MoDOT contract 260515-D03 bid tabulation
JCD0135-ROUTE 47-WASHINGTON COUNTY. Let by Missouri DOT on May 15, 2026, Washington, Central. 4 bids received; low bid $6,356,214 by H.R. Quadri Contractors, LLC.
- Owner
- Missouri DOT
- Letting
- 15 MAY 2026
- Pay items
- 103
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | H.R. Quadri Contractors, LLC | $6,356,214 | Low |
| 2 | N.B. West Contracting Company | $7,871,296 | +24% |
| 3 | Robertson Contractors, Inc. | $8,187,367 | +29% |
| 4 | Capital Paving & Construction, LLC | $8,605,485 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. H.R. Quadri Contractors, LLC | 2. N.B. West Contracting Company | 3. Robertson Contractors, Inc. | 4. Capital Paving & Construction, LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Clearing and grubbing (2013000) | ACRE | 8 | $10,000 | $12,500 | $8,500.00 | $11,860 |
| 0020 | Removal of improvements (2022010) | LS | 1 | $53,600 | $190,000 | $85,000 | $115,925 |
| 0030 | Disposal and plugging of wells (2027000) | EACH | 1 | $1,000.00 | $8,370.00 | $7,500.00 | $5,341.70 |
| 0040 | Unclassified excavation (2035000) | CY | 8,475 | $10.00 | $7.00 | $14.60 | $19.69 |
| 0050 | Embankment in place (2035500) | CY | 94,225 | $13.50 | $19.00 | $25.25 | $22.13 |
| 0060 | Compacting embankment (2036000) | CY | 6,272 | $5.00 | $2.00 | $5.60 | $6.67 |
| 0070 | Settlement gauge (2042010) | EACH | 10 | $1,000.00 | $3,780.00 | $2,800.00 | $2,379.12 |
| 0080 | Class 3 excavation (2063000) | CY | 50 | $20.00 | $13.00 | $52.00 | $92.94 |
| 0090 | Class 4 excavation (2063300) | CY | 424 | $20.00 | $28.00 | $35.00 | $61.58 |
| 0100 | Furnishing rock fill (2142000) | CY | 209 | $30.00 | $36.00 | $35.00 | $34.81 |
| 0110 | Placing rock fill (2143000) | CY | 209 | $20.00 | $68.00 | $20.00 | $16.09 |
| 0120 | Type 1 aggregate for base (4 in. thick) (3040143) | SY | 2,553 | $10.00 | $14.00 | $8.66 | $6.38 |
| 0130 | Type 5 aggregate for base (6 in. thick) (3040506) | SY | 10,419 | $15.00 | $13.00 | $12.74 | $9.18 |
| 0140 | Gravel (A) or crushed stone (B) (3105003) | SY | 1,950 | $15.00 | $42.00 | $14.00 | $10.73 |
| 0150 | 5 3/4 inches, bituminous pavement (4010105) | SY | 2,458.90 | $29.37 | $35.00 | $29.37 | $34.86 |
| 0160 | Misc.buckman driveway optional pavement (8 in. PCCP or 10.5 in. HMA) (4019905) | SY | 2,200.10 | $55.00 | $57.00 | $55.00 | $65.29 |
| 0170 | Misc.route 47 optional pavement (8 in. PCCP or 10 in. HMA) (4019905) | SY | 8,219 | $46.68 | $47.00 | $46.68 | $55.41 |
| 0180 | Concrete curb (6 in. height and under) type S (6091010) | LF | 483 | $40.00 | $57.00 | $49.50 | $70.68 |
| 0190 | Furnishing type 1 rock ditch liner (6096010A) | CY | 116 | $30.00 | $31.00 | $55.00 | $37.75 |
| 0200 | Furnishing type 2 rock ditch liner (6096020) | CY | 694 | $30.00 | $31.00 | $55.00 | $62.41 |
| 0210 | Furnishing type 3 rock ditch liner (6096030A) | CY | 1,043 | $30.00 | $31.00 | $55.00 | $55.47 |
| 0220 | Furnishing type 4 rock ditch liner (6096040A) | CY | 8 | $50.00 | $36.00 | $58.00 | $55.47 |
| 0230 | Placing type 1 rock ditch liner (6096041) | CY | 116 | $30.00 | $37.00 | $20.00 | $47.65 |
| 0240 | Placing type 2 rock ditch liner (6096042) | CY | 694 | $30.00 | $39.00 | $18.00 | $47.78 |
| 0250 | Placing type 3 rock ditch liner (6096043) | CY | 1,043 | $30.00 | $41.00 | $14.00 | $31.79 |
| 0260 | Placing type 4 rock ditch liner (6096044) | CY | 8 | $50.00 | $238.00 | $135.00 | $138.18 |
| 0270 | Bedding material for rock ditch liner (6096050) | CY | 382 | $60.00 | $84.00 | $20.00 | $89.98 |
| 0280 | Rock lining (6097000) | CY | 85 | $60.00 | $121.00 | $80.00 | $97.14 |
| 0290 | Furnishing type 2 rock blanket (6113020) | CY | 1,830 | $30.00 | $32.00 | $45.00 | $29.19 |
| 0300 | Placing type 2 rock blanket (6113040) | CY | 1,830 | $30.00 | $30.00 | $15.00 | $24.16 |
| 0310 | Impact attenuator 55 MPH (sand barrel array) (6122012) | EACH | 2 | $3,820.00 | $4,800.00 | $3,820.00 | $1.19 |
| 0320 | Replacement sand barrel (6122020) | EACH | 2 | $490.00 | $550.00 | $490.00 | $237.41 |
| 0330 | Impact attenuator (relocation) (6122030) | EACH | 2 | $975.00 | $3,500.00 | $975.00 | $1,187.04 |
| 0340 | Construction signs (6161005) | SF | 2,496 | $6.00 | $6.00 | $7.50 | $7.12 |
| 0350 | Channelizer (trim-line) (6161025) | EACH | 80 | $24.00 | $19.00 | $18.00 | $28.49 |
| 0360 | Type 3 moveable barricade (6161030) | EACH | 8 | $185.00 | $145.00 | $155.00 | $219.60 |
| 0370 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $3,500.00 | $2,800.00 | $2,800.00 | $4,154.65 |
| 0380 | Work zone traffic signal system (6162000A) | EACH | 3 | $4,000.00 | $6,000.00 | $2,700.00 | $8,226.21 |
| 0390 | Temporary traffic barrier anchored, contractor furnished retained (6173700B) | LF | 1,525 | $53.25 | $45.00 | $45.00 | $55.79 |
| 0400 | Mobilization (6181000) | LS | 1 | $305,294 | $703,032 | $525,000 | $1,032,617 |
| 0410 | Railroad plan submittal (6181015) | LS | 1 | $73,000 | $260,000 | $25,000 | $29,676 |
| 0420 | Additional mobilization for seeding (6181020) | EACH | 3 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0430 | 4 in. white class 1 pavement marking paint (18-mil, type P beads) (6206000D) | LF | 7,352 | $1.07 | $0.75 | $0.75 | $1.27 |
| 0440 | 4 in. yellow class 1 pavement marking paint (18-mil, type P beads) (6206001D) | LF | 7,753 | $1.07 | $0.75 | $0.75 | $1.27 |
| 0450 | 24 in. white class 1 pavement marking paint (18-mil, type P beads) (6206124B) | LF | 34 | $13.00 | $3.00 | $3.00 | $15.43 |
| 0460 | Pavement marking removal (6207001) | LF | 3,289 | $0.50 | $2.00 | $2.20 | $0.59 |
| 0470 | Pavement marking removal (symbols) (6207002) | EACH | 1 | $1,000.00 | $100.00 | $100.00 | $1,187.04 |
| 0480 | Permanent erosion control geotextile (6240103A) | SY | 8,954 | $3.00 | $3.00 | $2.80 | $3.63 |
| 0490 | Bituminous shoulder rumble strip (6261000A) | STA | 46.70 | $40.00 | $50.00 | $50.00 | $47.48 |
| 0500 | Bituminous centerline rumble strip (6261001) | STA | 24.10 | $47.00 | $95.00 | $95.00 | $55.79 |
| 0510 | Contractor furnished surveying and staking (6274000) | LS | 1 | $45,000 | $25,000 | $30,000 | $40,359 |
| 0520 | Class B-1 concrete (culverts) (7034041) | CY | 109.30 | $1,100.00 | $1,260.00 | $1,420.00 | $1,939.96 |
| 0530 | Reinforcing steel (culverts) (7061030) | LB | 18,760 | $2.00 | $2.00 | $2.15 | $4.51 |
| 0540 | 36 in. pipe group C (7250436) | LF | 174 | $70.00 | $145.00 | $100.00 | $90.27 |
| 0550 | 42 in. pipe group A (7261042) | LF | 149 | $125.00 | $170.00 | $205.00 | $190.03 |
| 0560 | 42 in. or allowed substitute group A flared end section (7320642A) | EACH | 2 | $3,000.00 | $4,600.00 | $3,750.00 | $4,485.72 |
| 0570 | 36 in. or allowed substitute group C flared end section (7320836A) | EACH | 2 | $1,000.00 | $3,780.00 | $2,100.00 | $2,403.62 |
| 0580 | Mulching (8025006) | ACRE | 11.30 | $1,400.00 | $1,400.00 | $1,400.00 | $1,661.86 |
| 0590 | Seeding - cool season grasses (8051000A) | ACRE | 5.60 | $2,700.00 | $2,700.00 | $2,700.00 | $3,205.02 |
| 0600 | Seeding - warm season grasses (8052000A) | ACRE | 2.80 | $2,700.00 | $2,700.00 | $2,700.00 | $3,205.02 |
| 0610 | Sediment trap rock (8061004) | CY | 27.80 | $25.00 | $100.00 | $85.00 | $147.80 |
| 0620 | Rock ditch check (8061005) | LF | 4,235 | $11.00 | $11.00 | $11.00 | $13.06 |
| 0630 | Alternate ditch check (8061006) | LF | 2,154 | $9.00 | $9.00 | $9.00 | $10.68 |
| 0640 | Type B berm (8061010A) | LF | 216 | $1.00 | $28.00 | $5.00 | $39.45 |
| 0650 | Slope drains (8061011) | LF | 73 | $5.00 | $96.00 | $38.00 | $73.01 |
| 0660 | Sediment removal (8061016) | CY | 516 | $10.00 | $78.00 | $1.00 | $30.01 |
| 0670 | Temporary seeding (8061017) | ACRE | 2.90 | $900.00 | $900.00 | $900.00 | $1,068.34 |
| 0680 | Silt fence (8061019) | LF | 1,643 | $3.00 | $3.00 | $3.00 | $3.56 |
| 0690 | Type C berm (8061050) | LF | 589 | $5.00 | $29.00 | $20.00 | $33.57 |
| 0700 | Guardrail type D (6061040) | LF | 50 | $24.00 | $24.00 | $83.05 | $28.49 |
| 0710 | MGS guardrail (6061060) | LF | 663 | $30.00 | $30.00 | $27.86 | $35.61 |
| 0720 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 4 | $4,100.00 | $4,100.00 | $3,796.50 | $4,866.88 |
| 0730 | Type A crashworthy end terminal (MASH) (6063014) | EACH | 4 | $3,800.00 | $3,800.00 | $3,107.04 | $4,510.77 |
| 0740 | U-channel post, 3 LB (9031250A) | LF | 73 | $32.00 | $32.00 | $32.67 | $37.99 |
| 0750 | 2.5 in. PSST post - 12 GA. (9031280) | LF | 104 | $36.00 | $36.00 | $35.68 | $42.73 |
| 0760 | Driven post anchor for 2.5 in. PSST - 7 GA. (9031281A) | EACH | 11 | $275.00 | $275.00 | $238.56 | $326.44 |
| 0770 | SH-flat sheet (9035004A) | SF | 27 | $36.00 | $36.00 | $77.65 | $42.73 |
| 0780 | SHF-flat sheet fluorescent (9035069A) | SF | 50 | $40.00 | $40.00 | $49.41 | $47.48 |
| 0790 | Class 1 excavation (2061000) | CY | 125 | $34.00 | $69.00 | $1.20 | $65.90 |
| 0800 | Bridge approach slab (minor road) (5031011A) | SY | 125 | $145.00 | $167.00 | $255.00 | $222.38 |
| 0810 | Drilled shafts (5 FT. 0 in. dia.) (7011108) | LF | 22.40 | $1,550.00 | $1,090.00 | $2,050.00 | $1,709.64 |
| 0820 | Rock sockets (4 FT 6 in. dia.) (7011207) | LF | 26 | $1,800.00 | $1,590.00 | $2,450.00 | $1,408.11 |
| 0830 | Video camera inspection (7011300) | EACH | 2 | $500.00 | $1,340.00 | $1,250.00 | $593.52 |
| 0840 | Foundation inspection holes (7011400) | LF | 46 | $175.00 | $330.00 | $250.00 | $237.56 |
| 0850 | Sonic logging testing (7011600) | EACH | 2 | $5,000.00 | $5,990.00 | $3,000.00 | $6,364.37 |
| 0860 | Galvanized structural steel piles (12 in) (7021212) | LF | 509 | $145.00 | $136.00 | $165.00 | $139.65 |
| 0870 | Pre-bore for piling (7026000) | LF | 60 | $525.00 | $349.00 | $400.00 | $450.00 |
| 0880 | Pile point reinforcement (7027000) | EACH | 12 | $360.00 | $188.00 | $300.00 | $150.16 |
| 0890 | Class B concrete (substructure) (7032003) | CY | 67.70 | $1,850.00 | $1,090.00 | $1,430.00 | $1,068.94 |
| 0900 | Class B-1 concrete (substructure) (7034003) | CY | 29.60 | $985.00 | $1,280.00 | $1,550.00 | $819.57 |
| 0910 | Type D barrier (7034219A) | LF | 705 | $160.00 | $119.00 | $158.00 | $135.06 |
| 0920 | Slab on steel (with transparent forms) (7034231) | SY | 1,082 | $740.00 | $591.00 | $680.00 | $693.04 |
| 0930 | Reinforcing steel (bridges) (7061060) | LB | 17,620 | $3.05 | $3.00 | $2.35 | $3.53 |
| 0940 | Temporary coating - concrete bents and piers (weathering steel) (7110500) | LS | 1 | $19,500 | $19,500 | $19,500 | $23,147 |
| 0950 | Fabricated structural low alloy steel (plate girder) A709, grade 50W (7121122) | LB | 471,260 | $2.28 | $2.75 | $3.20 | $2.48 |
| 0960 | Slab drain (7123610) | EACH | 11 | $680.00 | $776.00 | $650.00 | $653.53 |
| 0970 | Vertical drain at end bents (7151001) | EACH | 2 | $2,350.00 | $7,380.00 | $3,650.00 | $2,754.70 |
| 0980 | Laminated neoprene bearing pad (tapered) (7161003) | EACH | 8 | $460.00 | $837.00 | $765.00 | $534.50 |
| 0990 | Laminated neoprene bearing pad assembly (7162000) | EACH | 4 | $5,150.00 | $6,140.00 | $6,550.00 | $5,501.61 |
| 1000 | Class 4 excavation (2063300) | CY | 255 | $10.00 | $132.00 | $60.00 | $123.60 |
| 1010 | Misc.dewatering (2069901) | LS | 1 | $5,000.00 | $12,200 | $15,000 | $21,245 |
| 1020 | Class B-1 concrete (culverts-bridge) (7034040) | CY | 197.60 | $1,100.00 | $1,210.00 | $1,205.00 | $1,629.36 |
| 1030 | Reinforcing steel (culverts-bridge) (7061020) | LB | 25,430 | $2.00 | $2.00 | $2.00 | $3.56 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of May 15, 2026. Compiled by Mirage Metrics.