00
0325Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.03$7,265.00$6,469.00$8,000.00$10,164
0330Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM2.37$1,361.09$1,213.00$1,750.00$3,300.00
0335Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM1.24$4,998.41$4,458.00$5,600.00$7,260.00
0340Green-colored pavement markings, bike lane (0714-10)SF543$15.41$13.72$11.00$16.50
0345Conduit, furnish & install, open trench (0630-2-11)LF621$16.13$20.00$18.00$19.50
0350Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH14$1,519.00$1,500.00$1,500.00$1,620.00
0355Electrical power service, F&I, underground, meter by contractor (0639-1122)AS2$6,301.77$5,363.40$6,500.00$7,020.00
0360Electrical service wire, & install (0639-2-1)LF60$38.30$8.50$8.50$9.20
0365Prestressed concrete pole, type P-II pedestal (0641-2-11)EACH2$3,230.88$2,100.00$2,100.00$2,270.00
0370Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF2,043$3.54$2.10$2.10$2.30
0375Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF1,086$0.42$1.00$1.00$1.10
0380Luminaire & bracket arm, luminaire and arm; pole remains (0715-5-51)EACH5$427.72$425.00$425.00$460.00
0385Luminaire, F&I- replace existing luminaire on existing pole/arm, roadway, cobra head (0715-11211)EACH34$1,455.98$1,400.90$1,505.00$1,625.00
0390Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 8' arm length (0715-61411)EACH1$11,233$7,385.50$7,147.70$7,720.00
0395Light pole complete, F&I, standard pole standard foundation, 45' mounting height, 15' arm length (0715-61452)EACH4$11,331$7,478.80$7,504.00$8,100.00
0400Light pole complete, remove pole and foundation (0715-69000)EACH4$748.52$810.00$810.00$875.00
0405Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH38$1,154.30$618.00$674.10$730.00
0410Conduit, furnish & install, open trench (0630-2-11)LF33$16.13$28.00$28.00$30.00
0415Conduit, furnish & install, directional bore (0630-2-12)LF1,220$40.36$28.00$28.00$30.00
0420Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$7,167.02$9,500.00$9,500.00$10,260
0425Signal cable, remove- intersection (0632-7-6)PI1$855.45$1,200.00$1,200.00$1,300.00
0430Fiber optic cable locator (0633-6)DA203$140.01$240.00$240.00$260.00
0435Pull & splice box, F&I, 24" X 36" cover size (0635-2-12)EACH1$2,792.11$3,600.00$3,600.00$3,890.00
0440Pull & splice box, F&I, 17" X 30" cover size (0635-2-14)EACH17$1,679.39$1,750.00$1,750.00$1,890.00
0445Pull & splice box, install (0635-2-30)EACH1$885.41$600.00$600.00$650.00
0450Electrical power service, F&I, underground, meter by contractor (0639-1122)AS1$4,953.49$3,200.00$3,200.00$3,456.00
0455Electrical service wire, & install (0639-2-1)LF149$10.63$8.50$8.50$9.00
0460Electrical service disconnect, remove- pole or cabinet to remain (0639-3-60)EACH1$3,230.69$250.00$250.00$270.00
0465Prestressed concrete pole, type P-II service pole (0641-2-12)EACH1$3,305.59$2,400.00$2,400.00$2,600.00
0470Aluminum signals pole, (0646-1-11)EACH7$2,342.68$1,900.00$1,900.00$2,052.00
0475Aluminum signals pole, remove (0646-1-60)EACH2$641.59$250.00$250.00$270.00
0480Vehicular signal auxiliaries, repair/replace/retrofit- & install, backplate- flexible required (0650-2109)EACH23$802.25$750.00$600.00$650.00
0485Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS6$1,079.40$850.00$850.00$920.00
0490Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS1$1,977.88$1,150.00$1,150.00$1,250.00
0495Pedestrian signal, remove ped signal- pole/pedestal to remain (0653-1-60)AS2$213.87$250.00$250.00$270.00
0500Loop detector inductive, F&I, type 10 (0660-1110)EACH16$580.79$400.00$400.00$432.00
0505Loop assembly, F&I, type F (0660-2106)AS46$1,878.28$2,150.00$1,850.00$2,000.00
0510Pedestrian detector, furnish & install, standard (0665-1-11)EACH8$450.59$270.00$270.00$292.00
0515Pedestrian detector, remove- pole/pedestal to remain (0665-1-60)EACH4$106.93$50.00$50.00$54.00
FDOT contract T4751: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of February 25, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy