ODOT contract 250191 bid tabulation

D03-D12 Pedestrian Safety FY2025 (SPOT SAFETY). Let by Ohio DOT on April 10, 2025, District 3. 2 bids received; low bid $1,627,656 by Perk Company Inc, +7.1% against the engineer's estimate of $1,520,000.

Owner
Ohio DOT
Letting
10 APR 2025
Pay items
82
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Perk Company Inc$1,627,656Low+7.0%
2Madex Construction Co$2,371,885+46%+56%
ODOT contract 250191: bids by rank

Engineer's estimate: $1,520,000.

Bid tabulation

LinePay itemUnitQuantity1. Perk Company Inc2. Madex Construction Co
1Clearing and grubbing (201E11000)LS1$500.00$10,322
2Pavement removed (202E23000)SY1,845$25.00$31.54
3Walk removed, as per plan (202E30001)SF6,024$4.50$6.97
4Concrete median removed (202E30600)SY13$100.00$127.09
5Traffic island removed (202E30800)SY22$60.00$92.29
6Curb removed, as per plan (202E32001)FT741$16.50$21.61
7Guardrail removed (202E38000)FT15$20.00$26.76
8Excavation (203E10000)CY10$185.00$41.19
9Embankment (203E20000)CY10$195.00$41.77
10Subgrade compaction (204E10000)SY735$8.00$4.28
114" concrete walk, as per plan (608E10001)SF4,280$22.00$32.50
12Curb ramp, as per plan (608E52001)SF5,879$40.00$47.31
13Light pole foundation removed (625E75500)EACH3$950.00$2,065.15
14Topsoil (659E00300)CY5$225.00$143.74
15Seeding and mulching, class 1 (659E00500)SY100$44.00$10.58
16Seeding and mulching (659E10000)SY838$10.00$7.95
17Water (659E35000)MGAL5$125.00$51.92
18Erosion control (832E30000)EACH18,000$1.00$1.00
19Manhole adjusted to grade (611E99654)EACH10$2,000.00$2,691.21
20Special - gas valve box adjusted to grade (611E99700)EACH1$500.00$1,128.90
21Partial depth pavement repair (441), as per plan (251E01001)SY75$225.00$289.47
22Asphalt concrete base, PG64-22, (449) (301E56000)CY163$450.00$376.32
23Aggregate base (304E20000)CY126$110.00$219.72
24Non-tracking tack coat (407E20000)GAL82$10.00$11.58
25Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY31$765.00$1,476.32
26Asphalt concrete intermediate course, type 2, (449) (441E70300)CY38$725.00$1,447.37
27Curb, type 6, as per plan (609E26001)FT2,249$68.00$67.70
28Concrete median, as per plan (609E71001)SF162$21.00$69.69
29Ground mounted support, no. 3 post (630E03100)FT1,274$12.00$22.00
30Sign post reflector (630E08600)EACH100$45.00$52.11
31Sign hanger assembly, span wire (630E79000)EACH2$325.00$347.37
32Sign support assembly, pole mounted (630E79500)EACH49$75.00$214.21
33Sign, flat sheet (630E80100)SF1,471.80$14.00$28.95
34Removal of ground mounted sign and disposal (630E84900)EACH13$30.00$17.37
35Removal of ground mounted sign and storage (630E85000)EACH15$35.00$52.11
36Removal of ground mounted sign and reerection (630E85100)EACH6$95.00$75.26
37Removal of ground mounted post support and disposal (630E86002)EACH28$40.00$23.16
38Signing, misc.: solar-powered rectangular rapid FL (630E97700)EACH19$7,200.00$8,336.84
39Edge line, 4" (644E00100)MI1$4,800.00$3,473.68
40Stop line (644E00500)FT755$8.50$8.11
41Crosswalk line, 12" (644E00620)FT12,722$4.00$5.79
42Crosswalk line, 24" (644E00630)FT11,427$8.00$9.26
43Curb marking (644E00800)FT132$3.00$8.11
44Island marking (644E00900)SF97$4.00$6.95
45Lane arrow (644E01300)EACH4$105.00$150.53
46Yield line (644E20800)FT906$15.00$10.42
47Removal of pavement marking (644E30000)FT7,033$3.00$0.29
48Removal of pavement marking (644E30020)EACH4$200.00$115.79
49Longitudinal channelizing device, as per plan (831E00101)FT360$90.00$104.21
50Conduit, 2", 725.051 (625E25408)FT734$7.50$8.68
51Conduit, 3", 725.051 (625E25504)FT85$9.50$11.00
52Conduit, jacked or drilled, 725.051, as per plan (625E25907)FT510$65.00$75.26
53Conduit, jacked or drilled, 725.051, as per plan (625E25907)FT60$70.00$81.05
54Conduit, jacked or drilled, 725.051, as per plan (625E25907)FT200$75.00$86.84
55Trench (625E29000)FT518$12.00$13.89
56Trench in paved area (625E29400)FT318$112.00$13.89
57Pull box, 725.08, 18" (625E30700)EACH7$950.00$1,100.00
58Pull box removed (625E31510)EACH2$300.00$347.37
59Ground rod (625E32000)EACH39$275.00$318.42
60Underground warning marking tape (625E36010)FT836$3.50$4.05
61Pull box cleaned (625E39520)EACH20$200.00$231.58
62Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH43$505.00$584.74
63Accessible pedestrian pushbutton, as per plan (632E20751)EACH27$1,800.00$2,084.21
64Signal cable, 5 conductor, no. 14 AWG (632E40500)FT6,660$2.55$2.95
65Signal cable, 7 conductor, no. 14 AWG (632E40700)FT395$2.95$3.42
66Pedestal foundation, as per plan (632E64021)EACH39$1,100.00$1,273.68
67Test hole performed (632E64950)EACH39$200.00$231.58
68Conduit riser, 2" diameter (632E70400)EACH2$475.00$550.00
69Pedestal, 5', transformer base (632E89802)EACH2$700.00$810.53
70Pedestal, 8', transformer base (632E89900)EACH18$900.00$1,042.11
71Signalization, misc.: unlash and relash messenger (632E90500)FT150$6.00$6.95
72Controller item, misc.: add pedestrian phases (633E99000)EACH10$1,400.00$1,621.05
73Controller item, misc.: load controller settings (633E99000)EACH7$900.00$1,042.11
74Controller item, misc.: pedestrian load switch (633E99000)EACH10$300.00$347.37
75Law enforcement officer with patrol car for assistance (614E11110)HR120$110.00$114.63
76Water (616E10000)MGAL16$1.00$37.63
77Premium for contract performance bond and for payment bond (103E05000)LS1$17,370$166,737
78CPM progress schedule (108E10000)LS1$5,000.00$17,368
79Maintaining traffic (614E11000)LS1$34,260$101,127
80Field office, type B, as per plan (619E16011)MNTH6$3,500.00$1,764.71
81Construction layout stakes and surveying (623E10000)LS1$6,500.00$40,526
82Mobilization (624E10000)LS1$20,000$225,034
ODOT contract 250191: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy