ODOT contract 250194 bid tabulation
HUR-US 250/SR 61-00.75/VAR (TWO LANE RESURFACING). Let by Ohio DOT on April 10, 2025, HUR. 2 bids received; low bid $4,887,128 by Gerken Paving Inc, -0.3% against the engineer's estimate of $4,902,000.
- Owner
- Ohio DOT
- Letting
- 10 APR 2025
- Pay items
- 127
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Gerken Paving Inc | $4,887,128 | Low | 0.0% |
| 2 | Erie Blacktop Inc | $5,115,588 | +5.0% | +4.0% |
Engineer's estimate: $4,902,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gerken Paving Inc | 2. Erie Blacktop Inc |
|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 21,492 | $2.00 | $1.85 |
| 2 | Curb removed (202E32000) | FT | 1,975 | $8.00 | $13.85 |
| 3 | Curb and gutter removed (202E32500) | FT | 1,276 | $10.00 | $12.75 |
| 4 | Guardrail removed (202E38000) | FT | 1,031.25 | $2.00 | $2.10 |
| 5 | Guardrail post removed (202E38700) | EACH | 4 | $15.00 | $15.75 |
| 6 | Anchor assembly removed, type A (202E42000) | EACH | 3 | $245.00 | $260.00 |
| 7 | Anchor assembly removed, type E (202E42010) | EACH | 7 | $120.00 | $126.00 |
| 8 | Anchor assembly removed, type T (202E42040) | EACH | 3 | $95.00 | $99.75 |
| 9 | Anchor assembly removed, type B (202E42050) | EACH | 2 | $110.00 | $115.50 |
| 10 | Bridge terminal assembly removed (202E47000) | EACH | 5 | $65.00 | $68.25 |
| 11 | Embankment, as per plan (203E20001) | CY | 91.50 | $66.00 | $69.30 |
| 12 | Reshaping under guardrail, as per plan (209E15001) | STA | 6 | $50.00 | $52.50 |
| 13 | Linear grading (209E60500) | MI | 3.50 | $2,000.00 | $2,275.00 |
| 14 | Guardrail, type 5 (606E13000) | FT | 168.75 | $20.00 | $21.00 |
| 15 | Guardrail, type MGS (606E15050) | FT | 1,075 | $18.80 | $19.75 |
| 16 | Guardrail rebuilt, type 5 (606E16500) | FT | 12.50 | $18.00 | $18.90 |
| 17 | Raising type 5 guardrail (606E17000) | FT | 300 | $6.80 | $7.15 |
| 18 | Replace existing guardrail blockout (606E17700) | EACH | 5 | $45.00 | $47.25 |
| 19 | Guardrail post (606E17900) | EACH | 6 | $135.00 | $142.00 |
| 20 | Anchor assembly, type E (606E26100) | EACH | 3 | $2,280.00 | $2,395.00 |
| 21 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 4 | $2,320.00 | $2,440.00 |
| 22 | Anchor assembly, type T (606E26500) | EACH | 2 | $960.00 | $1,010.00 |
| 23 | Anchor assembly, MGS type T (606E26550) | EACH | 6 | $1,320.00 | $1,390.00 |
| 24 | Anchor assembly rebuilt, type E (606E27850) | EACH | 1 | $1,050.00 | $1,100.00 |
| 25 | Anchor assembly rebuilt, type T (606E27900) | EACH | 3 | $750.00 | $790.00 |
| 26 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 1 | $2,550.00 | $2,680.00 |
| 27 | Bridge terminal assembly, type 2 (606E35100) | EACH | 1 | $520.00 | $550.00 |
| 28 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 1 | $550.00 | $580.00 |
| 29 | Bridge terminal assembly, type 4 (606E35140) | EACH | 2 | $930.00 | $980.00 |
| 30 | 4" concrete walk (608E10000) | SF | 8,462 | $7.50 | $9.40 |
| 31 | Curb ramp (608E52000) | SF | 16,368 | $17.50 | $13.85 |
| 32 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 15 | $439.95 | $465.00 |
| 33 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 5 | $1,029.95 | $1,085.00 |
| 34 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,645.00 | $3,830.00 |
| 35 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 13 | $13.50 | $14.20 |
| 36 | Topsoil, as per plan (659E00301) | CY | 37 | $35.00 | $120.00 |
| 37 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 38 | Catch basin adjusted to grade (611E98630) | EACH | 203 | $1,125.00 | $895.00 |
| 39 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 22 | $1,600.00 | $2,550.00 |
| 40 | Manhole adjusted to grade (611E99654) | EACH | 223 | $644.95 | $680.00 |
| 41 | Special - miscellaneous metal (611E99820) | LB | 1,500 | $2.50 | $2.65 |
| 42 | Partial depth pavement repair (asphalt concrete base) (251E01042) | CY | 1,255 | $220.00 | $300.00 |
| 43 | Full depth pavement sawing (252E01500) | FT | 32 | $5.50 | $46.00 |
| 44 | Pavement repair (253E02000) | CY | 125 | $310.00 | $400.00 |
| 45 | Pavement planing, asphalt concrete(1.50") (254E01000) | SY | 192,980 | $2.60 | $2.15 |
| 46 | Patching planed surface (254E01600) | SY | 872 | $12.00 | $8.90 |
| 47 | Non-tracking tack coat (407E20000) | GAL | 17,368 | $2.25 | $2.55 |
| 48 | Prime coat, as per plan (408E10001) | GAL | 1,643 | $7.25 | $5.40 |
| 49 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 7,827 | $218.00 | $230.00 |
| 50 | Combination curb and gutter, type 2 (609E12000) | FT | 376 | $32.00 | $38.60 |
| 51 | Curb, type 2-A, as per plan (609E14001) | FT | 275 | $15.00 | $38.80 |
| 52 | Curb, type 6 (609E26000) | FT | 514 | $28.00 | $27.60 |
| 53 | Curb, type 6, as per plan (609E26001) | FT | 192 | $28.00 | $34.40 |
| 54 | Compacted aggregate (617E10100) | CY | 229 | $100.00 | $85.00 |
| 55 | Valve box adjusted to grade (638E10800) | EACH | 130 | $419.95 | $440.00 |
| 56 | Sign support assembly, pole mounted (630E79500) | EACH | 5 | $425.00 | $142.00 |
| 57 | Sign, flat sheet (630E80100) | SF | 5 | $35.00 | $29.40 |
| 58 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $65.00 | $78.75 |
| 59 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $25.00 | $31.50 |
| 60 | Edge line, 6", type 1 (642E00104) | MI | 0.60 | $800.00 | $1,050.00 |
| 61 | Center line, type 1 (642E00300) | MI | 1.02 | $900.00 | $1,260.00 |
| 62 | Channelizing line, 8" (644E00400) | FT | 1,617 | $2.00 | $1.60 |
| 63 | Stop line (644E00500) | FT | 352 | $7.00 | $7.35 |
| 64 | Transverse/diagonal line (644E00700) | FT | 1,463 | $6.00 | $6.30 |
| 65 | Lane arrow (644E01300) | EACH | 16 | $90.00 | $105.00 |
| 66 | Edge line, 6" (646E10010) | MI | 0.18 | $16,200 | $8,400.00 |
| 67 | Center line (646E10200) | MI | 0.13 | $16,200 | $12,600 |
| 81 | Edge line, 6" (644E00104) | MI | 2.28 | $4,175.00 | $3,850.00 |
| 82 | Edge line, 6" (644E00104) | MI | 1.58 | $4,175.00 | $3,850.00 |
| 83 | Center line (644E00300) | MI | 7.91 | $4,000.00 | $6,050.00 |
| 84 | Channelizing line, 8" (644E00400) | FT | 8,171 | $1.30 | $1.65 |
| 85 | Stop line (644E00500) | FT | 1,510 | $7.00 | $6.60 |
| 86 | Crosswalk line, 24" (644E00630) | FT | 2,221 | $7.00 | $6.60 |
| 87 | Crosswalk line, 24", as per plan (644E00631) | FT | 667 | $14.00 | $6.60 |
| 88 | Transverse/diagonal line (644E00700) | FT | 1,006 | $8.00 | $6.60 |
| 89 | Railroad symbol marking (644E01000) | EACH | 2 | $800.00 | $605.00 |
| 90 | School symbol marking, 72" (644E01100) | EACH | 4 | $700.00 | $330.00 |
| 91 | Parking lot stall marking (644E01200) | FT | 3,010 | $3.00 | $1.65 |
| 92 | Lane arrow (644E01300) | EACH | 200 | $90.00 | $93.50 |
| 93 | Pavement marking, misc.:(handicap parking stall) ( [alternate group AA2] (644E50100) | EACH | 4 | $300.00 | $82.50 |
| 94 | Pedestrian signal head (LED), type D2, countdown (632E20730) | EACH | 2 | $975.00 | $1,025.00 |
| 95 | Accessible pedestrian pushbutton (632E20750) | EACH | 2 | $950.00 | $1,000.00 |
| 96 | Detector loop, as per plan (632E26501) | EACH | 45 | $1,650.00 | $1,735.00 |
| 97 | Pedestal foundation, as per plan (632E64021) | EACH | 10 | $1,950.00 | $2,050.00 |
| 98 | Reuse of pedestrian signal head, as per plan (632E90203) | EACH | 8 | $950.00 | $1,000.00 |
| 99 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 520 | $110.00 | $96.50 |
| 100 | Work zone marking sign (614E12460) | EACH | 166 | $125.00 | $73.50 |
| 101 | Work zone marking sign (614E12460) | EACH | 16 | $125.00 | $147.00 |
| 102 | Asphalt concrete for maintaining traffic (614E13000) | CY | 45 | $525.00 | $450.00 |
| 103 | Portable changeable message sign, as per plan (614E18601) | SNMT | 20 | $1,450.00 | $1,050.00 |
| 104 | Work zone center line, class III, 642 paint (614E21550) | MI | 17.87 | $900.00 | $1,155.00 |
| 105 | Work zone stop line, class III, 642 paint (614E26610) | FT | 3,724 | $3.00 | $2.10 |
| 106 | Portions of structure removed, as per plan (202E11301) | CY | 13 | $1,467.76 | $1,540.00 |
| 107 | Removal misc.:joint sealer (202E98200) | FT | 169 | $8.19 | $8.60 |
| 108 | Excavation, as per plan (203E10001) | CY | 4 | $117.50 | $125.00 |
| 109 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 33 | $26.55 | $28.00 |
| 110 | Class QC2 concrete, bridge deck (511E34444) | CY | 10 | $2,210.25 | $2,320.00 |
| 111 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 15 | $47.12 | $49.50 |
| 112 | Trimming of beam end, as per plan (513E21001) | EACH | 12 | $1,958.25 | $2,060.00 |
| 113 | Joint sealer (516E31000) | FT | 169 | $27.24 | $28.60 |
| 114 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $21,604 | $22,685 |
| 115 | Topsoil, as per plan (659E00301) | CY | 4 | $115.00 | $270.00 |
| 116 | Seeding and mulching (659E10000) | SY | 20 | $73.80 | $77.50 |
| 117 | Repair seeding and mulching (659E14000) | SY | 1 | $8.00 | $8.40 |
| 118 | Inter-seeding (659E15000) | SY | 1 | $1.95 | $2.05 |
| 119 | Commercial fertilizer (659E20000) | TON | 0.01 | $1,250.00 | $1,313.00 |
| 120 | Lime (659E31000) | ACRE | 0.01 | $100.00 | $105.00 |
| 121 | Water (659E35000) | MGAL | 0.11 | $5.00 | $5.27 |
| 122 | Superplasticized dense concrete overlay using hydrodemolition (848E10200) | SY | 125 | $296.00 | $310.80 |
| 123 | Surface preparation using hydrodemolition (848E20000) | SY | 125 | $546.06 | $575.00 |
| 124 | Superplasticized dense concrete overlay (variable thickness), material only (848E30200) | CY | 2 | $452.00 | $475.00 |
| 125 | Hand chipping (848E50000) | SY | 19 | $198.87 | $210.00 |
| 126 | Test slab (848E50100) | LS | 1 | $1,584.00 | $1,665.00 |
| 127 | Full-depth repair (848E50200) | CY | 6 | $1,845.00 | $1,937.25 |
| 128 | Deep beam bridge retrofit railing, as per plan (517E75601) | FT | 184 | $112.00 | $118.00 |
| 129 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,750.00 | $4,320.00 |
| 130 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,000 | $30,000 |
| 131 | Maintaining traffic (614E11000) | LS | 1 | $330,000 | $325,000 |
| 132 | Field office, type B (619E16010) | MNTH | 7 | $3,900.00 | $2,800.00 |
| 133 | Construction layout stakes and surveying (623E10000) | LS | 1 | $33,435 | $25,000 |
| 134 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $10,000 | $9,500.00 |
| 135 | Mobilization (624E10000) | LS | 1 | $100,000 | $250,000 |
| 200 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 214 | $265.00 | $280.00 |
| 201 | Edge line, 6" (646E10010) | MI | 0.08 | $16,200 | $8,400.00 |
| 202 | Ground rod (625E32000) | EACH | 10 | $265.00 | $280.00 |
| 203 | Pedestal, misc.:' reuse of pedestrian pedestal (632E90010) | EACH | 6 | $1,825.00 | $1,920.00 |
| 204 | Reuse of pedestrian pushbutton, as per plan (632E90211) | EACH | 8 | $400.00 | $420.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.