INDOT contract R-41054-A bid tabulation
INTERSECTION IMPROVEMENT, ROUNDABOUT. Let by Indiana DOT on February 12, 2025, Hamilton, Greenfield. 8 bids received; low bid $1,983,670 by Midwest Paving LLC.
- Owner
- Indiana DOT
- Letting
- 12 FEB 2025
- Pay items
- 119
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Midwest Paving LLC | $1,983,670 | Low |
| 2 | Calumet Civil Contractors Inc | $2,029,000 | +2.0% |
| 3 | E & B Paving LLC | $2,227,296 | +12% |
| 4 | Morphey Construction Inc. | $2,234,000 | +13% |
| 5 | Gradex Inc | $2,244,930 | +13% |
| 6 | Rieth-Riley Construction Co., Inc. | $2,272,476 | +15% |
| 7 | His Constructors Inc | $2,350,865 | +19% |
| 8 | Bunn Excavating Inc | $2,621,634 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Midwest Paving LLC | 2. Calumet Civil Contractors Inc | 3. E & B Paving LLC | 4. Morphey Construction Inc. | 5. Gradex Inc | 6. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $19,600 | $25,000 | $33,361 | $20,000 | $187,364 | $21,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $50,471 | $99,069 | $188,679 | $111,700 | $112,247 | $92,837 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $1,000.00 | $23,000 | $7,863.92 | $44,680 | $44,899 | $10,146 |
| 0012 | Excavation, common (203-02000) | CYS | 4,751 | $38.00 | $20.00 | $45.00 | $20.00 | $28.08 | $38.00 |
| 0013 | Borrow (203-02070) | CYS | 3,825 | $24.00 | $1.00 | $2.00 | $20.00 | $8.20 | $24.00 |
| 0014 | Linear grading (203-08607) | LFT | 600 | $6.00 | $9.00 | $7.80 | $25.00 | $8.71 | $6.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 38,985 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $15,398 | $23,000 | $59,160 | $800.00 | $38,067 | $29,007 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $2,700.00 | $2,500.00 | $3,500.00 | $1,900.00 | $1,900.00 | $3,500.00 |
| 0018 | Subgrade treatment, type III (207-08266) | SYS | 1,480 | $10.00 | $5.00 | $5.00 | $10.00 | $0.72 | $10.00 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 745 | $52.00 | $30.50 | $46.52 | $50.00 | $24.21 | $52.00 |
| 0020 | Subgrade treatment, type ibc (207-12635) | SYS | 9,380 | $9.95 | $12.00 | $10.00 | $13.00 | $11.28 | $11.32 |
| 0021 | Structure backfill, type 1 (211-09264) | CYS | 312 | $71.00 | $67.00 | $85.78 | $100.00 | $39.82 | $71.00 |
| 0022 | Geogrid, type IB (214-11796) | SYS | 136 | $4.00 | $2.30 | $9.64 | $3.00 | $3.07 | $4.00 |
| 0023 | Drying soils for embankment (217-11917) | TON | 292 | $222.10 | $255.00 | $222.10 | $240.00 | $222.10 | $222.10 |
| 0024 | Compacted aggregate, no. 5 (301-12232) | CYS | 58 | $68.00 | $134.00 | $117.66 | $190.00 | $80.30 | $68.00 |
| 0025 | Compacted aggregate, no. 53 (301-12234) | CYS | 1,379 | $75.00 | $80.00 | $82.62 | $100.00 | $54.83 | $78.05 |
| 0026 | Compacted aggregate, no. 53 (303-01180) | TON | 220 | $50.00 | $52.00 | $57.56 | $75.00 | $36.32 | $86.85 |
| 0027 | Widening with HMA, type B (304-07493) | TON | 35 | $300.00 | $155.00 | $415.00 | $300.00 | $415.00 | $350.25 |
| 0028 | Milling, transition (306-08043) | SYS | 366 | $10.00 | $13.50 | $15.00 | $20.00 | $8.88 | $11.77 |
| 0029 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 931 | $100.00 | $115.00 | $105.00 | $105.00 | $105.00 | $131.71 |
| 0030 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 1,118 | $84.00 | $95.00 | $86.00 | $86.00 | $86.00 | $113.65 |
| 0031 | QC/QA-HMA, 3, 58S, base, 19.0 MM (401-000053) | TON | 2,539 | $90.00 | $86.00 | $80.00 | $80.00 | $80.00 | $106.38 |
| 0032 | Joint adhesive, surface (401-10258) | LFT | 5,372 | $0.50 | $0.45 | $0.33 | $0.33 | $0.33 | $1.08 |
| 0033 | Joint adhesive, intermediate (401-10259) | LFT | 5,149 | $0.50 | $0.45 | $0.33 | $0.33 | $0.33 | $1.20 |
| 0034 | Liquid asphalt sealant (401-11785) | LFT | 5,372 | $0.05 | $0.35 | $0.01 | $0.01 | $0.01 | $0.01 |
| 0035 | Asphalt for tack coat (406-05520) | TON | 8 | $1.00 | $1.00 | $0.01 | $0.01 | $0.01 | $0.01 |
| 0036 | PCCP, 7 in. (502-11564) | SYS | 591 | $108.00 | $115.00 | $110.00 | $125.00 | $110.00 | $107.53 |
| 0037 | D-1 contraction joint (503-05240) | LFT | 240 | $10.00 | $17.00 | $35.00 | $35.00 | $35.00 | $34.41 |
| 0038 | HMA for sidewalk (604-05528) | TON | 166 | $140.00 | $120.00 | $144.00 | $144.00 | $144.00 | $165.07 |
| 0039 | Sidewalk, concrete (604-06070) | SYS | 65 | $65.00 | $77.00 | $73.23 | $104.00 | $73.23 | $127.48 |
| 0040 | Curb ramp, concrete (604-08086) | SYS | 111 | $120.00 | $155.00 | $166.00 | $250.00 | $166.00 | $217.64 |
| 0041 | Detectable warning surfaces (604-12083) | SYS | 30 | $360.00 | $400.00 | $262.00 | $262.00 | $262.00 | $350.92 |
| 0042 | Curb, concrete (605-06120) | LFT | 1,372 | $35.00 | $19.00 | $31.00 | $40.00 | $31.00 | $37.42 |
| 0043 | Curb and gutter, concrete (605-06140) | LFT | 1,824 | $30.00 | $21.00 | $33.00 | $35.00 | $33.00 | $37.13 |
| 0044 | Curb and gutter, rolled curb (605-97937) | LFT | 315 | $25.00 | $48.00 | $21.00 | $42.00 | $21.00 | $55.53 |
| 0045 | Monument, type B (615-06505) | EACH | 8 | $1,125.00 | $1,125.00 | $950.00 | $950.00 | $1,125.00 | $950.00 |
| 0046 | Monument, section corner (615-06527) | EACH | 1 | $800.00 | $800.00 | $1,625.00 | $1,625.00 | $800.00 | $1,625.00 |
| 0047 | Riprap, revetment (616-06405) | TON | 157 | $79.00 | $75.00 | $94.27 | $150.00 | $60.40 | $79.00 |
| 0048 | Geotextile for riprap, type 1A (616-12246) | SYS | 311 | $2.00 | $4.00 | $7.07 | $3.00 | $2.80 | $2.00 |
| 0049 | Geotextile for riprap, type 2A (616-12248) | SYS | 488 | $2.00 | $4.00 | $4.81 | $4.00 | $3.28 | $2.00 |
| 0050 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $350.00 | $250.00 | $350.00 | $350.00 | $250.00 | $350.00 |
| 0051 | Fertilizer for permanent seeding (621-06545) | TON | 1 | $775.00 | $800.00 | $775.00 | $775.00 | $800.00 | $775.00 |
| 0052 | Seed mixture, type U (621-06554) | LBS | 39 | $15.40 | $60.00 | $15.40 | $20.00 | $60.00 | $15.40 |
| 0053 | Mulching material (621-06565) | TON | 1 | $890.00 | $510.00 | $890.00 | $890.00 | $510.00 | $890.00 |
| 0054 | Water (621-06567) | KGAL | 20 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0055 | Topsoil (621-06570) | CYS | 794 | $40.00 | $83.28 | $77.03 | $20.00 | $63.55 | $50.00 |
| 0056 | Sodding (621-06574) | SYS | 80 | $3.78 | $5.27 | $3.78 | $20.00 | $4.60 | $3.78 |
| 0057 | Sodding, nursery (621-06575) | SYS | 4,764 | $3.78 | $8.63 | $3.78 | $10.00 | $8.11 | $3.78 |
| 0058 | Field office, type C (628-09403) | MOS | 12 | $4,500.00 | $3,200.00 | $3,222.00 | $2,000.00 | $3,000.00 | $4,579.57 |
| 0059 | Computer system equipment (628-11976) | EACH | 1 | $540.00 | $1,500.00 | $540.00 | $800.00 | $2,500.00 | $1,205.15 |
| 0060 | Field drilled hole in concrete (702-51863) | EACH | 5 | $500.00 | $20.20 | $8.82 | $100.00 | $300.00 | $30.00 |
| 0061 | Temporary pipe (713-04509) | LS | 1 | $5,063.00 | $1,000.00 | $2,671.74 | $1,500.00 | $4,833.60 | $5,063.00 |
| 0062 | Safety metal end section, 4:1, diameter 15 in. (715-03475) | EACH | 1 | $929.00 | $650.00 | $1,325.33 | $1,800.00 | $1,468.08 | $929.00 |
| 0063 | Safety metal end section, 4:1, diameter 12 in. (715-04611) | EACH | 2 | $1,024.00 | $650.00 | $1,310.25 | $1,800.00 | $1,314.13 | $1,024.00 |
| 0064 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 2,138 | $8.00 | $8.90 | $9.08 | $9.00 | $8.90 | $8.00 |
| 0065 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 417 | $8.00 | $35.00 | $35.70 | $35.00 | $35.00 | $8.00 |
| 0066 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 316 | $62.00 | $61.00 | $65.97 | $74.00 | $35.54 | $62.00 |
| 0067 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 177 | $63.00 | $73.00 | $80.54 | $84.00 | $42.12 | $63.00 |
| 0068 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 178 | $99.00 | $102.00 | $102.12 | $145.00 | $62.90 | $99.00 |
| 0069 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 160 | $54.00 | $73.00 | $55.63 | $56.00 | $35.53 | $54.00 |
| 0070 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 50 | $70.00 | $82.00 | $77.79 | $111.00 | $42.13 | $70.00 |
| 0071 | Video inspection for pipe (715-09064) | LFT | 698 | $3.60 | $3.60 | $3.50 | $4.00 | $1.31 | $3.60 |
| 0072 | Pipe end section, diameter 12 in. (715-46000) | EACH | 4 | $760.00 | $1,400.00 | $1,278.29 | $750.00 | $1,406.82 | $760.00 |
| 0073 | Pipe end section, diameter 15 in. (715-46005) | EACH | 2 | $816.00 | $1,500.00 | $1,334.04 | $880.00 | $1,470.54 | $816.00 |
| 0074 | Pipe end section, diameter 24 in. (715-46020) | EACH | 1 | $1,069.00 | $1,500.00 | $1,769.92 | $2,000.00 | $2,087.43 | $1,069.00 |
| 0075 | Geotextile for underdrains, type 1A (718-12305) | SYS | 2,189 | $0.50 | $2.95 | $3.01 | $3.00 | $2.95 | $1.00 |
| 0076 | Aggregate for underdrains (718-52610) | CYS | 190 | $75.00 | $69.75 | $71.15 | $70.00 | $69.75 | $75.00 |
| 0077 | Manhole, type J10 (720-02367) | EACH | 2 | $4,465.00 | $6,300.00 | $5,620.43 | $5,000.00 | $3,935.49 | $4,465.00 |
| 0078 | Manhole, type J7, modified (720-08239) | EACH | 1 | $3,300.00 | $5,800.00 | $5,210.96 | $5,000.00 | $7,046.04 | $3,300.00 |
| 0079 | Casting, manhole, adjust to grade (720-12798) | EACH | 4 | $350.00 | $600.00 | $1,325.21 | $900.00 | $755.27 | $350.00 |
| 0080 | Inlet, type J10 (720-45045) | EACH | 2 | $2,400.00 | $3,700.00 | $3,918.23 | $3,700.00 | $2,009.57 | $2,400.00 |
| 0081 | Catch basin, type J10 (720-45240) | EACH | 7 | $3,020.00 | $4,000.00 | $5,516.63 | $4,000.00 | $2,009.56 | $3,020.00 |
| 0082 | Manhole, type C4 (720-45410) | EACH | 3 | $2,500.00 | $5,700.00 | $4,802.62 | $4,600.00 | $2,931.33 | $2,500.00 |
| 0083 | Manhole, type C7 (720-94432) | EACH | 2 | $2,400.00 | $5,600.00 | $4,863.47 | $4,500.00 | $2,931.02 | $2,400.00 |
| 0084 | Road closure sign assembly (801-04308) | EACH | 8 | $196.00 | $400.00 | $196.00 | $196.00 | $500.00 | $196.00 |
| 0085 | Detour route marker assembly (801-06625) | EACH | 32 | $140.00 | $125.00 | $140.00 | $140.00 | $250.00 | $140.00 |
| 0086 | Construction sign, type A (801-06640) | EACH | 8 | $180.00 | $175.00 | $180.00 | $180.00 | $500.00 | $180.00 |
| 0087 | Construction sign, type B (801-06645) | EACH | 2 | $58.00 | $120.00 | $58.00 | $58.00 | $200.00 | $58.00 |
| 0088 | Maintaining traffic (801-06775) | LS | 1 | $3,690.00 | $35,000 | $9,425.90 | $48,061 | $89,797 | $13,837 |
| 0089 | Barricade, type III-A (801-07118) | LFT | 12 | $10.00 | $20.00 | $10.00 | $10.00 | $20.00 | $10.00 |
| 0090 | Barricade, type III-B (801-07119) | LFT | 156 | $11.00 | $20.00 | $11.00 | $11.00 | $20.00 | $11.00 |
| 0091 | Temporary accessible pedestrian path (801-12641) | SYS | 62 | $144.00 | $20.00 | $100.00 | $100.00 | $96.83 | $50.99 |
| 0092 | Temporary pedestrian channelizer (801-12862) | LFT | 562 | $19.93 | $10.00 | $25.00 | $20.00 | $45.00 | $28.23 |
| 0093 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 461 | $32.00 | $32.00 | $32.00 | $22.00 | $32.00 | $54.00 |
| 0094 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 56 | $30.00 | $30.00 | $30.00 | $36.00 | $30.00 | $66.00 |
| 0095 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 276 | $31.00 | $31.00 | $31.00 | $21.00 | $31.00 | $52.00 |
| 0096 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 33 | $32.00 | $32.00 | $32.00 | $40.00 | $32.00 | $72.00 |
| 0097 | Handhole, lighting (807-02191) | EACH | 3 | $1,500.00 | $1,500.00 | $1,500.00 | $3,000.00 | $1,500.00 | $1,500.00 |
| 0098 | Light pole, ornamental (807-03951) | EACH | 10 | $12,500 | $12,500 | $12,500 | $12,500 | $12,500 | $12,500 |
| 0099 | Conduit, steel, galvanized, 2 in. (807-06592) | LFT | 229 | $35.00 | $35.00 | $35.00 | $50.00 | $35.00 | $35.00 |
| 0100 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 999 | $22.00 | $22.00 | $22.00 | $45.00 | $22.00 | $22.00 |
| 0101 | Cable, pole circuit, XHHW, no. 6 copper, stranded, 2 1/C (807-11593) | LFT | 480 | $16.50 | $16.50 | $16.50 | $12.00 | $16.50 | $16.50 |
| 0102 | Service point, type I (807-86805) | EACH | 1 | $10,000 | $10,000 | $10,000 | $11,000 | $10,000 | $10,000 |
| 0103 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 1,140 | $1.50 | $1.50 | $1.50 | $3.00 | $1.50 | $1.50 |
| 0104 | Connector kit, unfused (807-86910) | EACH | 10 | $50.00 | $50.00 | $50.00 | $75.00 | $50.00 | $50.00 |
| 0105 | Connector kit, fused (807-86915) | EACH | 10 | $50.00 | $50.00 | $50.00 | $75.00 | $50.00 | $50.00 |
| 0106 | Multiple compression fitting, non- waterproofed (807-86920) | EACH | 24 | $32.00 | $32.00 | $32.00 | $20.00 | $32.00 | $32.00 |
| 0107 | Multiple compression fitting, waterproofed (807-86925) | EACH | 4 | $55.00 | $55.00 | $55.00 | $25.00 | $55.00 | $55.00 |
| 0108 | Insulation link, non- waterproofed (807-86930) | EACH | 24 | $32.00 | $32.00 | $32.00 | $20.00 | $32.00 | $32.00 |
| 0109 | Insulation link, waterproofed (807-86935) | EACH | 12 | $55.00 | $55.00 | $55.00 | $25.00 | $55.00 | $55.00 |
| 0110 | Wire, no. 4 copper, in plastic duct, 4 1/C (807-97237) | LFT | 229 | $22.00 | $22.00 | $22.00 | $45.00 | $22.00 | $22.00 |
| 0111 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 470 | $7.79 | $9.00 | $7.79 | $7.79 | $15.00 | $7.79 |
| 0112 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 901 | $0.84 | $1.25 | $0.84 | $0.84 | $2.00 | $0.84 |
| 0113 | Line, thermoplastic, solid, white, 8 in. (808-06705) | LFT | 750 | $1.65 | $6.25 | $1.65 | $1.65 | $4.00 | $1.65 |
| 0114 | Line, thermoplastic, dotted, white, 12 in. (808-11691) | LFT | 73 | $8.86 | $7.50 | $8.86 | $8.86 | $10.00 | $8.86 |
| 0115 | Transverse marking, thermoplastic, yield line, white, 36 in. (808-12148) | LFT | 145 | $18.72 | $15.00 | $18.72 | $18.72 | $35.00 | $18.72 |
| 0116 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 481 | $0.84 | $1.25 | $0.84 | $0.84 | $2.00 | $0.84 |
| 0117 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 2,570 | $1.16 | $2.50 | $1.16 | $1.16 | $3.00 | $1.16 |
| 0118 | Transverse marking, thermoplastic, crosshatch line, white, 12 in. (808-75260) | LFT | 167 | $3.90 | $9.00 | $3.90 | $3.90 | $7.50 | $3.90 |
| 0119 | Snowplowable raised pavement marker (808-75998) | EACH | 16 | $325.00 | $385.00 | $125.00 | $250.00 | $325.00 | $125.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of February 12, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way