ODOT contract 250049 bid tabulation
GRE-IR 71/SR 72-01.50/00.29 (BRIDGE REPAIR). Let by Ohio DOT on January 30, 2025, GRE. 4 bids received; low bid $2,794,718 by Miller Bros Const Inc, -2.5% against the engineer's estimate of $2,866,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 121
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Miller Bros Const Inc | $2,794,718 | Low | -2.0% |
| 2 | Complete General Construction Company | $2,841,323 | +2.0% | -1.0% |
| 3 | Eagle Bridge Co | $3,017,585 | +8.0% | +5.0% |
| 4 | Sunesis Construction Co | $3,150,349 | +13% | +10% |
Engineer's estimate: $2,866,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Miller Bros Const Inc | 2. Complete General Construction Company | 3. Eagle Bridge Co | 4. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,500.00 | $5,000.00 | $1,500.00 | $7,392.00 |
| 2 | Pavement removed (202E23000) | SY | 1,302 | $9.00 | $20.00 | $18.00 | $14.00 |
| 3 | Guardrail removed (202E38000) | FT | 850 | $2.00 | $2.00 | $2.00 | $3.00 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 2 | $145.00 | $145.00 | $145.00 | $150.00 |
| 5 | Bridge terminal assembly removed (202E47000) | EACH | 4 | $75.00 | $75.00 | $75.00 | $125.00 |
| 6 | Excavation (203E10000) | CY | 824 | $26.00 | $28.00 | $15.00 | $16.00 |
| 7 | Embankment (203E20000) | CY | 124 | $25.00 | $36.00 | $30.00 | $24.00 |
| 8 | Subgrade compaction (204E10000) | SY | 2,197 | $3.50 | $4.50 | $4.50 | $5.00 |
| 9 | Proof rolling (204E45000) | HR | 2 | $700.00 | $125.00 | $150.00 | $222.00 |
| 10 | Guardrail, type MGS with long posts (606E15100) | FT | 900 | $22.00 | $22.00 | $22.00 | $22.00 |
| 11 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 1 | $2,620.00 | $2,620.00 | $2,620.00 | $2,600.00 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,380.00 | $1,380.00 | $1,380.00 | $1,250.00 |
| 13 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,560.00 | $2,560.00 | $2,560.00 | $2,300.00 |
| 14 | Compacted aggregate (617E10100) | CY | 37 | $135.00 | $140.00 | $110.00 | $156.00 |
| 15 | Special - misc: consultant for concrete quality CO (690E98400) | LS | 1 | $16,000 | $6,000.00 | $5,000.00 | $10,000 |
| 16 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 158 | $60.00 | $160.00 | $75.00 | $153.00 |
| 17 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $250.00 | $150.00 | $100.00 |
| 18 | Topsoil (659E00300) | CY | 94 | $24.00 | $40.00 | $5.00 | $0.01 |
| 19 | Seeding and mulching (659E10000) | SY | 846 | $4.30 | $5.40 | $4.00 | $4.00 |
| 20 | Repair seeding and mulching (659E14000) | SY | 42 | $4.30 | $1.59 | $2.00 | $2.00 |
| 21 | Inter-seeding (659E15000) | SY | 42 | $4.30 | $0.11 | $2.00 | $2.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.11 | $1,250.00 | $624.73 | $1,750.00 | $1,400.00 |
| 23 | Lime (659E31000) | ACRE | 0.17 | $150.00 | $56.76 | $10.00 | $450.00 |
| 24 | Water (659E35000) | MGAL | 5 | $1.00 | $1.14 | $10.00 | $25.00 |
| 25 | Slope erosion protection mat, type C (670E00530) | SY | 266 | $3.00 | $3.69 | $3.00 | $2.00 |
| 26 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,345.00 | $1,500.00 | $3,500.00 | $3,345.00 |
| 27 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $15,300 | $5,000.00 | $11,000 | $10,920 |
| 28 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $14,468 | $14,475 | $17,500 | $14,468 |
| 29 | Erosion control (832E30000) | EACH | 19,538 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Aggregate drains (605E31100) | FT | 266 | $26.00 | $19.00 | $11.00 | $14.00 |
| 31 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 429 | $21.00 | $26.00 | $21.00 | $26.00 |
| 32 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 414 | $213.00 | $240.00 | $213.00 | $240.00 |
| 33 | Aggregate base (304E20000) | CY | 357 | $75.00 | $123.00 | $95.00 | $104.00 |
| 34 | Tack coat (407E10000) | GAL | 284 | $3.90 | $5.00 | $3.90 | $5.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 18 | $3.90 | $10.00 | $3.90 | $10.00 |
| 36 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 60 | $350.00 | $400.00 | $350.00 | $400.00 |
| 37 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 78 | $310.00 | $390.00 | $310.00 | $390.00 |
| 38 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 110 | $225.00 | $325.00 | $225.00 | $325.00 |
| 39 | Curb, type 4-C (609E24510) | FT | 100 | $58.00 | $86.00 | $70.00 | $40.00 |
| 40 | RPM (621E00100) | EACH | 12 | $217.50 | $208.00 | $217.50 | $218.00 |
| 41 | Raised pavement marker removed (621E54000) | EACH | 14 | $60.00 | $44.00 | $20.00 | $7.00 |
| 42 | Barrier reflector, type 1, bidirectional (626E00102) | EACH | 8 | $12.50 | $12.50 | $12.50 | $12.00 |
| 43 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 10 | $13.50 | $13.50 | $13.50 | $12.00 |
| 44 | Ground mounted support, no. 3 post (630E03100) | FT | 48 | $15.50 | $32.50 | $15.50 | $16.00 |
| 45 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $45.00 | $65.00 | $45.00 | $45.00 |
| 46 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $20.00 | $15.00 | $20.00 | $20.00 |
| 47 | Edge line, 6", type 1 (642E00104) | MI | 0.10 | $10,995 | $13,605 | $10,995 | $10,995 |
| 48 | Center line, type 1 (642E00300) | MI | 0.05 | $14,655 | $18,145 | $14,655 | $14,655 |
| 49 | Edge line, 6" (644E00104) | MI | 0.22 | $10,520 | $12,435 | $10,520 | $10,520 |
| 50 | Center line (644E00300) | MI | 0.11 | $14,030 | $15,820 | $14,030 | $14,030 |
| 51 | Edge line, 6" (646E10010) | MI | 0.12 | $21,055 | $18,290 | $21,055 | $21,055 |
| 52 | Center line (646E10200) | MI | 0.06 | $28,080 | $24,400 | $28,080 | $28,080 |
| 53 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 250 | $110.00 | $85.00 | $115.00 | $85.00 |
| 54 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 3 | $2,860.00 | $2,400.00 | $2,860.00 | $2,400.00 |
| 55 | Detour signing (614E12420) | LS | 1 | $21,995 | $54,950 | $30,000 | $12,033 |
| 56 | Barrier reflector, type 1 (one-way) (614E13310) | EACH | 20 | $14.00 | $14.00 | $13.00 | $14.00 |
| 57 | Object marker, one way (614E13350) | EACH | 20 | $18.00 | $18.00 | $18.00 | $18.00 |
| 58 | Portable changeable message sign, as per plan (614E18601) | SNMT | 36 | $995.00 | $800.00 | $725.00 | $995.00 |
| 59 | Water (616E10000) | MGAL | 5 | $450.00 | $68.84 | $20.00 | $19.00 |
| 60 | Portable barrier, unanchored (622E41100) | FT | 540 | $70.00 | $29.25 | $50.00 | $29.00 |
| 61 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 14 | $85.00 | $27.00 | $60.00 | $35.00 |
| 62 | Class QC1 concrete, misc.: shoulder pier barrier R (511E53010) | CY | 3 | $2,500.00 | $3,500.00 | $8,000.00 | $4,255.00 |
| 63 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 51 | $65.00 | $35.00 | $35.00 | $35.00 |
| 64 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 822 | $28.00 | $29.30 | $22.00 | $28.00 |
| 65 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 31 | $47.00 | $40.00 | $40.00 | $40.00 |
| 66 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 2 | $100.00 | $250.00 | $250.00 | $250.00 |
| 67 | Field painting, misc.: coating beam ends (514E27700) | SF | 175 | $100.00 | $150.00 | $150.00 | $150.00 |
| 68 | Joint sealer (516E31000) | FT | 55 | $33.00 | $45.00 | $100.00 | $23.00 |
| 69 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44301) | EACH | 8 | $2,100.00 | $1,685.00 | $2,250.00 | $2,460.00 |
| 70 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $37,000 | $15,000 | $35,000 | $20,172 |
| 71 | Patching concrete structure, as per plan (519E11101) | SF | 216 | $340.00 | $185.00 | $200.00 | $242.00 |
| 72 | Concrete patching with galvanic anode protection (844E10000) | SF | 57 | $345.00 | $175.00 | $210.00 | $178.00 |
| 73 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $245,000 | $220,000 | $325,000 | $334,797 |
| 74 | Approach slab removed (202E22900) | SY | 192 | $67.00 | $55.00 | $35.00 | $67.00 |
| 75 | Vandal protection fence removed (202E75260) | FT | 566 | $7.50 | $7.50 | $7.50 | $20.00 |
| 76 | Removal misc.: portion of structure removed, bulb (202E98200) | FT | 566 | $16.00 | $24.00 | $30.00 | $7.00 |
| 77 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $400.00 | $400.00 | $1.00 | $2,500.00 |
| 78 | Unclassified excavation (503E21300) | LS | 1 | $31,000 | $34,000 | $40,000 | $28,768 |
| 79 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 200 | $1.75 | $1.41 | $1.25 | $3.00 |
| 80 | Uncoated steel reinforcement (509E25000) | LB | 8,342 | $1.15 | $1.42 | $1.25 | $1.00 |
| 81 | Galvanized steel reinforcement (509E26000) | LB | 94,083 | $1.80 | $1.98 | $2.00 | $2.00 |
| 82 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 9,484 | $1.40 | $1.47 | $1.50 | $1.00 |
| 83 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 64 | $30.00 | $19.00 | $40.00 | $33.00 |
| 84 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 360 | $39.00 | $19.00 | $30.00 | $33.00 |
| 85 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 2 | $4,500.00 | $3,500.00 | $5,500.00 | $5,076.00 |
| 86 | Class QC2 concrete with QC/QA, bridge deck, as per plan (511E34447) | CY | 329 | $1,150.00 | $1,100.00 | $1,250.00 | $1,360.00 |
| 87 | Class QC2 concrete with QC/QA, bridge deck (parapet), as per plan (511E34451) | CY | 94 | $625.00 | $850.00 | $925.00 | $656.00 |
| 88 | Class QC1 concrete, pier, as per plan (511E43211) | CY | 22 | $1,550.00 | $2,400.00 | $2,750.00 | $8,047.00 |
| 89 | Class QC1 concrete, abutment (511E45710) | CY | 40 | $760.00 | $1,500.00 | $1,650.00 | $1,389.00 |
| 90 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,105 | $30.00 | $26.00 | $26.00 | $26.00 |
| 91 | Type 2 waterproofing (512E33000) | SY | 36 | $60.00 | $40.00 | $40.00 | $27.00 |
| 92 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 292 | $26.00 | $32.00 | $32.00 | $32.00 |
| 93 | Welded stud shear connectors (513E20000) | EACH | 4,620 | $4.70 | $7.00 | $4.60 | $5.00 |
| 94 | Surface preparation of existing structural steel (514E00050) | SF | 16,180 | $12.00 | $10.00 | $10.00 | $10.00 |
| 95 | Field painting of existing structural steel, prime coat (514E00056) | SF | 16,180 | $4.00 | $5.00 | $5.00 | $5.00 |
| 96 | Field painting structural steel, intermediate coat (514E00060) | SF | 16,270 | $4.00 | $4.00 | $4.00 | $4.00 |
| 97 | Field painting structural steel, finish coat (514E00066) | SF | 16,270 | $4.00 | $2.50 | $2.50 | $3.00 |
| 98 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 24 | $100.00 | $150.00 | $150.00 | $150.00 |
| 99 | Final inspection repair (514E10000) | EACH | 8 | $100.00 | $200.00 | $200.00 | $200.00 |
| 100 | Field painting, misc.: coating of beam ends (514E27700) | SF | 250 | $140.00 | $135.00 | $135.00 | $135.00 |
| 101 | Armorless preformed joint seal (516E10010) | FT | 67 | $50.00 | $95.00 | $75.00 | $81.00 |
| 102 | 1" preformed expansion joint filler (516E13600) | SF | 17 | $23.00 | $12.00 | $10.00 | $7.00 |
| 103 | 2" preformed expansion joint filler (516E13900) | SF | 72 | $14.00 | $14.00 | $15.00 | $15.00 |
| 104 | Semi-integral abutment expansion joint seal (516E14020) | FT | 103 | $34.00 | $45.00 | $40.00 | $57.00 |
| 105 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 15 | $2,000.00 | $1,190.00 | $2,500.00 | $2,311.00 |
| 106 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44301) | EACH | 10 | $2,100.00 | $1,685.00 | $2,000.00 | $2,686.00 |
| 107 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $76,000 | $44,000 | $65,000 | $41,508 |
| 108 | Porous backfill with geotextile fabric (518E21200) | CY | 73 | $125.00 | $118.00 | $135.00 | $76.00 |
| 109 | 6" perforated corrugated plastic pipe (518E40000) | FT | 80 | $10.00 | $14.00 | $20.00 | $6.00 |
| 110 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 88 | $28.00 | $21.00 | $20.00 | $6.00 |
| 111 | Structure drainage, misc.: plugging existing weeph (518E62200) | EACH | 8 | $290.00 | $140.00 | $250.00 | $194.00 |
| 112 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 191 | $365.00 | $460.00 | $500.00 | $579.00 |
| 113 | Type C installation, as per plan (526E90031) | FT | 67 | $325.00 | $350.00 | $375.00 | $361.00 |
| 114 | Crushed aggregate slope protection (601E20010) | CY | 121 | $95.00 | $115.00 | $60.00 | $126.00 |
| 115 | Vandal protection fence, 6' straight, coated fabric (607E39900) | FT | 460 | $94.50 | $94.50 | $94.50 | $98.00 |
| 116 | Structure grounding system (625E33000) | EACH | 1 | $8,200.00 | $16,000 | $15,000 | $8,200.00 |
| 117 | Patching concrete structures with trowelable mortar (843E50000) | SF | 42 | $265.00 | $155.00 | $225.00 | $187.00 |
| 118 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $13,534 | $19,000 | $45,000 | $16,490 |
| 119 | Maintaining traffic (614E11000) | LS | 1 | $58,000 | $150,000 | $60,000 | $123,019 |
| 120 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,100 | $10,000 | $25,000 | $38,500 |
| 121 | Mobilization (624E10000) | LS | 1 | $139,736 | $100,000 | $140,000 | $106,424 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.