Depew and Owen Builders, Inc.: IDOT bid record
Depew and Owen Builders, Inc. submitted 21 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 23 SEP 2022, and was the low bidder on 13 of them (62%). When it was not low, its total sat a median +6.0% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $6,177,744
- Latest bid
- 23 SEP 2022
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 11 | 5 | 45% |
| 2022 | 10 | 8 | 80% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 07 | 15 | 8 | 53% |
| District 08 | 3 | 3 | 100% |
| District 06 | 2 | 1 | 50% |
| District 05 | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Terminal marker - DA | 72501000 | EACH | 15 | 13 (87%) | $40.00 | $47.85 |
| Rem exist struct | 50100100 | EACH | 15 | 11 (73%) | $10,000 | $50,000 |
| Name plates | 51500100 | EACH | 16 | 10 (63%) | $412.90 | $773.24 |
| Earth excavation | 20200100 | CY | 15 | 8 (53%) | $15.00 | $48.00 |
| Contr low-streng matl | 59300100 | CY | 8 | 8 (100%) | $97.50 | $260.00 |
| Reinf bars, epoxy CTD | 50800205 | LB | 15 | 7 (47%) | $2.00 | $2.50 |
| Conc struct | 50300225 | CY | 17 | 6 (35%) | $700.00 | $1,260.00 |
| Channel excavation | 20300100 | CY | 16 | 6 (38%) | $17.00 | $35.00 |
| Seeding CL 2 SPL | X2501000 | ACRE | 10 | 6 (60%) | $5,025.00 | $9,000.00 |
| Driving piles | 51202305 | LF | 15 | 5 (33%) | $1.00 | $0.10 |
| Steel railing TY S1 | 50900205 | LF | 11 | 5 (45%) | $145.00 | $171.15 |
| Concrete encasement | 50300280 | CY | 9 | 4 (44%) | $700.00 | $1,200.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Samron Midwest Contracting, Inc. | 6 | 3 of 6 |
| Lake Contracting, Inc. | 6 | 1 of 6 |
| County Contractors, Inc. | 5 | 0 of 5 |
| Plocher Construction Company, Inc. | 4 | 2 of 4 |
| Sangamo Construction Company | 4 | 1 of 4 |
| Howell Paving, Inc. | 3 | 2 of 3 |
| White Construction LLC | 3 | 1 of 3 |
| Kieffer Bros. Construction Co., Inc. | 2 | 0 of 2 |
| Keller Construction, Inc. | 2 | 0 of 2 |
| Yamnitz, William d/b/a Yamnitz & Associates | 2 | 1 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 23 SEP 2022 | 91597 | District 05 | Project Number: J9Jx-577 / /, section 07-08119-01-BR | 1 of 3 | $1,158,188 | Low, 43% under the second |
| 17 JUN 2022 | 76P78 | District 08 | Section 17BR-1 | 1 of 2 | $420,588 | Low, 1.0% under the second |
| 17 JUN 2022 | 93789 | District 06 | Project Number: 9Exr-862 / /, section 19-07116-00-BR | 2 of 3 | $805,488 | +5.0% |
| 17 JUN 2022 | 95914 | District 07 | Project Number: 6Hil-452 / /, section 18-20122-00-BR | 1 of 1 | $392,688 | Low |
| 17 JUN 2022 | 95916 | District 07 | Project Number: 8Gm5-575 / /, section 19-07132-00-BR | 1 of 1 | $299,988 | Low |
| 29 APR 2022 | 93781 | District 06 | Project Number: 5Fm7-562 / /, section 19-11115-00-BR | 1 of 3 | $399,988 | Low, 7.0% under the second |
| 11 MAR 2022 | 95907 | District 07 | Project Number: 7Crw-135 / /, section 18-00287-00-BR | 1 of 3 | $939,488 | Low, 11% under the second |
| 11 MAR 2022 | 95910 | District 07 | Project Number: Eswg-850 / /, section 17-00098-00-BR | 2 of 2 | $969,888 | +6.0% |
| 21 JAN 2022 | 95898 | District 07 | Project Number: Bq7G-886 / /, section 04-12114-00-BR | 1 of 4 | $238,588 | Low, 14% under the second |
| 21 JAN 2022 | 95906 | District 07 | Project Number: Gjzp-832 / /, section 18-08137-00-BR | 1 of 2 | $520,888 | Low, 11% under the second |
| 05 NOV 2021 | 74995 | District 07 | Section D7 | 5 of 5 | $588,888 | +21% |
| 11 JUN 2021 | 95894 | District 07 | Project Number: J0J7-421 / /, section 19-00124-00-BR | 1 of 3 | $418,488 | Low, 9.0% under the second |
| 11 JUN 2021 | 95896 | District 07 | Project Number: L3Z9-012 / /, section 17-18119-00-BR | 1 of 4 | $296,588 | Low, 17% under the second |
| 23 APR 2021 | 95895 | District 07 | Project Number: 6G85-256 / /, section 18-06117-00-BR | 1 of 2 | $318,888 | Low, 4.0% under the second |
| 05 MAR 2021 | 74946 | District 07 | Section D7 | 3 of 6 | $374,788 | +15% |
| 05 MAR 2021 | 95888 | District 07 | Project Number: 1Kij-037 / /, section 17-20129-00-BR | 2 of 4 | $366,788 | +1.0% |
| 05 MAR 2021 | 97749 | District 08 | Project Number: 2Muy-482 / /, section 15-09034-00-BR | 1 of 3 | $236,788 | Low, 5.0% under the second |
| 15 JAN 2021 | 95884 | District 07 | Project Number: Mwp9-383 / /, section 17-00170-00-BR | 2 of 3 | $689,888 | +3.0% |
| 15 JAN 2021 | 95886 | District 07 | Project Number: Vfl2-092 / /, section 18-00122-00-BR | 2 of 3 | $571,488 | +6.0% |
| 15 JAN 2021 | 95887 | District 07 | Project Number: Gqgz-590 / /, section 18-09115-00-BR | 2 of 3 | $396,828 | +8.0% |
| 15 JAN 2021 | 97746 | District 08 | Project Number: Lr8W-861 / /, section 16-00102-00-BR | 1 of 4 | $536,588 | Low, 4.0% under the second |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.